Phoenix Building Permit Review Times
Phoenix tells applicants up front how long first review should take, and reports every month whether it delivered. In its September 2026 report (covering August reviews), commercial building plan reviews met or beat their goals and home building plans ran two to four days over, but civil and site plan reviews ran 9 to 23 days over goal in 7 of 8 categories.
Phoenix permitting, the figures
The key published figures for this jurisdiction — each cited to its official source.
What the data shows
Civil and site plan reviews ran furthest over: minor site plans averaged 41 days against a 20-day goal, minor civil plans 43 against 20, and major pre-application meetings 45 against 28 (Plan Reviews: Turnaround Times, City of Phoenix PDD, September 2026).
Commercial plan reviews met or beat their goals: major projects averaged 30 days against a 45-day goal, medium projects 33 against 35, and minor projects 25 against 25 (Plan Reviews: Turnaround Times, September 2026).
Home plans ran slightly over: custom and standard plans averaged 32 days against a 30-day goal, and major remodels and additions 34 against 30 (Plan Reviews: Turnaround Times, September 2026).
The figures cover the initial review only, and the city notes that turnaround times fluctuate with monthly workload and project complexity (Plan Reviews: Turnaround Times, September 2026).
Most delay accumulates before technical review
The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.
Phoenix permitting: FAQ
How long does plan review take in Phoenix?
Per the City of Phoenix Planning & Development Department's September 2026 turnaround report, initial plan review averaged 30 calendar days for major commercial projects (goal 45), 32 days for custom and standard home plans (goal 30) and 22 days for minor residential remodels and additions (goal 20).
Does Phoenix publish its permit review times?
Yes. Phoenix publishes a monthly Plan Reviews: Turnaround Times report showing both the target (“goal”) and the previous month's actual average days for initial plan review, by project type (Plan Reviews: Turnaround Times, September 2026).
Are these total permit times?
No. They are initial plan-review times in calendar days. If plans need corrections, the later review rounds are not part of these figures, and the numbers change month to month with workload (Plan Reviews: Turnaround Times, September 2026).
Is Phoenix meeting its plan review goals?
For commercial projects, yes: all three commercial sizes were at or under goal in the September 2026 report. Residential building plans ran two to four days over goal, while plot plans beat theirs at 4 days against 5. Civil and site plan reviews were the exception: 7 of their 8 categories ran over goal, by 9 to 23 days, for example minor site plans at 41 days against 20 and minor civil plans at 43 against 20 (Plan Reviews: Turnaround Times, September 2026).
Sources
All figures on this page are drawn from Plan Reviews: Turnaround Times (monthly report), City of Phoenix Planning & Development Department. Monthly report of goal vs. average INITIAL plan-review turnaround, in calendar days. “Goal” is the target; “Average” is the prior month's typical completion time. Figures cited from the September 2026 edition (the city replaces the report at the same address each month). www.phoenix.gov/administration/departments/pdd/about-us/reports-data.html. Specific tables, reports, and pages are cited inline with each figure above.
These are the City of Phoenix Planning & Development Department's published goal and average turnaround times for initial plan review (calendar days), from its monthly Plan Reviews: Turnaround Times report (September 2026 edition). “Goal” is the target; “Average” is the typical number of days in the previous month. The city replaces the report at the same address each month, so the linked figures change. Figures fluctuate monthly and exclude correction cycles. Methodology differs from other jurisdictions on this site, so compare with care.