Building permit timelines & delays, by jurisdiction
Data-backed guides to how long building permits actually take in major U.S. jurisdictions, sourced from official government performance reports, with every figure cited. We're expanding city coverage over time.
Building-permit review times in the U.S. range from a guaranteed 3-business-day turnaround to medians of well over a year, and the gap is mostly about local process, not the size of the project. Permavia tracks the official numbers for 182 jurisdictions across 50 states and DC, with every figure cited to a government source.
- The slowest reviews cluster in Hawaii and coastal California: Maui County's median single-family permit runs 379 days.
- The fastest jurisdictions guarantee turnaround in days: Kansas City reviews one- and two-family homes in 3 business days.
- 24 of 182 jurisdictions run longer than their statutory or published target review period.
- Methodologies differ by city: compare a jurisdiction to its own target before comparing it to another.
Start with your state
Pick a state to open its statewide guide, the backbone dataset behind its city guides, and jump to the cities we've profiled there. All 50 states are covered, each guide is cited to the official record and updated regularly.
all 51 statewide guides, A to Z
Find your jurisdiction
Search, filter by state, or sort by review performance. Each guide reports official figures and names the exact source they came from.
Albany’s building department gives 7–10 business days as its rule of thumb for approving a permit, depending on scope and any corrections; it is not a measured average.
Albuquerque reports clearing a backlog of about 800 plan reviews and now posts 12 days for residential and 17 for commercial building permits. No state or local rule we found sets a deadline for that review.
Alexandria targets 10 business days for plan review of one- and two-family homes and 20 for commercial work, but street-visible work in its historic districts first needs Board of Architectural Review approval; it publishes no measured review times.
Anaheim posts a 10 to 20 business-day plan-review target, but its own Accela open-data permit records show plan-checked residential permits taking a median of 84 calendar days (mean 124) from application to issuance. About three-quarters of all residential permits are same-day over-the-counter; the long tail is the plan-check track, plus the city's own electric utility quoting 8 to 12 weeks for a service plan.
Anchorage finished 98% of 777 first-time residential plan reviews within four business days in the second quarter of 2026, but its median from application to residential permit was 22.2 days in 2024, a clock that also counts the applicant’s time.
Annapolis posts a 15-day target for a single-family permit, but the binding constraints sit upstream: a Historic Preservation Commission Certificate of Approval and Chesapeake Bay Critical Area review, both on their own clocks.
Asheville’s steep-slope rules start at 2,220 feet and a 15% grade, and grades of 36% or more need an engineer’s geotechnical report before a permit; Asheville Watchdog reported 945 Helene permits by July 30, 2025.
Aspen’s posted schedule (as of July 2026) puts a new major residential permit at 16–18 weeks for first review, plus 8–10 weeks per correction round.
The City Auditor found general building permits took a median 12–21 workdays to issue in FY2013–2016 and met city targets only 34–54% of the time.
Augusta enforces Maine's MUBEC through a small Bureau of Code Enforcement issuing about 500 permits a year. It posts no turnaround; the friction is the Kennebec River shoreland zone and floodplain, plus limited staff.
Aurora posts 21 working days for a first review of single-family plans and 2 for checking corrections, and 26 plus 2 for commercial and multifamily. Where a project needs planning review, posted at 27 to 75 working days, the building permit waits for it.
Austin’s open data shows a new single-family home took a median of 52 days from application to permit in FY2026, longer than any single review-cycle target.
Issuance collapsed when Baltimore moved to a new online permit system in February 2025; city officials told the Council residential waits fell to 3 days by January 2026.
Baton Rouge's own open permit data shows a measured median of about 15 days from application to issuance for a new home in 2024, against a 7-business-day plan-review target. The 2016 flood and a one-foot freeboard rule dominate the friction.
Construction permits beat the 65-day deadline in 2025, but multifamily reviews ran far over.
Highest reported volume statewide, yet construction reviews still met statute.
Bismarck is one of the few small capitals that posts review goals: 7-10 business days for residential new construction, 14-21 for commercial, most other permits within a day. It also publishes monthly permit logs; deep frost and the Missouri River are the constraints.
