Kansas City Building Permit Timelines & Delays

Kansas City, Missouri’s published goal for reviewing one- and two-family home plans is seven business days per submittal, and the city has posted no measured review times since its permit and plan-review dashboard was paused at the end of March 2024. New buildings, additions and changes of use carry a four-week published turnaround, and tenant finishes, remodels and resubmittals two weeks. The Plans Review Division calls these “guaranteed turnaround times,” while its home-plan bulletin calls the seven days a “goal” (Information Bulletin No. 100).

Last reviewed November 7, 2026
headline figure
7 biz-d business-day review goal for one- and two-family homes
what to know
KCMO posts a 7-business-day review goal per submittal for one- and two-family plans and 4 weeks for new commercial; no measured times since March 2024.
data source
Plans Review Division: Commitment to Customer Service (turnaround times)
by the numbers

Kansas City permitting, the figures

The key published figures for this jurisdiction — each cited to its official source.

7 business days
One- and two-family dwelling plan review
Published goal for each complete submittal, first and later
Source: Plans Review Division: Commitment to Customer Service (turnaround times) — City of Kansas City, Information Bulletin No. 100 (revised Apr. 4, 2024); Plans Review Division turnaround list (as of Nov. 2026)
4 weeks
New buildings / additions / change of use
Published turnaround, the city calls these “guaranteed”
Source: Plans Review Division: Commitment to Customer Service (turnaround times) — City of Kansas City, Plans Review Division, “Commitment to Customer Service” (as of Nov. 2026)
2 weeks
Tenant finishes / remodels / resubmittals
Published turnaround; review comment resolution, 1 week
Source: Plans Review Division: Commitment to Customer Service (turnaround times) — City of Kansas City, Plans Review Division, “Commitment to Customer Service” (as of Nov. 2026)
2 business days
Commercial incomplete-plans notice
Applicant told if plans are incomplete and what is needed to resubmit
Source: Plans Review Division: Commitment to Customer Service (turnaround times) — City of Kansas City, Information Bulletin No. 110 Part B (revised Sept. 26, 2025)
$30 / $75
Scheduled Express Review fee
Per review appointment, one- and two-family / commercial, on top of the permit fee
Source: Plans Review Division: Commitment to Customer Service (turnaround times) — City of Kansas City, Information Bulletin No. 115 (revised June 9, 2025)
2× permit fee
Priority plan review fee
Halves the normal turnaround, one-week minimum; not offered for one- and two-family reviews
Source: Plans Review Division: Commitment to Customer Service (turnaround times) — City of Kansas City, Plans Review Division, Priority Plan Review (as of Nov. 2026)
4 business days
Certified Permitting Program target
Certified new one-family plans; city page still says “launching in late July 2026”, no launch notice posted
Source: Plans Review Division: Commitment to Customer Service (turnaround times) — City of Kansas City, City Planning & Development Department page (as of Nov. 2026)
4,036
Housing units authorized, Jackson County (2025)
Up from 4,003 in 2024; whole county, not city limits
Source: Plans Review Division: Commitment to Customer Service (turnaround times) — U.S. Census Bureau Building Permits Survey via FRED, series BPPRIV029095 (annual, 2025)
analysis

What the data shows

  • A one- or two-family home plan has a published review goal of seven business days, and the same goal applies to every resubmittal, so each round of corrections carries its own seven-business-day clock (City of Kansas City, Information Bulletin No. 100, 2024).

  • Commercial work runs on longer published clocks: four weeks for new buildings, additions and changes of use, two weeks for tenant finishes, remodels and resubmittals, and one week to resolve review comments, with notice within two business days if plans are incomplete (City of Kansas City, Plans Review Division and Information Bulletin No. 110 Part B, 2025).

  • Paying for speed has limits: priority review halves the turnaround (never below one week) for twice the permit fee but is not offered for one- and two-family reviews, while Scheduled Express Review buys a set review appointment for $30 (homes) or $75 (commercial) per review (City of Kansas City, Plans Review Division and Information Bulletin No. 115, 2025).

  • No measured review times are currently published: the city’s permit and plan-review dashboard says its data was “temporarily paused at the end of March 2024 due to server updates” (City of Kansas City, Permit and Plan Review Data, 2024).

how Permavia helps in kansas city

Most delay accumulates before technical review

The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.

frequently asked

Kansas City permitting: FAQ

How long does residential plan review take in Kansas City, MO?

The city’s published goal is seven business days for a complete one- or two-family dwelling submittal, and the same goal applies to each resubmittal (City of Kansas City, Information Bulletin No. 100, revised April 2024). The Plans Review Division lists the same seven days. These are targets: the city has posted no measured review times since its dashboard was paused in March 2024.

Can I get a permit faster than the standard timeline?

Sometimes. Scheduled Express Review gives eligible smaller projects a set review appointment, listed as same-day service, for $30 per review on one- and two-family dwellings or $75 on commercial projects, on top of the permit fee (City of Kansas City, Information Bulletin No. 115, revised June 2025). First reviews of commercial new buildings, additions, tenant finishes and changes of occupancy are not eligible. Priority plan review halves the normal turnaround, with a one-week minimum, for twice the permit fee, but not for one- and two-family reviews (City of Kansas City, Plans Review Division).

How do I apply for a residential building permit in Kansas City?

Plan review applications for new residential and commercial projects, and plan revisions, are submitted through CompassKC, the city’s online permitting portal (City of Kansas City, City Planning & Development Department). Home plans must meet the submittal requirements in Information Bulletin No. 100, and the seven-business-day review goal starts only once the application is complete.

Is Kansas City changing how it reviews permits?

Yes. On May 1, 2024 the City Council approved moving land-development review, permitting and inspections to the Public Works and Water Services departments (Ordinance 230741). Its Certified Permitting Program, with a four-business-day review target for certified new one-family plans, was set to launch in late July 2026 and be evaluated after 12–15 months; the city has not posted whether it launched.

Sources

All figures on this page are drawn from Plans Review Division: Commitment to Customer Service (turnaround times), City of Kansas City, Missouri, City Planning & Development Department. The Plans Review Division page lists published turnaround times: seven days for one- and two-family dwelling review (a seven-business-day goal per Information Bulletin No. 100, revised April 2024), two weeks for tenant finishes, remodels and resubmittals, four weeks for new buildings, additions and changes of use, and one week for review comment resolution; priority review costs twice the permit fee. www.kcmo.gov/city-hall/departments/city-planning-development/plans-review-division. Specific tables, reports, and pages are cited inline with each figure above.

The day and week figures are the city’s published turnaround targets, not measured completion times; the city has posted no measured review times since its permit and plan-review dashboard was paused at the end of March 2024. The Jackson County housing-unit count (Census Building Permits Survey) covers the whole county, including other cities, and does not match Kansas City’s city limits. Review targets are defined differently in each city, so these figures are not comparable across cities.