Nashville Building Permit Timelines & Delays
Metro Nashville’s Department of Codes and Building Safety (Metro Codes) does not publish a measured permit turnaround, so the firmest timeline figure is its own posted rule: for architectural plan review on larger projects, reviewers are “required to review within 30 days upon receipt of the drawing file,” for first review and re-review alike. No expedited review is offered, but commercial plans and Fire Marshal reviews can go to a third-party reviewer registered with the State of Tennessee. A building permit can also need sign-offs from Water and Sewer, Stormwater, Health, Fire, Planning, the Nashville Department of Transportation (NDOT) and Historic, and Metro Codes says it cannot speak to how long those take.
Nashville permitting, the figures
The key published figures for this jurisdiction — each cited to its official source.
What the data shows
Metro Codes requires architectural plan reviewers on larger projects to review within 30 days of receiving the drawing file, for initial review and re-review, and says no expedited review is available, though commercial plans and Fire Marshal reviews can go to a state-registered third-party reviewer (Metro Codes, Commercial Permit FAQ, 2026).
A Codes building permit can need approvals from Water and Sewer, Stormwater, Health, Fire Life Safety, the Planning Commission, NDOT and Historic; those reviews can run at the same time, but the Codes permit is issued last, and Metro Codes says it cannot speak to how long the other reviews take (Metro Codes, Commercial Permit FAQ, 2026).
Davidson County authorized 5,632 new private housing units by permit in 2025, down from 6,880 in 2024 and about 65% below the 2021 peak of 16,310 (U.S. Census Bureau Building Permits Survey via FRED, 2026).
WPLN reported that the June 2022 city budget added 35 staff to a codes department that had added only 19 people since 2000, while construction value grew from $1.3 billion to over $5.3 billion over the same span, and that Codes had added a third-party review policy for larger commercial projects (WPLN, 2022).
Most delay accumulates before technical review
The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.
Nashville permitting: FAQ
How long does Metro Nashville take to review building permit plans?
For architectural plan review on larger projects, Metro Codes says plan reviewers are “required to review within 30 days upon receipt of the drawing file,” for both initial review and re-review (Metro Codes, Commercial Permit FAQ, 6/2026). That is a stated requirement, not a measured average, and Metro does not publish one. No expedited review is offered, but for commercial new construction, additions, renovations and tenant finish-outs, applicants can use a third-party reviewer registered with the State of Tennessee for the commercial plans and Fire Marshal reviews; Master permits are not eligible.
Why can a permit take longer than the 30-day review window?
The 30 days covers Metro Codes’ own plan review. After you apply, a zoning examiner emails a permit checklist naming the agencies that must approve, which can include Water and Sewer, Stormwater, Health, Fire Life Safety, the Planning Commission, NDOT and Historic, and some require their own permits, such as grading. Those reviews can run at the same time, but the Codes building permit is issued last, and Metro Codes says it cannot speak to how long the other agencies take (Metro Codes, Commercial Permit FAQ, 6/2026).
How much residential construction is Nashville permitting?
Davidson County authorized 5,632 new private housing units by permit in 2025, down from 6,880 in 2024 and from a 2021 peak of 16,310 (U.S. Census Bureau Building Permits Survey via FRED, series BPPRIV047037). Separately, Metro’s FY2027 recommended budget sets a goal to “maintain or exceed 12,500 building permits issued,” a target that counts all building permits, not housing units (Metro Nashville FY2027 Recommended Budget).
Has Nashville modernized its permitting process?
Yes. On September 8, 2025, Metro launched ePlans, which lets applicants upload one set of plans reviewed concurrently by all permitting departments, track progress and receive stamped plans; Codes and the Fire Marshal’s Office went first, with other departments to follow (Metro Codes, Apply for Electronic Plans Review). Metro Codes does not accept paper, mailed or walk-in plans (Metro Codes, Commercial Permit FAQ, 6/2026). In 2022 WPLN reported 35 new codes staff in that year’s budget and a third-party review policy for larger commercial projects (WPLN, June 23, 2022).
Sources
All figures on this page are drawn from Department of Codes & Building Safety: Commercial Building Permit Process, Metro Nashville / Davidson County. Metro Codes’ commercial permit page links its Commercial Permit FAQ (6/2026), which states plan reviewers are required to review architectural plans for larger projects within 30 days of receiving the drawing file, offers no expedited review, accepts third-party review of commercial plans and Fire Marshal reviews, and issues the Codes permit last after other Metro agencies. nashville.gov/departments/codes/construction-and-permits/commercial-building-permit-process. Specific tables, reports, and pages are cited inline with each figure above.
Metro Codes does not publish measured plan-review times or a review backlog, so the 30 days is the department’s stated requirement for architectural review of larger projects, not verified performance, and it covers only Codes, not Water, Stormwater, NDOT or the other agencies. The housing figures are Census Building Permits Survey counts of units authorized in Davidson County, a county-level proxy for Metro Nashville; they measure volume, not speed. The FY2027 figure is a budget goal for all building permits. Staffing figures are WPLN reporting from June 2022 and may not reflect current staffing. Permit-time figures are not comparable across cities, which define and measure them differently.