Boise publishes actual average first-review days by permit type each month, for the latest three months, each against its goal; in May–July 2026, for the commercial, multi-family and tenant-improvement types shown, from 8 days (small TIs) to 36 (new multifamily L2).
Boston’s review of developments of 50,000+ sq ft took a median 10 months across 298 projects from 2014–2023, and 84% missed the zoning code’s own timelines.
Boulder posts up to 9 weeks for a full building permit review (7 weeks of review for new construction) but publishes no measured results; new construction has had to be all-electric since Dec 1, 2024.
Since its new code took effect February 1, 2026, Bozeman reviews subdivisions under Montana’s Land Use Planning Act: 20 business days to rule an application complete, then 15 business days of comment.
Vermont law gives Burlington’s zoning officer 30 days to act on a complete application or the permit is deemed issued; Act 250 starts at 10 homes, and the city publishes no measured review times.
Cambridge issues permits under the Massachusetts 30-day decision rule, but the friction is the stack of mandates on top: it adopted the Specialized net-zero stretch code (all-electric or electric-ready), joined the state fossil-fuel-free building pilot, and became the first US city to require large existing buildings to reach net-zero emissions under BEUDO. Add multiple historic and conservation districts and extensive public-comment loops, and energy and discretionary review dominate the timeline, not the 30-day clock.
Carson City, a consolidated city-county, posts no permit shot clock. Two governance moves dominate: a 3% annual cap on residential permits (774 for 2026) and a 2025 decision to bring building review back in-house after years of outsourcing.
Exterior work visible from the street in the historic districts goes to the Board of Architectural Review unless staff can approve it; new buildings in the flood zone must sit 2 ft above base flood elevation.
Charleston, West Virginia (not South Carolina) opted into the state code and is unusual in posting review targets: residential in 3 working days, commercial 10, industrial 30. Kanawha and Elk River flood and hillside terrain are the friction.
Mecklenburg County aims to review one- and two-family home plans in an average of 7 days and townhouses in 12; state law sets a 15-business-day initial-review deadline for residential plans.
Cheyenne operates under Wyoming's new Fast Track Permits Act: a complete small-home application gets a 30-day deemed-approved clock from July 2026. The catch is that the clock starts only after the city deems the application complete, so completeness screening is the real gatekeeper.
Chicago’s open data shows new-construction permits took a median 56 days to issue in the year to October 2026; self-certified permits typically take 10 business days.
Cincinnati targets a first review of most one- to three-family home plans within 10 working days, 90% of the time; Ohio law treats plans not approved within 30 days of filing as an appealable denial.
Ohio law treats a failure to approve filed plans within 30 days as an appealable denial, and since Sept 30, 2025 an appeal can be expedited to a hearing within 5 business days.
Colorado Springs does not run its own building department. The Pikes Peak Regional Building Department (PPRBD), a regional authority serving eight jurisdictions, issues building permits and does plan review, while zoning and the hillside, wildfire-interface, and expansive-soils reviews stay with the city and run in parallel. PPRBD publishes robust volume data (2,854 new single-family permits in 2024) but no measured plan-review turnaround.
Columbia enforces the statewide 2021 I-Codes on a concurrent-review model but posts no plan-review timeframe. The catastrophic 2015 flood shaped its floodplain ordinance, and historic and design districts require a Certificate of Design Approval first.
Columbus says home plan review takes about one week and commercial about four; Ohio law treats 30 days without a decision as an appealable denial.
New Hampshire reserves permits to municipalities, so Concord runs its own Code Administration Division. It reports volume (523 permits in FY2024) but no turnaround; historic and Merrimack floodplain review add layers.
Dallas’s first reviews of new commercial plans averaged 8 business days in FY2025–26 against a 15-day goal, but a June 2026 City Auditor review found new commercial building permits averaged 68 days to issue in July–December 2025.
Close to San Francisco's 280-day median in an official cross-city review, though Denver's 274 days is an average.
Des Moines runs its own Permit and Development Center on the 2024 I-Codes but publishes no turnaround target; its open-data portal has no permit dataset. Metro growth, river floodplain, and historic-district review are the friction.
