Dallas Building Permit Timelines & Delays
Dallas now finishes first reviews of new commercial plans in about half the time its own goal allows: 8 business days on average in the fiscal year to September 2026, against a 15-day goal. In the backlog years, on a different measure, city staff took a median of 72 days to review a residential permit (May 2021). Getting the permit takes longer: the City Auditor found that new commercial building permits opened and issued in July–December 2025 averaged 68 days to issue, sixth of nine Texas cities compared, and most of the delayed permits it sampled were held up at intake or in assigning plan reviewers.
Dallas permitting, the figures
The key published figures for this jurisdiction — each cited to its official source.
What the data shows
Dallas dug out of a permitting backlog: Development Services officials reported that staff took a median of 72 days to review a residential permit in May 2021, 58 days in May 2022 and 5 days in May 2023, and, on a different measure, the Planning and Development Department told the City Council in January 2025 that the median approval time for new commercial construction permits fell by 87 days (32%) from 2023 to 2024, from 276 to 189 days (Dallas Development Services via The Dallas Morning News, 2023; City of Dallas council briefing and NBC DFW, 2025).
On the city’s FY2025–26 scorecard (October 2025–September 2026), initial reviews of new commercial projects averaged 8 business days against a 15-day goal, falling from 14 in October and November 2025 to between 4 and 7 each month from April to September 2026, while initial reviews of new homes and additions averaged 2 business days against a 10-day goal (City of Dallas Planning and Development Department, 2026).
Q-Team, the city’s optional expedited commercial review, charges $1,000 per hour plus an intake fee of $500 to $1,250 by project size, up to a cap, and its first reviews averaged 3 business days in FY2025–26 against a 10-day goal, and requested revisions are reviewed within 10 business days of resubmittal (City of Dallas Planning and Development Department, 2026).
End to end is slower: a June 2026 City Auditor review found that new commercial building permits opened and issued in July–December 2025 averaged 68 days to issue (sixth of nine Texas cities compared) and commercial remodels 29 days (second), and 37 of 48 sampled delayed permits were held up by staff availability at intake or in assigning plan reviewers, which management tied to the switch to the DallasNow permitting system (Dallas Office of the City Auditor, 2026).
Most delay accumulates before technical review
The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.
Dallas permitting: FAQ
How long does commercial plan review take in Dallas?
On the City of Dallas Planning and Development Department’s FY2025–26 scorecard (October 2025–September 2026), initial reviews of new commercial projects averaged 8 business days against a 15-business-day goal; the city’s 2023 Commercial Quick Guide set a 5-day target for prescreen and intake before that review. That covers the first review only. Getting the permit takes longer: a City Auditor review found new commercial building permits opened and issued in July–December 2025 averaged 68 days to issue.
Does Dallas offer expedited permit review?
Yes. Q-Team is an optional, appointment-based expedited review for commercial projects, at $1,000 per hour plus an intake fee of $500 to $1,250 by project size, up to a fee cap. Projects must be zoned for the intended use and platted (or able to show a legal building site), meetings are booked at least five days ahead, and requested revisions are reviewed within 10 business days of resubmittal. The city’s 2023 Commercial Quick Guide asked for plans that are “Ready for Construction” documents. First Q-Team reviews averaged 3 business days in FY2025–26 against a 10-day goal.
How long does residential plan review take in Dallas?
On the City of Dallas Planning and Development Department’s FY2025–26 scorecard (October 2025–September 2026), initial reviews of new homes and additions averaged 2 business days against a 10-day goal, and resubmitted new-home reviews averaged 1 business day against a 5-day goal. These are review-step times, not the time to issue a permit.
Are these total permit times?
No. The city’s scorecard reports average business days for an initial or resubmitted review, not the time from application to an issued permit. The closest end-to-end measure is the City Auditor’s: new commercial building permits opened and issued in July–December 2025 averaged 68 days to issue, counting the time applicants spent on resubmittals.
Sources
All figures on this page are drawn from Dallas Planning & Development Performance Goals FY2025–26, City of Dallas, Planning and Development Department. Official monthly scorecard for October 2025–September 2026: average business days for initial and resubmitted plan reviews against the department’s goals (new commercial 15, Q-Team first review 10, new homes and additions 10, new-home resubmittals 5), and inspections performed and on time by category. It notes that some numbers were not tracked for the whole fiscal year. The City Auditor’s June 2026 permit audit, the department’s January 2025 council briefing, the 2023 Commercial Quick Guide, Q-Team terms and news figures are cited inline. dallascityhall.com/departments/pnv/Documents/AH%20Memos/PDD_PerformanceSummaryforFY-2025-26.pdf. Specific tables, reports, and pages are cited inline with each figure above.
The FY2025–26 scorecard figures are measured averages of business days for one review step (an initial or resubmitted review), shown against the city’s own goals; they are not end-to-end times, and the scorecard notes that some numbers were not tracked for the whole fiscal year. The 2023 Commercial Quick Guide’s 5-day prescreen and 15-day initial review were targets, not measured times. The residential 72→5-day figures are May medians of staff review time that Development Services reported to The Dallas Morning News (2023), and the overdue-plan counts are point-in-time figures it reported to CandysDirt (2023); a May 2023 ransomware attack also delayed permit issuance that year. The 276→189-day figures are calendar-year medians of approval time for new commercial construction permits from the department’s January 2025 council briefing (the slide gives the 87-day, 32% drop; NBC DFW reported the day counts). None of these is directly comparable with the scorecard or audit averages. The City Auditor’s averages leave out permits that took longer than six months, which lowers Dallas’s figures, and include applicant resubmittal time that the city’s own measures exclude. Methodology differs from other jurisdictions on this site, so compare with care.