Permittable is now Permavia. Read about our new name

jurisdiction guide · indiana

Indiana Building Permit Timelines & Delays

Since January 1, 2026, any Indiana city, town or county that reviews plans for one- and two-family homes and townhouses has 3 business days to say whether an application is complete and 7 more to finish plan review. If it says it can’t meet that, the builder can hire a licensed architect, engineer or certified building official as a private reviewer, and the local government must refund its plan-review and inspection fees, keeping at most $100. From July 1, 2026, a local office that misses these deadlines also forfeits fees still owed and refunds fees already paid, unless the delay was the applicant’s fault or outside its control.

Last reviewed November 14, 2026
headline figure
7 biz-d for a local plan review of a complete one- or two-family home application, statewide since Jan. 1, 2026
what to know
Since January 1, 2026, an Indiana city, town or county that reviews house plans must finish within 7 business days of saying an application is complete; if it can’t, a private reviewer can step in and the local fees come back, less up to $100. Commercial plans have a separate 10-business-day state clock.
data source
Indiana’s home plan-review deadlines (IC 36-7-2.5) and the state Construction Design Release
by the numbers

Indiana permitting, the figures

The key published figures for this jurisdiction — each cited to its official source.

7 business days
Local plan review, 1–2 family homes
After the local office’s notice that the application is complete, where it requires plan review; in effect since Jan. 1, 2026
Source: Indiana’s home plan-review deadlines (IC 36-7-2.5) and the state Construction Design Release — Ind. Code 36-7-2.5-17, added by HEA 1005 (2025)
3 business days
Completeness notice
The local office must say whether a home application is complete or incomplete
Source: Indiana’s home plan-review deadlines (IC 36-7-2.5) and the state Construction Design Release — Ind. Code 36-7-2.5-16(b), HEA 1005 (2025)
3 business days
Home inspections
The completeness notice must say whether the office can inspect within 3 business days of a written request, as well as review plans within 7
Source: Indiana’s home plan-review deadlines (IC 36-7-2.5) and the state Construction Design Release — Ind. Code 36-7-2.5-18, HEA 1005 (2025)
Permit next business day
If the office misses its stated timeline
A full or limited permit; delays caused by the applicant or outside the office’s control don’t count
Source: Indiana’s home plan-review deadlines (IC 36-7-2.5) and the state Construction Design Release — Ind. Code 36-7-2.5-21 to -23, HEA 1005 (2025)
Fees back, less ≤ $100
Private reviewer refund
When the office says it can’t meet the timeline and the applicant uses a private provider, it refunds plan-review and inspection fees; it must issue the permit by the next business day after a complete private plan-review report
Source: Indiana’s home plan-review deadlines (IC 36-7-2.5) and the state Construction Design Release — Ind. Code 36-7-2.5-20 and -31, HEA 1005 (2025)
Since July 1, 2026
Missed-deadline fee forfeiture
A unit that misses the home-permit deadlines forfeits regulatory fees owed and refunds fees paid
Source: Indiana’s home plan-review deadlines (IC 36-7-2.5) and the state Construction Design Release — Ind. Code 36-7-2.5-23.5, added by HEA 1001 (2026), Section 18
10 business days
State design release (Class 1)
From a complete filing; 20 business days if selected for detailed review, then 10 per round of corrections; times exclude waiting on the submitter
Source: Indiana’s home plan-review deadlines (IC 36-7-2.5) and the state Construction Design Release — Indiana Dept. of Homeland Security, Building Plan Review Process (2026); Ind. Code 22-15-3.2-8 to -10
2014 building, 2020 residential
Codes in effect
2014 Indiana Building Code (2012 IBC) since Dec. 1, 2014; 2020 Indiana Residential Code (2018 IRC) since Dec. 26, 2019; a 2024 IBC-based update is pending, not in effect (regulatory and fiscal analysis stage on Sept. 1, 2026)
Source: Indiana’s home plan-review deadlines (IC 36-7-2.5) and the state Construction Design Release — Fire Prevention and Building Safety Commission, Rules page (2026)
analysis

What the data shows

  • Since January 1, 2026, a local office that requires permits for one- and two-family homes must say within 3 business days whether an application is complete and finish plan review within 7 business days of that notice, and it must issue a full or limited permit by the next business day if it misses a timeline it said it could meet (House Enrolled Act 1005, 2025).

  • If the office says it can’t meet the timeline, the applicant may use a private provider (a licensed architect, professional engineer or certified building official with no stake in the project), and the office must refund its plan-review and inspection fees, keeping at most a $100 convenience fee; since July 1, 2026, missing the deadlines also means forfeiting or refunding fees (House Enrolled Act 1005, 2025; House Enrolled Act 1001, 2026).