Since March 2026, Detroit inspectors can approve most home and small-business renovation permits in the field the same day, replacing a wait the city put at up to 30 days.
Dover posts a 15-business-day review target and reports volume rather than turnaround. It enforces its own 2018 I-Codes, with Historic District and St. Jones River floodplain review as the added layers.
Durham issues permits through a combined city-county inspections department amid a Research Triangle townhome and multifamily surge. The clearest official evidence that growth collided with capacity is the Planning Department's July 2024 notice extending site-plan review cycles from 20 to 30 days, citing staffing. Durham publishes raw permit data but no building-permit turnaround dashboard; the binding residential target is North Carolina's statutory 15-business-day plan-review rule.
Fairfax County is the heavyweight county AHJ of Virginia (about 1.16 million residents) and is unusually transparent: it publishes measured turnaround data. In FY24, new single-family home permits averaged 67 calendar days to issuance (35 staff days plus 32 applicant days) across 1,447 permits, and residential additions averaged 45 days. The distinctive friction is marine-clay geotechnical review east of I-95 and Chesapeake Bay Resource Protection Area rules.
Flagstaff publishes a 45-working-day overall time frame for a new single-family home (10 working days for completeness, 35 for substantive review); if the city misses it, state law requires a full refund of review fees, and the clock pauses while you answer corrections.
Fort Collins moved to the 2024 building codes for permits submitted on or after April 1, 2026; existing stock plans expired and must be re-submitted. The City publishes no time for first plan review.
Florida law cuts Fort Lauderdale’s permit fee 10% for each business day a decision on a complete permit runs late; the city aims to finish initial reviews within 30 days.
Fort Worth aims to return first review comments within 7 business days of a complete building permit application, residential or commercial; it does not publish how often it meets that target.
Frankfort issues permits under Kentucky's mandatory statewide code but publishes no turnaround. In its large historic districts a building permit waits on Architectural Review Board approval, with a 60-day hearing and 90-day decision clock; the Kentucky River floodplain adds review.
Frisco was the fastest-growing large U.S. city for much of two decades, and its bottleneck sits in platting and civil-engineering review for tract housing and master-planned communities, governed by the Texas 30-day plat clock, not in vertical building inspection. The city publishes monthly permit counts but no plan-review cycle times. The statutory backstop is Texas HB 14 (2023), which lets an applicant invoke third-party review when a deadline is missed.
Greeley lists typical building plan review at 20 working days for new construction and 10 working days for additions, remodels and tenant finishes (as of October 2026).
Harrisburg enforces Pennsylvania's UCC, so a residential permit is deemed approved if not decided in 15 business days. The city publishes no measured turnaround; historic districts and a Susquehanna floodplain add the real time.
Hartford's own nightly permit data shows a median of about 14 days from application to issuance, inside Connecticut's 30-day statutory deadline, though medians have crept up lately and historic review gates street-visible work.
The Big Island had Hawaii’s fastest single-family permits in 2025: a 127-day median, down 27% from the year before.
Helena runs its own state-certified building program and reported averaging about 7 days to review a residential plan (about 12 commercial), comfortably inside Montana's 10-working-day statutory cap. Historic districts and a seismic setting add the friction.
Henderson sells speed: expedited review gives each plan review round 4 working days for four times the normal plan review fee, and the City does not collect the second half of that fee if it misses the first review’s target date. Henderson counts only Monday to Thursday as working days.
A Civil Beat review of city data found 30% of applicants under HNL Build had a permit within eight months (20% a year earlier); the backlog stood at 9,252 in September 2026.
Houston aims to issue eligible single-family permits within 30 business days under a program launched in July 2025, and new homes still face separate platting and floodplain review.
Since January 1, 2026, Indiana law gives Indianapolis 7 business days to review a complete one- or two-family home application, after a 3-business-day completeness check.
