Tennessee Building Permit Timelines & Delays

In Tennessee, if a registered third party has already checked your plans, a city or county that runs its own plan review has 10 business days to approve them, send a list of deficiencies or ask for more information. If it misses that, it must refund the plan review fees, and you can withdraw the plans and file them with the State Fire Marshal’s Office, which also has 10 business days. That rule has applied since October 1, 2024 under Public Chapter 771; apart from it, state law asks a local program only to be performing plan examinations and inspections within 30 days of a request, as a condition of enforcing its own codes. From January 1, 2027, a separate law, Public Chapter 1044, puts 30- and 60-business-day deadlines, with automatic approval, on site plans, subdivision plats and other development applications, but not on building, fire, mechanical, plumbing or electrical permits.

Last reviewed November 12, 2026
headline figure
10 biz-d for a local answer on plans a registered third party has already checked; plan review fees refunded if missed
what to know
Where a Tennessee city or county runs its own plan review, plans already checked by a registered third party must get an answer within 10 business days. Local governments can also opt out of the state’s residential code.
data source
Tenn. Code Ann. §68-120-101: statewide codes, the residential opt-out and third-party review
by the numbers

Tennessee permitting, the figures

The key published figures for this jurisdiction — each cited to its official source.

10 business days
Answer on third-party-checked plans
To approve, send a deficiency report or request more information on plans a registered third-party plans examiner has reviewed, where the local government runs its own program; in effect since October 1, 2024; third-party inspection reports get the same 10 business days
Source: Tenn. Code Ann. §68-120-101: statewide codes, the residential opt-out and third-party review — Tenn. Code Ann. §68-120-101(k)(2)–(3); Public Chapter 771 (2024)
Fees refunded
If the local office misses it
The local jurisdiction must refund the plan review fees it collected, and the applicant may withdraw the plans and file them with the State Fire Marshal’s Office, which has 10 business days to respond
Source: Tenn. Code Ann. §68-120-101: statewide codes, the residential opt-out and third-party review — Tenn. Code Ann. §68-120-101(k)(2)(D); Tennessee State Fire Marshal’s Office, Third-Party FAQ
30 days
Local program review condition
A city or county that enforces its own codes certifies it performs plan examinations and inspections within 30 days of the request; a condition of enforcing its own codes, not a deadline on each permit
Source: Tenn. Code Ann. §68-120-101: statewide codes, the residential opt-out and third-party review — Tenn. Code Ann. §68-120-101(b)(2)(B)
Two-thirds vote
Residential code opt-out
Of the county or city legislative body, exempting one- and two-family dwellings from the statewide standards; the resolution expires 180 days after that body’s next election unless readopted
Source: Tenn. Code Ann. §68-120-101: statewide codes, the residential opt-out and third-party review — Tenn. Code Ann. §68-120-101(b)(1)(B); UT MTAS, Statewide Building Standards
2018 IRC
Statewide residential code
International Residential Code, effective July 16, 2020, with the 2018 International Energy Conservation Code for one- and two-family dwellings and townhouses
Source: Tenn. Code Ann. §68-120-101: statewide codes, the residential opt-out and third-party review — Tennessee State Fire Marshal’s Office, Currently Adopted Codes
2021 I-Codes
Statewide commercial codes
Building, fire, existing building, mechanical, plumbing, fuel gas, property maintenance and commercial energy codes, effective April 17, 2025
Source: Tenn. Code Ann. §68-120-101: statewide codes, the residential opt-out and third-party review — Tennessee State Fire Marshal’s Office, Currently Adopted Codes
30 and 60 business days
Development review deadlines from January 1, 2027
Public Chapter 1044 (2026), adopted, not yet in effect: comments within 30 business days and approval or a place on an agenda within 60 for site plans, plats and other non-legislative development applications; automatic approval if either deadline is missed; at most two deficiency notices; building, fire, mechanical, plumbing and electrical permits are not covered
Source: Tenn. Code Ann. §68-120-101: statewide codes, the residential opt-out and third-party review — University of Tennessee Institute for Public Service, Public Chapter 1044 Policy Guide (June 2026)
43,374
Housing units authorized, 2025
8th-most of any state, up from 9th in 2024; units authorized by permit, not homes started; measured
Source: Tenn. Code Ann. §68-120-101: statewide codes, the residential opt-out and third-party review — U.S. Census Bureau, Building Permits Survey, 2025 Annual Highlights
analysis

What the data shows

  • Where a city or county runs its own plan review, it must approve, report deficiencies on or request more information about plans already checked by a registered third party within 10 business days, or refund the plan review fees, after which the applicant can file with the State Fire Marshal’s Office, which also has 10 business days; the rule has applied since October 1, 2024 (Tenn. Code Ann. §68-120-101(k); Public Chapter 771, 2024).

