Hawaii County (Big Island) Building Permit Timelines
A single-family building permit on the Big Island took a median of 127 days in 2025, the fastest of Hawaii’s four counties and 27% quicker than the year before, according to the University of Hawaiʻi Economic Research Organization (UHERO). That is still about four months from application to permit, and the other counties run longer: Maui 186 days, Kauai 309 and Honolulu 394 (first half of 2025) (UHERO Housing Factbook, 2026).
Hawaii County permitting, the figures
The key published figures for this jurisdiction — each cited to its official source.
What the data shows
Hawaii County recorded the state’s fastest single-family permit processing for permits issued in 2025, a median of 127 days, down 27% from the year before (UHERO Housing Factbook, 2026).
Permits in the county’s EPIC system averaged about 115 days from application upload to issuance between July 2021 and March 2024, a measure that includes time with the applicant (Hawaii County Auditor, 2025).
Over that audit window the county received 15,575 EPIC applications and issued 11,134 permits, with an average of 16 applications submitted a day against 12 processed, leaving a backlog that generally trended upward (Hawaii County Auditor, 2025).
The county reported that average review and approval time for new residential construction fell 69%, from more than six months to about two months, between the first halves of 2024 and 2025 (Big Island Now, 2025).
Most delay accumulates before technical review
The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.
Hawaii County permitting: FAQ
How long does a residential building permit take in Hawaii County?
UHERO reports a median of 127 days for single-family permits issued in 2025 (UHERO Housing Factbook, 2026). The county reported that new residential construction averaged about two months for review and approval in the first half of 2025 (Big Island Now, 2025), and county staff told a state House permitting task force in September 2025 that residential permits “can now be approved in about 45 calendar days” (SPEED Task Force minutes, 2025). The Building Division’s goal is 60 calendar days from a complete submittal; we found no public report of how often it is met.
Is Hawaii County faster or slower than the rest of Hawaii?
It is the fastest county in the state for single-family permits: a 127-day median in 2025, versus 186 days in Maui County, 309 on Kauai, and 394 in Honolulu, where UHERO could only measure permits issued in the first half of 2025 (UHERO Housing Factbook, 2026). About half of Maui’s 2025 single-family permits were wildfire-recovery disaster permits, which cleared in a median of 83 days, so the county figures are not like-for-like.
What is the EPIC permitting system?
EPIC (Electronic Processing and Information Center) is Hawaii County’s online permit system, used for building permits since July 2021. Applicants submit plans electronically, multiple approving agencies can review them concurrently (Hawaii County Auditor, 2025), and applicants can follow a permit’s workflow, pay invoices and request inspections online (County of Hawaii DPW).
Is there a permit backlog on the Big Island?
The county’s 2025 audit found that from July 2021 to March 2024 an average of 16 applications arrived each day while staff processed 12, and the cumulative backlog generally trended upward; it received 15,575 applications and issued 11,134 permits in that time (Hawaii County Auditor, 2025). The audit recommended exempting more low-risk work and a self-certification program for licensed design professionals; these are recommendations, not adopted rules. In August 2025 the county said the backlog had been “significantly reduced” but gave no count (Big Island Now, 2025).
Sources
All figures on this page are drawn from The Hawaii Housing Factbook (2026), UHERO, University of Hawaiʻi Economic Research Organization. Annual, county-by-county analysis of building-permit processing times and housing-supply constraints; supplemented by Hawaii DBEDT's 2025 study on the cost of permit delays in Honolulu. uhero.hawaii.edu/the-hawaii-housing-factbook-2026/. Specific tables, reports, and pages are cited inline with each figure above.
Figures come from three methods and periods. UHERO’s 127-day figure is a median for single-family permits issued in 2025. The County Auditor’s 115-day figure is an average from application upload to issuance for EPIC permits, July 2021–March 2024, and includes time with the applicant. The first-half 2025 figures are averages the county reported through local news, without a published method. These are measured results; the 60-day residential goal is a target, and we found no public report tracking performance against it. The numbers are not directly comparable with each other or with other jurisdictions’ figures.