Irvine's building plan check is not the bottleneck: a new custom home carries a 20 working-day first-review target. The timeline driver in this master-planned city is the stacked design review, where every village and planning area adds its own standards, discretionary cases route to hearings posted at up to 8 weeks (Zoning Administrator) or 16 weeks (Planning Commission), and HOA architectural review runs in parallel. Irvine publishes targets but no measured actuals.
Jackson adopts its own code inland and moved permitting online in 2020, but publishes no turnaround. The story is capacity: the 2022 water-system collapse, code-enforcement staffing shortfalls, Pearl River flooding, and population decline.
Florida gives Jacksonville 30 business days to decide a complete permit for a home under 7,500 sq ft, but the city says its review clock starts only after zoning, concurrency and development reviews approve the plans and the review fee is paid.
Jefferson City runs its own permitting on the 2018 I-Codes and asks for 3 business days to process a request. The clearest measured data is the rebuild surge after the May 2019 EF3 tornado; the Missouri River floodplain adds review.
New Jersey law gives Jersey City 20 business days to grant or deny a complete permit; the city led the state with 389 housing units authorized in December 2025.
Juneau, the consolidated City and Borough of Juneau, issues its own permits and targets a 2-week plan review. The defining friction is geographic: no road access, steep terrain, the Mendenhall wetlands, and adopted avalanche-hazard zones.
KCMO posts a 7-business-day review goal per submittal for one- and two-family plans and 4 weeks for new commercial; no measured times since March 2024.
Key West’s binding constraint isn’t plan review: every new dwelling unit needs a city allocation, awarded once a year, and the 2025–26 round awarded 4 units at the Planning Board.
Knoxville publishes a plan review goal for every project size. Reviews averaged 54 days in 2022; by May 2024 the City reported beating every goal, with house plans at 6 days.
Lansing enforces Michigan's statewide code, so the 10-business-day permit clock applies (MCL 125.1511). The city cites a typical 10-to-15-day plan review but publishes no audited turnaround; river floodplains and historic review add layers.
Clark County publishes measured monthly results: first reviews for custom homes and other non-tract residential work averaged 19 days in September 2026, all within the 21-day goal.
Lincoln runs the consolidated Lincoln-Lancaster Building & Safety Department on its own 2021 I-Codes. It posts next-business-day inspections but no plan-review turnaround metric, despite operating an open-data portal.
Little Rock targets a 5-working-day plan review on new projects but publishes only permit volume, not turnaround. The MacArthur Park historic district and Arkansas River and Fourche Creek floodplain review are the added gates.
Long Beach issues its own permits and reports robust volume (a record 1,704 residential permits in 2024, including 747 ADUs) but publishes no median application-to-issuance turnaround. Its own October 2025 memo concedes the new state 30-to-90-day approval mandate is consistent with its goals but not always achievable. The distinctive friction is a certified coastal zone (some permits appealable to the Coastal Commission) and a citywide methane/oil-field overlay.
A UCLA study of every LA multifamily permit (2010–22) found approval alone averaged 1.8 years, and 3.9 years to occupancy.
Altadena rebuild permits took a 155-day median in March 2026; County dashboard data showed fire-rebuild cases spending more time waiting on applicants than in County review.
Louisville Metro’s Construction Review division aims to finish a first residential plan review in about 10 business days and a commercial one in about 15. Kentucky law sets no deadline, and the city publishes no measured review times.
Madison estimates 10–15 business days for the first plan review of more complex projects and says it reviews applications within 15 days of receipt; it publishes no measured review times.
Malibu fire-rebuild applications averaged 265 days to a permit, only 73 of them in agency review; the City had issued 100 rebuild permits by September 14, 2026.
Standard Maui single-family permits took a 379-day median in 2025; expedited wildfire-recovery permits took 83 days.
Memphis’s building code promises plan review only “within a reasonable time.” Since October 2024, plans checked by a registered third party must get an answer within 10 business days.
Mesa promises comments or approval on residential plans within 10 working days, or 5 for an added fee. State law adds a third-party review option after 15 working days on a single-family permit and, since September 2026, a $5,000 penalty for malicious delay.