  • Commercial, industrial, public and multifamily (Class 1) buildings can’t start construction until the state issues a Construction Design Release, and the state must answer a complete filing within 10 business days, or 20 once a project is selected for detailed review, with 10 business days per correction round (Indiana Department of Homeland Security, 2026).

  • Indiana’s statewide building code is still the 2014 edition based on the 2012 International Building Code, and the residential code is the 2020 edition based on the 2018 International Residential Code; an update based on the 2024 International Building Code is pending and not in effect, and was at the regulatory and fiscal analysis stage on September 1, 2026 (Fire Prevention and Building Safety Commission, 2026).

how Permavia helps in indiana

Most delay accumulates before technical review

The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.

frequently asked

Indiana permitting: FAQ

How long can an Indiana city take to review plans for a house?

Seven business days after it tells you the application is complete, and it has 3 business days to send that notice (Ind. Code 36-7-2.5-16 and -17, in effect since January 1, 2026). The notice must also say whether the office can meet that 7-day review and a 3-business-day inspection timeline; if it misses a timeline it said it could meet, it must issue a full or limited permit by the next business day, and since July 1, 2026 it also forfeits or refunds its fees (Ind. Code 36-7-2.5-18, -21 and -23.5). Delays caused by the applicant or outside the office’s control don’t count.

Can I use a private plan reviewer for a house in Indiana?

Yes. An applicant for a one- or two-family home or townhouse may use a private provider, meaning a licensed architect, professional engineer or certified building official who isn’t a local employee and has no stake in the project, for plan review, inspections or both, at the applicant’s cost (House Enrolled Act 1005, 2025). If the local office said it couldn’t meet the timeline, it must refund its plan-review and inspection fees, less a convenience fee of up to $100, and it must issue the permit by the next business day after receiving a complete private plan-review report (Ind. Code 36-7-2.5-20 and -31).

Do commercial and multifamily projects need state approval in Indiana?

Yes. Buildings used by the public, by employees or by three or more tenants are Class 1 structures, and no construction may start on them until the Indiana Department of Homeland Security, or a local government the state has certified to do the review, issues a design release (675 IAC 12-6-3; Ind. Code 22-15-3-1). The department has 10 business days from a complete filing to release the design, flag the filing as incomplete or select it for review; if it sends no review notice in that time, it must provide the release or a temporary confirmation number by the 11th day (Ind. Code 22-15-3.2-8). Selected projects get an answer within 20 business days and each round of corrections within 10, and uploading more documents before the first answer restarts the clock (IDHS, Building Plan Review Process). Small accessory buildings and minor remodeling are among the exemptions (675 IAC 12-6-4), and local permits may still be needed.

Which building codes apply in Indiana?

The 2014 Indiana Building Code, based on the 2012 International Building Code, in effect since December 1, 2014, and for one- and two-family homes the 2020 Indiana Residential Code, based on the 2018 International Residential Code, in effect since December 26, 2019 (Fire Prevention and Building Safety Commission, Rules page). A draft 2026 Indiana Building Code based on the 2024 International Building Code is in rulemaking, not adopted and not in effect; the commission’s September 1, 2026 agenda still listed its regulatory and fiscal analysis (FPBSC agenda, Sept. 1, 2026).

Sources

All figures on this page are drawn from Indiana’s home plan-review deadlines (IC 36-7-2.5) and the state Construction Design Release, Indiana General Assembly; Indiana Department of Homeland Security. House Enrolled Act 1005 (2025) added IC 36-7-2.5, in effect since January 1, 2026: a city, town or county that reviews one- and two-family home plans has 3 business days to say an application is complete and 7 business days to finish plan review, must issue a permit by the next business day if it misses a timeline it said it could meet, and refunds plan-review and inspection fees (less up to $100) when it says it can’t and the applicant uses a private provider. House Enrolled Act 1001 (2026) added fee forfeiture for missed deadlines from July 1, 2026. Class 1 (commercial, public and multifamily) buildings separately need a state Construction Design Release: 10 business days from a complete filing, 20 if selected for review (Indiana Department of Homeland Security, Building Plan Review Process). iga.in.gov/legislative/2025/bills/house/1005/details. Specific tables, reports, and pages are cited inline with each figure above.

Every day count here is a legal deadline, not a measured outcome: no official source found for this guide reports how long Indiana design releases or local home plan reviews actually take, or how often the deadlines are met. The home deadlines run in business days from the local completeness notice and exclude delays caused by the applicant or outside the office’s control, and the state design-release times exclude time spent waiting on the submitter. Deadlines differ by building class, so they aren’t comparable with other states’ permit clocks.