jurisdiction guide · utah

Salt Lake City Building Permit Review Times

Salt Lake City aims to return first-review comments within 30 days on commercial projects, 21 business days on apartment projects and 14 business days on one- or two-family homes and townhomes. That puts a commercial first review at about a month and a small home at under three weeks, before any corrections.

Last reviewed October 28, 2026
headline figure
30 d commercial first-review target (apartments 21 business days, homes 14)
what to know
Salt Lake City publishes first-review turnaround targets: 30 days commercial, 21 business days for apartments, 14 business days for homes and townhomes.
data source
Building Services: Permitting Process (plan-review turnaround targets)
by the numbers

Salt Lake City permitting, the figures

The key published figures for this jurisdiction — each cited to its official source.

30 days
Commercial plan review, first review
target to return first-review comments
Source: Building Services: Permitting Process (plan-review turnaround targets) — Permitting Process: first-review targets
21 business days
Apartment plan review, first review
target to return first-review comments
Source: Building Services: Permitting Process (plan-review turnaround targets) — Permitting Process: first-review targets
14 business days
One- or two-family and townhome plan review, first review
target to return first-review comments
Source: Building Services: Permitting Process (plan-review turnaround targets) — Permitting Process: first-review targets
180 days
Applicant response window
to respond to comments or obtain the permit
Source: Building Services: Permitting Process (plan-review turnaround targets) — Permitting Process
analysis

What the data shows

  • Salt Lake City’s Building Services division targets first-review turnaround of 30 days for commercial projects, 21 business days for apartment projects and 14 business days for one- or two-family dwellings and townhomes, measured from when a submittal is accepted into the review queue (SLC Building Services).

  • A submittal does not enter the review queue until it clears pre-screening and the plan-review fee is paid through the Citizen Access Portal, so calendar time can exceed the target when intake is incomplete.

  • Applicants have 180 days from the date of the comment email to respond or obtain the permit before the application lapses.

how Permavia helps in salt lake city

Most delay accumulates before technical review

The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.

frequently asked

Salt Lake City permitting: FAQ

How long does plan review take in Salt Lake City?

Salt Lake City’s Building Services division targets 30 days to return first-review comments on commercial projects, 21 business days on apartment projects and 14 business days on one- or two-family dwellings and townhomes, measured from when the submittal is accepted into the review queue.

Do these times include corrections?

No: they're first-review targets. Resubmittal cycles add time, and applicants have 180 days from the comment email to respond or obtain the permit.

When does the review clock start?

After the submittal clears pre-screening and the plan-review fee is paid through the Citizen Access Portal, that's when the project is accepted into the review queue.

Sources

All figures on this page are drawn from Building Services: Permitting Process (plan-review turnaround targets), Salt Lake City Corporation, Building Services Division. Published targets to return first-review comments: 30 days for commercial projects, 21 business days for apartment projects and 14 business days for one- or two-family dwelling or townhome projects, measured from acceptance into the review queue. Applicants have 180 days to respond to comments or obtain the permit. www.slc.gov/buildingservices/permitting-process/. Specific tables, reports, and pages are cited inline with each figure above.

These are the City of Salt Lake City Building Services division’s target first-review turnaround times (30 days for commercial, 21 business days for apartments, 14 business days for one- or two-family dwellings and townhomes), measured from acceptance into the review queue, not total end-to-end permit time. Resubmittal cycles add time, and the clock starts only after pre-screening and fee payment. Source: SLC.gov Building Services.