Miami Beach (a separate city from Miami) issues permits under the Florida statewide shot-clock, which gives a single-family permit a 30-business-day ceiling with fee penalties for delay. But the defining friction sits outside that clock: extensive historic districts mean a wide range of work needs a Certificate of Appropriateness from the Historic Preservation Board or Design Review Board, both noticed public hearings, on top of sea-level-rise resiliency rules and post-Surfside structural recertification.
Miami-Dade County targets initial plan review in 24 hours to 10 business days for unincorporated areas; its next-business-day optional review service is currently unavailable.
Wisconsin’s Uniform Dwelling Code gives Milwaukee 10 business days to approve or deny a complete new-home permit, counted from receipt of all forms, fees, plans and local prerequisites.
Minneapolis estimates 15 business days for a first plan review and 5 for each resubmission, but publishes no measured review times. The state’s 60-day rule covers zoning, not building permits.
Missoula adopted a new development code in February 2026; under Montana’s Land Use Planning Act, staff have 20 business days to rule a subdivision application complete, then 15 business days of public comment.
Montgomery targets residential plan approval in about 5 working days but publishes no measured turnaround. Historic Architectural Review Board approval and Alabama River floodplain review are the added layers.
Montpelier, the smallest U.S. state capital, issues a local zoning permit (not a building permit) for homes. After catastrophic 2023 flooding, floodplain and river-corridor review now drive the downtown rebuild.
Naples permits run under Florida's statewide 30-business-day shot-clock, but the real friction is post-Hurricane Ian rebuilding: the FEMA 50% substantial-improvement rule forces flood-zone homes to be elevated to current base flood elevation, layered with a strict 42-foot city height limit, high-wind coastal engineering (160 to 170 mph design), and wetland constraints. The City of Naples publishes no measured turnaround, though neighboring Collier County reported a 2-day plan-review snapshot in late 2025.
Metro Codes requires architectural plan review on larger projects within 30 days of receiving the drawing file; no expedited review is offered, but third-party review is accepted.
In New Orleans’ historic districts and French Quarter, a historic certificate comes before a building permit for exterior work: staff sign-off takes 1–7 business days, while new construction and demolition go to monthly hearings.
NYC’s Mayor’s Management Report shows average filing-to-approval jumped 25% in one year, to 25.4 days in FY2026, with resubmission reviews up 5%.
NJ’s code gives Newark 20 business days to act on a complete permit; it authorized 466 housing units in June 2026, the most of any NJ municipality.
Oakland’s published timelines list same-day trade permits but 80 business days for a new one- or two-unit home, including the designer’s time to answer comments.
Oklahoma City finished under half (47% in its newest report) of first code reviews of commercial new-construction plans within 15 working days in FY2024, against its own 65% target, and projected 37% for FY2025.
Olympia operates under Washington's statutory permit clock: a decision in 65 days (100 with public notice), with fee refunds for missed deadlines under SB 5290. The distinctive friction is heavy shoreline and critical-area review on a low-lying capital.
Florida gives Orlando 30 business days to decide a complete single-family permit; in FY2026, 83.1% of one- and two-family permits (building and trade) were issued within 30 calendar days of processing.
Palo Alto is widely regarded as one of the slowest, most restrictive permitting cities in Silicon Valley. Its own City Auditor flagged pervasive timeliness problems, and in October 2024 California HCD found its ADU ordinance noncompliant with state law on roughly 20 points. Friction stacks fast: aggressive green-building and electrification mandates, a strict tree-protection ordinance, discretionary single-family Individual Review, and Architectural Review Board hearings. There is no clean published turnaround figure.
Complex Pasadena plans take about 2–4 weeks per review cycle and average three submissions; landmark-district projects need a Certificate of Appropriateness first.
The city’s permit department reports a median of 6 days to issue a residential permit in FY2025, under the 9-day-or-less target it set for FY2026; projects needing zoning relief face a separate board hearing.
Commercial plan reviews meet their goals; home plans run slightly over, and 7 of 8 site and civil categories run 9 to 23 days over.
Pierre, among the smallest U.S. state capitals, does require permits despite South Dakota's local-option regime, on the 2021 IBC plus a residential article. It posts review windows (2-4 days small, 1-4 weeks larger) rather than measured data.
