Permittable is now Permavia. Read about our new name

jurisdiction guide · georgia

Savannah Building Permit Timelines & Delays

Savannah’s Development Services Department says residential building permits, for new homes and additions or remodels, are “typically approved in two weeks,” while commercial and multi-family projects of three or more units “may take more than 30 days.” The city names the most common cause of delay as missing Site Development Permit plans: that permit typically takes 60 to 90 days after a complete application, and the city warns it can take anywhere from 30 days to 6 months or longer, depending on the site, the quality of the plans and how quickly consultants answer comments.

Last reviewed November 3, 2026
headline figure
historic review + flood site development permits typically run 60–90 days; historic review adds time
what to know
The city says residential permits are typically approved in two weeks, but Site Development Permits typically take 60–90 days, and historic-district review and a 2-ft flood-elevation rule add more.
data source
Development Services Permitting FAQ, Historic Review & Flood Protection
by the numbers

Savannah permitting, the figures

The key published figures for this jurisdiction — each cited to its official source.

~2 weeks
Residential building permit
City’s stated typical approval time for new construction and additions/remodels; a target, not a measured time
Source: Development Services Permitting FAQ, Historic Review & Flood Protection — City of Savannah, Permitting FAQ: “How long does it take to get a building permit…” (2026)
>30 days
Commercial / multi-family (3+ units)
City’s stated estimate, not a measured time
Source: Development Services Permitting FAQ, Historic Review & Flood Protection — City of Savannah, Permitting FAQ: “How long does it take to get a building permit…” (2026)
60–90 days
Site Development Permit (typical)
After a complete application; depends on site issues, plan quality and consultant response
Source: Development Services Permitting FAQ, Historic Review & Flood Protection — City of Savannah, Permitting FAQ: “How long does it take to get a site permit…” (2026)
30 days–6+ months
Site permit (full range)
City’s stated range; missing Site Development Permit plans are the most common cause of building-permit delay
Source: Development Services Permitting FAQ, Historic Review & Flood Protection — City of Savannah, Permitting FAQ: “How long does it take to get a building permit…” (2026)
10 business days
Site plan review per department
Each city department and the MPC review; repeats until all departments accept the plans
Source: Development Services Permitting FAQ, Historic Review & Flood Protection — City of Savannah, Permitting FAQ: “What is the process for getting a site plan approved?” (2026)
1× / month
Historic District Board of Review (downtown)
2nd Wednesday at 1 p.m.; up to two minor items can be staff-reviewed, three or more go to the board
Source: Development Services Permitting FAQ, Historic Review & Flood Protection — MPC, HDBR page and 2026 HDBR application
1× / month
Historic Preservation Commission (Victorian, Cuyler-Brownville, Streetcar)
Wednesdays at 2 p.m., mostly the 4th Wednesday in 2026; conservation districts reviewed for contributing demolition only
Source: Development Services Permitting FAQ, Historic Review & Flood Protection — MPC, 2026 HPC application
+2 ft above BFE
Floodplain freeboard (new / substantial improvement)
Adopted Oct. 24, 2024; applies to building permits submitted on or after Jan. 1, 2025 (was 1 ft since 2008)
Source: Development Services Permitting FAQ, Historic Review & Flood Protection — City of Savannah, Flood Protection Information; Flood Damage Prevention Ordinance Sec. 8-7046 (2025)
analysis

What the data shows

  • The city says residential permits are typically approved in two weeks, but commercial and multi-family (three or more units) projects may take more than 30 days, and a Site Development Permit typically takes 60 to 90 days after a complete application, or anywhere from 30 days to 6 months or longer (City of Savannah, Permitting FAQ, 2026).

  • Review is sequential and stops for corrections: building plans pass from reviewer to reviewer and are placed on hold until every concern is addressed, and site plans give each city department and the MPC ten business days per round until all accept (City of Savannah, Permitting FAQ, 2026).

