Salt Lake City Building Permit Review Times
Salt Lake City aims to return first-review comments within 30 days on commercial projects, 21 business days on apartment projects and 14 business days on one- or two-family homes and townhomes. That puts a commercial first review at about a month and a small home at under three weeks, before any corrections.
Salt Lake City permitting, the figures
The key published figures for this jurisdiction — each cited to its official source.
What the data shows
Salt Lake City’s Building Services division targets first-review turnaround of 30 days for commercial projects, 21 business days for apartment projects and 14 business days for one- or two-family dwellings and townhomes, measured from when a submittal is accepted into the review queue (SLC Building Services).
A submittal does not enter the review queue until it clears pre-screening and the plan-review fee is paid through the Citizen Access Portal, so calendar time can exceed the target when intake is incomplete.
Applicants have 180 days from the date of the comment email to respond or obtain the permit before the application lapses.
Most delay accumulates before technical review
The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.
Salt Lake City permitting: FAQ
How long does plan review take in Salt Lake City?
Salt Lake City’s Building Services division targets 30 days to return first-review comments on commercial projects, 21 business days on apartment projects and 14 business days on one- or two-family dwellings and townhomes, measured from when the submittal is accepted into the review queue.
Do these times include corrections?
No: they're first-review targets. Resubmittal cycles add time, and applicants have 180 days from the comment email to respond or obtain the permit.
When does the review clock start?
After the submittal clears pre-screening and the plan-review fee is paid through the Citizen Access Portal, that's when the project is accepted into the review queue.
Sources
All figures on this page are drawn from Building Services: Permitting Process (plan-review turnaround targets), Salt Lake City Corporation, Building Services Division. Published targets to return first-review comments: 30 days for commercial projects, 21 business days for apartment projects and 14 business days for one- or two-family dwelling or townhome projects, measured from acceptance into the review queue. Applicants have 180 days to respond to comments or obtain the permit. www.slc.gov/buildingservices/permitting-process/. Specific tables, reports, and pages are cited inline with each figure above.
These are the City of Salt Lake City Building Services division’s target first-review turnaround times (30 days for commercial, 21 business days for apartments, 14 business days for one- or two-family dwellings and townhomes), measured from acceptance into the review queue, not total end-to-end permit time. Resubmittal cycles add time, and the clock starts only after pre-screening and fee payment. Source: SLC.gov Building Services.