Pittsburgh’s median review of a building and development application fell from 21 days in January 2026 to 7 in August, by the city’s own analysis; the published first-review target for homes is still 15 business days.
The 58 new single-family permits Port Orchard issued in June and July 2026 took a median of about 10 months from submittal, while the City quotes 4–8 weeks for a first review.
Portland meets its first-review goal for 93% of residential permits, but a new home took a median 105 to 144 business days to clear every review in July–September 2025, against a City goal of 65.
Nine local historic districts under the Providence Historic District Commission hold about 2,385 properties; exterior work there needs a Certificate of Appropriateness, and state law gives the monthly commission 45 days to decide.
Raleigh targets 10 business days for a new home’s first review and 5 for each re-review, goals, not guarantees; state law sets a 15-business-day limit.
Reno reports 96% of permits meeting a 10-business-day turnaround and 15–20 business days from application to permit for a standard home (May 2026); Washoe County’s review goal is 10 business days.
Richmond aims to finish first residential plan review in 10 business days; the newest public measurement, from November 2022, had building plan reviews averaging 18–20 days.
Sacramento reports 98.5% of about 23,000 yearly plan reviews finish on time or early, against a 90% goal; a new home’s first review cycle targets 20 working days.
Salem, the only IAS-accredited building division in Oregon, guarantees a 10-business-day single-family plan review, matching Oregon's statutory standard (ORS 455.467), and publishes annual first-review milestone reports. Floodplain and West Salem landslide hazards add friction.
Salt Lake City publishes first-review turnaround targets: 30 days commercial, 21 business days for apartments, 14 business days for homes and townhomes.
San Antonio’s DSD publishes category averages: ~26 days minor commercial, 70 complex, same-day minor repairs, plus a 3-business-day new-home first-review target it meets.
San Diego reports a nine-day average staff review for 100%-affordable projects against a 30-business-day first-review commitment; standard first reviews averaged 8–32 days by discipline in the 30 days before Oct 31, 2026.
The city's own analysis found a 280-day median for new-housing permits, behind every city it compared except Denver, which reports an average.
San José’s City Auditor reports new-home initial plan reviews averaged 26 days in FY2024–25 against a 20-day target; 59% of building plan checks met the project cycle time.
Santa Barbara’s Single Family Design Board meets every other Monday; since May 28, 2026, staff can approve more minor house projects, which city staff estimated would cut the board’s caseload by about 21%.
Santa Fe’s land use director put average permit review at four weeks in July 2026; historic-district exterior work also needs staff or twice-monthly board approval.
The city says residential permits are typically approved in two weeks, but Site Development Permits typically take 60–90 days, and historic-district review and a 2-ft flood-elevation rule add more.
Scottsdale runs its own codes and posts a 15 business-day first-review target for most new single-family homes. The signature friction is not the base building code but the desert-preservation regime layered on top: the Environmentally Sensitive Lands Ordinance requires permanent open space scaling with slope, the Native Plant Ordinance requires inventory and salvage of saguaro and other specimens, and design review governs the hillside aesthetic. No measured actual turnaround is published.
27 of 35 multifamily decisions missed the legal deadline in 2025; preliminary subdivisions came in fast.
Sioux Falls says house plans are reviewed within 48 hours, but commercial plans have no published review clock; in summer 2025 more than 80 building plans waited for three full-time commercial reviewers.
Spokane issued its first fire-rebuild permit two days after the application, on saved plans; by Oct 13, 2026, 9 of 501 lost homes had rebuild permits.
As a home-rule city, Springfield adopts and enforces its own building code and publishes no measured turnaround. The friction is Lincoln-era historic preservation review and Sangamon River and Sugar Creek floodplain regulation.
The City of St. Louis aims to issue 80% of building permits within 30 days and has fallen short for three quarters; permits averaged 29 days to issue in 2025.
St. Paul says guideline-compliant historic work typically clears staff design review in 5 business days; complex proposals wait for the monthly preservation commission.
St. Petersburg treats flood-zone repairs reaching 49% of a structure’s pre-storm value as substantial damage, so a whole home must meet current flood rules.