  • In the Savannah Downtown Historic District, a Certificate of Appropriateness comes before the building permit, and the Historic District Board of Review meets once a month, on the 2nd Wednesday; applications with three or more minor items, or for new construction, demolition or relocation, go to the board rather than staff (MPC, HDBR application, 2026).

  • City Council adopted a 2-foot freeboard on October 24, 2024: new and substantially improved buildings in the 100-year floodplain must have their lowest floor at least 2 feet above base flood elevation, up from 1 foot, for building permits submitted on or after January 1, 2025 (City of Savannah, Flood Protection Information, 2026).

how Permavia helps in savannah

Most delay accumulates before technical review

The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.

frequently asked

Savannah permitting: FAQ

How long does a residential building permit take in Savannah?

The city says residential permits for new construction and additions or remodels are typically approved in two weeks, while commercial and multi-family projects of three or more units may take more than 30 days (City of Savannah, Permitting FAQ). If the project also needs a Site Development Permit, that typically takes 60 to 90 days after a complete application, and the city warns it can run from 30 days to 6 months or longer. These are the city’s estimates, not measured times.

How does plan review work in Savannah?

Building, trade and site permits are applied for online through the city’s permit portal, eTRAC, and documents must be submitted electronically (City of Savannah, Development Services). Building plans go from reviewer to reviewer and are “placed on hold until all of the concerns are addressed”; once every reviewer approves, a permit specialist prepares the permit (City of Savannah, Permitting FAQ). Site plans go to all city departments and the MPC, each with ten business days per round, until all departments accept them. The city’s online Permit Tracker shows the status of active permits and is updated weekly.

What extra review applies in Savannah’s historic districts?

Exterior changes visible from the street need a Certificate of Appropriateness, which must be issued before the building permit (MPC, 2022). In the Savannah Downtown Historic District, staff can review up to two minor items such as a color change, roof repair or awnings, but three or more items, new construction, demolition or relocation go to the Historic District Board of Review, which meets on the 2nd Wednesday of each month (MPC, 2026 HDBR application). The Victorian, Cuyler-Brownville and Streetcar districts go to the Historic Preservation Commission, which meets monthly, mostly on the 4th Wednesday in 2026; in the city’s conservation districts it reviews only demolition of contributing buildings (MPC, 2026 HPC application).

Do flood rules affect building permits in Savannah?

Yes. In the 100-year floodplain, new and substantially improved buildings must have their lowest floor at least 2 feet above base flood elevation, up from the 1 foot required since 2008 (City of Savannah, Flood Protection Information). City Council adopted the change on October 24, 2024, and it applies to building permits submitted on or after January 1, 2025 (City of Savannah, Flood Protection Information; Development Services). The standard is in Sec. 8-7046 of the city’s Flood Damage Prevention Ordinance; the city says to use its 2025 ordinance PDF, since the online code may not show the latest changes.

Sources

All figures on this page are drawn from Development Services Permitting FAQ, Historic Review & Flood Protection, City of Savannah, GA (with the Chatham County-Savannah Metropolitan Planning Commission). The city’s stated permit timelines (residential typically two weeks, commercial and multi-family more than 30 days, Site Development Permits typically 60–90 days or 30 days to 6+ months, ten business days per department per site-plan round), MPC’s monthly Historic District Board of Review and Historic Preservation Commission schedules, and the city’s 2-ft floodplain freeboard for building permits submitted on or after Jan. 1, 2025. www.savannahga.gov/m/faq?cat=56. Specific tables, reports, and pages are cited inline with each figure above.

All timing figures here are the City of Savannah’s own published estimates (two weeks, more than 30 days, 60–90 days, 30 days to 6 months, ten business days per department), not measured or audited review times. The city does not appear to publish median review or issuance times; its Permit Tracker shows the status of individual permits, not overall turnaround. Historic-board schedules are MPC’s published meeting calendars, and the 2-foot freeboard is an adopted ordinance standard. Because cities measure and report permit times differently, these figures are not comparable with other cities’.