New York City Building Permit Timelines & Delays

Getting building plans approved in New York City took 25.4 days on average in the city’s 2026 fiscal year (July 2025–June 2026), up 25% in a single year and up from 14.7 days in FY2022. The city says most of that time passes while plans sit with the applicant for corrections, so every round of objections and resubmission adds days (NYC Mayor’s Management Report, FY2026).

Last reviewed November 1, 2026
headline figure
25.4 d avg. DOB NOW filing-to-approval (FY2026)
what to know
NYC’s Mayor’s Management Report shows average filing-to-approval jumped 25% in one year, to 25.4 days in FY2026, with resubmission reviews up 5%.
data source
Mayor’s Management Report: Department of Buildings
by the numbers

New York City permitting, the figures

The key published figures for this jurisdiction — each cited to its official source.

25.4 days
Avg. filing-to-approval (DOB NOW)
FY2026, all applications; up from 20.3 in FY2025 and 14.7 in FY2022
Source: Mayor’s Management Report: Department of Buildings — NYC Mayor’s Management Report, FY2026
5.4 days
Avg. first plan review: all applications
DOB NOW, FY2026; up from 3.7 in FY2025
Source: Mayor’s Management Report: Department of Buildings — NYC Mayor’s Management Report, FY2026
9.4 days
Avg. first plan review: new buildings
DOB NOW, FY2026; up from 6.3 in FY2025
Source: Mayor’s Management Report: Department of Buildings — NYC Mayor’s Management Report, FY2026
~3×
Time with applicant vs. with DOB
DOB: applicant correction time is typically three times Department review time
Source: Mayor’s Management Report: Department of Buildings — NYC Mayor’s Management Report, FY2026
111,842
Resubmission plan reviews completed
DOB NOW, FY2026; up 5% from 106,759 in FY2025
Source: Mayor’s Management Report: Department of Buildings — NYC Mayor’s Management Report, FY2026
103,865
Jobs professionally certified
FY2026; 5,954 audited before approval, 24.7% audited after approval
Source: Mayor’s Management Report: Department of Buildings — NYC Mayor’s Management Report, FY2026
265,012
Jobs filed in DOB NOW
All applications, FY2026; up from 259,086 in FY2025
Source: Mayor’s Management Report: Department of Buildings — NYC Mayor’s Management Report, FY2026
analysis

What the data shows

  • The average time from filing to approval in DOB NOW rose to 25.4 days in FY2026 from 20.3 days in FY2025, a 25% jump, after holding near 20 days in FY2024 and FY2025 (NYC Mayor’s Management Report, FY2026).

  • The city attributes most elapsed time to the applicant, stating that time with the applicant is typically three times as long as the time the filing is with the Department, and that rising resubmission volume (111,842 reviews in FY2026, up 5%) contributes to the longer average (NYC Mayor’s Management Report, FY2026).

  • The Department’s own first review also slowed in FY2026: 5.4 days across all DOB NOW applications (from 3.7), 9.4 days for new buildings (from 6.3) and 8.4 days for major renovations (from 6.0) (NYC Mayor’s Management Report, FY2026).

  • 103,865 jobs were professionally certified in FY2026, skipping Department plan examination; the Department audited 5,954 of them before approval and 24.7% after approval (NYC Mayor’s Management Report, FY2026).

how Permavia helps in new york city

Most delay accumulates before technical review

The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.

frequently asked

New York City permitting: FAQ

How long does it take to get plans approved for a building permit in NYC?

For jobs filed in DOB NOW, the Department of Buildings’ online filing system, the average time from filing to approval was 25.4 days in FY2026 (July 2025–June 2026), up from 20.3 days in FY2025 (NYC Mayor’s Management Report, FY2026). The report counts approvals separately from work permits issued, and the average combines all application types; the city says most of the clock is time the applicant spends correcting plans, not Department review time.

Why do permits take longer than the official review time suggests?

First plan review averaged 5.4 days across all DOB NOW applications in FY2026, and 9.4 days for new buildings (NYC Mayor’s Management Report, FY2026). Most of the rest is correction cycles: the city says time with the applicant is typically three times as long as time with the Department, and it completed 111,842 resubmission plan reviews in FY2026, up 5%, which it says contributes to the longer average.

What is professional certification and how common is it?

Professional certification lets a Professional Engineer or Registered Architect certify that the plans they file meet applicable requirements, eliminating Department plan examination and approval; it must be selected at pre-filing (NYC DOB, Professional Certification). It is heavily used: 103,865 jobs were professionally certified in FY2026, and the Department audited 5,954 before approval and 24.7% after approval (NYC Mayor’s Management Report, FY2026).

Are NYC permit timelines getting better or worse?

Worse. Average filing-to-approval in DOB NOW went from 14.7 days in FY2022 to 18.1 in FY2023, 20.2 in FY2024, 20.3 in FY2025 and 25.4 in FY2026 (NYC Mayor’s Management Report, FY2026). A June 2026 review by the New York State Comptroller’s office found the Department’s full-time staff at 1,571 in June 2025, 7.8% below its March 2020 peak, though it did not measure how staffing affects plan review times (Office of the State Comptroller, Report 5-2027).

Sources

All figures on this page are drawn from Mayor’s Management Report: Department of Buildings, NYC Mayor’s Office of Operations / Department of Buildings. The city’s official annual performance report on DOB NOW plan-review and permit metrics; FY2026 (July 2025–June 2026) average filing-to-approval was 25.4 days. www.nyc.gov/assets/operations/downloads/pdf/mmr2026/dob.pdf. Specific tables, reports, and pages are cited inline with each figure above.

All Department of Buildings timeline figures are city fiscal-year averages (July–June) from the Mayor’s Management Report and combine every application type filed in DOB NOW, so they do not show how long a specific large multifamily new building takes. First plan review counts only the days until the Department completes its first examination, not the full filing-to-approval clock.