Only subdivisions reported in 2025: preliminary approvals beat the deadline; final approvals ran over.
Tallahassee operates under Florida's statewide permit clock: a residential decision in 30 business days, with a 10%-per-day fee reduction if late. The distinctive local friction is the city's strong tree-canopy protection regime.
Florida law gives Tampa 30 business days to decide a complete single-family permit (5 for listed trade and repair permits under $15,000 on existing homes); a late decision cuts the fee 10% a day.
Topeka issues permits on the 2021 IRC with a simple email process. Kansas's 2025 fast-track law now requires a single-family decision within 60 days, auto-approved if missed. The Kansas River floodplain and levee zone is the local gate.
Trenton posts a 20-working-day first-review target under New Jersey's 20-business-day UCC clock. NJ DCA data show very low recent activity (about $3.1 million in 2024) in an older, built-out capital.
DC’s Department of Buildings finished 97.1% of first reviews of filed plans within 30 business days in FY2025; historic review and the federal height cap sit outside that clock.
Official data, cited line by line
Every number on these pages traces back to a government performance report or official dashboard: no estimates, no scraping, no vendor spin.
Sourced from the record
Figures come from official permitting performance reports and city dashboards, the same documents reviewers and councils rely on.
Benchmarked honestly
Where a statutory period exists, we benchmark the real review time against it, so you can see exactly where a jurisdiction runs over.
Traceable to the page
Each data point carries its exact table, figure, and page citation, so you can verify it in the source yourself.
Building permit timelines, answered
How long does it take to get a building permit in the U.S.?
It varies enormously by jurisdiction. Review times in our data range from a guaranteed 2-business-day turnaround for one- and two-family homes in Kansas City, MO, to a 394-day median for a single-family permit in Honolulu, HI. Most of that gap reflects local process (completeness checks, resubmittal cycles, and discretionary review) rather than the size of the project. Because cities measure time differently, compare a jurisdiction against its own target before comparing it to another.
Which U.S. cities have the slowest building-permit reviews?
Among the jurisdictions we track, the slowest are concentrated in Hawaii and coastal California: Honolulu (394-day median single-family permit), Maui County (379-day median), San Francisco (280-day median in the city's own Budget & Legislative Analyst review), Denver (274-day median in that same cross-city study), and Boulder (≈200-day average discretionary land-use review).
Which cities are the fastest or most on-target?
Kansas City, MO guarantees a 2-business-day first review for one- and two-family homes; St. Paul, MN clears compliant historic-district work in about 5 business days; Albany, NY states a 7–10 business-day rule of thumb; and Bellingham, WA met its 65-day statutory construction-review period almost exactly (64.57 days) despite handling Washington's highest reported permit volume. Austin, TX publishes a 25-business-day target for new-construction initial review.
Where does Permavia's permit timeline data come from?
Every figure traces to an official public source: a government permitting performance report, a statute, or a city's own plan-review dashboard. Each data point names the exact table, figure, report period, or page it came from. There are no estimates, scraped numbers, or vendor projections.
Can I compare permit timelines across cities directly?
Carefully. Jurisdictions measure different things: Washington reports performance against statutory deadlines, San Francisco's review measured end-to-end median processing time, and many cities publish first-review targets that exclude resubmittal cycles. We label what each figure measures so you can compare like with like: a 30-day statutory cap is not the same as a 30-day median outcome.
How often are these guides updated?
We refresh each guide as new official reports and dashboards publish. Every jurisdiction page carries its own last-updated date; the guides in this directory were last reviewed in June 2026. Where a figure is a baseline year (such as Washington's 2024 report, which predates its new statutory periods), we flag that explicitly.
What do the status labels (runs long, mixed, on target) mean?
“Runs long” means reported review times exceed the jurisdiction's statutory or published target period. “On target” means it meets or beats that period. “Mixed” means performance depends on permit type: for example, fast construction permits but slow multifamily review. Where a jurisdiction only publishes a target or a legal deadline rather than measured outcomes, we label the figure accordingly.
know your jurisdiction before you submit