jurisdiction guide · arizona

Phoenix Building Permit Review Times

Phoenix tells applicants up front how long first review should take, and reports every month whether it delivered. In its September 2026 report (covering August reviews), commercial building plan reviews met or beat their goals and home building plans ran two to four days over, but civil and site plan reviews ran 9 to 23 days over goal in 7 of 8 categories.

Last reviewed October 27, 2026
headline figure
30 d commercial major avg (goal 45), Sept 2026
what to know
Commercial plan reviews meet their goals; home plans run slightly over, and 7 of 8 site and civil categories run 9 to 23 days over.
data source
Plan Reviews: Turnaround Times (monthly report)
by the numbers

Phoenix permitting, the figures

The key published figures for this jurisdiction — each cited to its official source.

30 avg days
Commercial, major (over 50,000 sq ft and over $5 million)
goal 45 calendar days; initial review
Source: Plan Reviews: Turnaround Times (monthly report) — Plan Reviews: Turnaround Times, September 2026 (Commercial)
33 avg days
Commercial, medium (5,000–50,000 sq ft and $350,000–$5 million)
goal 35 calendar days; initial review
Source: Plan Reviews: Turnaround Times (monthly report) — Plan Reviews: Turnaround Times, September 2026 (Commercial)
25 avg days
Commercial, minor (under 5,000 sq ft or under $350,000)
goal 25 calendar days; initial review
Source: Plan Reviews: Turnaround Times (monthly report) — Plan Reviews: Turnaround Times, September 2026 (Commercial)
32 avg days
Residential, custom & standard plans
goal 30 calendar days; initial review
Source: Plan Reviews: Turnaround Times (monthly report) — Plan Reviews: Turnaround Times, September 2026 (Residential)
34 avg days
Residential, major remodels & additions
goal 30 calendar days; over 2,000 sq ft and/or more than one level
Source: Plan Reviews: Turnaround Times (monthly report) — Plan Reviews: Turnaround Times, September 2026 (Residential)
22 avg days
Residential, minor remodels & additions
goal 20 calendar days; 2,000 sq ft or less, one level
Source: Plan Reviews: Turnaround Times (monthly report) — Plan Reviews: Turnaround Times, September 2026 (Residential)
4 avg days
Plot plans
goal 5 calendar days; initial review
Source: Plan Reviews: Turnaround Times (monthly report) — Plan Reviews: Turnaround Times, September 2026
41 avg days
Site plans, minor (final)
goal 20 calendar days; initial review
Source: Plan Reviews: Turnaround Times (monthly report) — Plan Reviews: Turnaround Times, September 2026 (Site Plans)
analysis

What the data shows

  • Civil and site plan reviews ran furthest over: minor site plans averaged 41 days against a 20-day goal, minor civil plans 43 against 20, and major pre-application meetings 45 against 28 (Plan Reviews: Turnaround Times, City of Phoenix PDD, September 2026).

  • Commercial plan reviews met or beat their goals: major projects averaged 30 days against a 45-day goal, medium projects 33 against 35, and minor projects 25 against 25 (Plan Reviews: Turnaround Times, September 2026).

  • Home plans ran slightly over: custom and standard plans averaged 32 days against a 30-day goal, and major remodels and additions 34 against 30 (Plan Reviews: Turnaround Times, September 2026).

  • The figures cover the initial review only, and the city notes that turnaround times fluctuate with monthly workload and project complexity (Plan Reviews: Turnaround Times, September 2026).

how Permavia helps in phoenix

Most delay accumulates before technical review

The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.

frequently asked

Phoenix permitting: FAQ

How long does plan review take in Phoenix?

Per the City of Phoenix Planning & Development Department's September 2026 turnaround report, initial plan review averaged 30 calendar days for major commercial projects (goal 45), 32 days for custom and standard home plans (goal 30) and 22 days for minor residential remodels and additions (goal 20).

Does Phoenix publish its permit review times?

Yes. Phoenix publishes a monthly Plan Reviews: Turnaround Times report showing both the target (“goal”) and the previous month's actual average days for initial plan review, by project type (Plan Reviews: Turnaround Times, September 2026).

Are these total permit times?

No. They are initial plan-review times in calendar days. If plans need corrections, the later review rounds are not part of these figures, and the numbers change month to month with workload (Plan Reviews: Turnaround Times, September 2026).

Is Phoenix meeting its plan review goals?

For commercial projects, yes: all three commercial sizes were at or under goal in the September 2026 report. Residential building plans ran two to four days over goal, while plot plans beat theirs at 4 days against 5. Civil and site plan reviews were the exception: 7 of their 8 categories ran over goal, by 9 to 23 days, for example minor site plans at 41 days against 20 and minor civil plans at 43 against 20 (Plan Reviews: Turnaround Times, September 2026).

Sources

All figures on this page are drawn from Plan Reviews: Turnaround Times (monthly report), City of Phoenix Planning & Development Department. Monthly report of goal vs. average INITIAL plan-review turnaround, in calendar days. “Goal” is the target; “Average” is the prior month's typical completion time. Figures cited from the September 2026 edition (the city replaces the report at the same address each month). www.phoenix.gov/administration/departments/pdd/about-us/reports-data.html. Specific tables, reports, and pages are cited inline with each figure above.

These are the City of Phoenix Planning & Development Department's published goal and average turnaround times for initial plan review (calendar days), from its monthly Plan Reviews: Turnaround Times report (September 2026 edition). “Goal” is the target; “Average” is the typical number of days in the previous month. The city replaces the report at the same address each month, so the linked figures change. Figures fluctuate monthly and exclude correction cycles. Methodology differs from other jurisdictions on this site, so compare with care.