  • A county or city can exempt one- and two-family dwellings from the state’s residential standards by a two-thirds vote of its governing body, a resolution that expires 180 days after that body’s next election unless readopted, and in those opt-out areas an owner can still ask the State Fire Marshal’s Office to inspect a home and, if it meets the state standards, receive a certificate of occupancy (Tenn. Code Ann. §68-120-101(b)(1); Tennessee State Fire Marshal’s Office, 2025).

  • Commercial projects are built to the 2021 International Building Code and related codes, in effect since April 17, 2025, while homes statewide remain on the 2018 International Residential Code, in effect since July 16, 2020 (Tennessee State Fire Marshal’s Office, 2025).

  • From January 1, 2027, local staff will have 30 business days to comment on site plans, subdivision plats and similar development applications and 60 to approve them or put them on an agenda, with automatic approval if either deadline is missed, but the law does not cover building, fire, mechanical, plumbing or electrical permits (University of Tennessee Institute for Public Service, 2026).

how Permavia helps in tennessee

Most delay accumulates before technical review

The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.

frequently asked

Tennessee permitting: FAQ

Does all of Tennessee require building permits?

Not everywhere for houses. A county or city can exempt one- and two-family dwellings from the state’s residential standards by a two-thirds vote of its governing body, and the resolution expires 180 days after that body’s next election unless it is readopted (Tenn. Code Ann. §68-120-101(b)(1)(B)). The state does not enforce its residential code in these opt-out areas, but an owner can ask the State Fire Marshal’s Office to inspect a new home or addition and, if it meets the statewide standards, receive a certificate of occupancy, which can help with lenders and loan programs that require one (Tennessee State Fire Marshal’s Office, Opt-Out Jurisdictions). Where no local program or opt-out applies, the state issues residential permits and inspects the foundation, the framing and rough-in, and the finished home (Tennessee State Fire Marshal’s Office, Residential Permits).

Is there a statewide permit deadline in Tennessee?

Only for plans a third party has already checked. Since October 1, 2024, a local jurisdiction that runs its own program has 10 business days to approve such plans, issue a deficiency report or ask for more information; if it misses that, it must refund the plan review fees, and the applicant may file with the State Fire Marshal’s Office, which then has 10 business days (Tenn. Code Ann. §68-120-101(k); Public Chapter 771, 2024). Third-party inspection reports get the same 10 business days. Apart from that, a local program certifies that it performs plan examinations and inspections within 30 days of a request, a condition of enforcing its own codes rather than a deadline on each permit (Tenn. Code Ann. §68-120-101(b)(2)(B)).

What changes for Tennessee development review on January 1, 2027?

Public Chapter 1044, adopted in 2026, takes effect. Local staff must send written comments on site plans, preliminary plats and other non-legislative development applications within 30 business days and approve them or place them on an agenda within 60 business days; an application is approved automatically if either deadline is missed, and local governments may issue no more than two written deficiency notices (University of Tennessee Institute for Public Service, Public Chapter 1044 Policy Guide, June 2026). Rezonings and annexations are not covered, and neither are building, fire, mechanical, plumbing or electrical permits, which stay under the separate third-party rules.

Which building codes apply in Tennessee?

The State Fire Marshal’s Office, in the Department of Commerce and Insurance, has adopted the 2021 International Building, Fire, Existing Building, Mechanical, Plumbing, Fuel Gas and Property Maintenance Codes and the 2021 International Energy Conservation Code for commercial buildings, effective April 17, 2025. For one- and two-family dwellings and townhouses, the state code is the 2018 International Residential Code, effective July 16, 2020, and the electrical code is the 2017 National Electrical Code (Tennessee State Fire Marshal’s Office, Currently Adopted Codes). Cities and counties that enforce their own codes may adopt different editions, so ask the local building department which apply.

Sources

All figures on this page are drawn from Tenn. Code Ann. §68-120-101: statewide codes, the residential opt-out and third-party review, Tennessee State Fire Marshal’s Office, Department of Commerce and Insurance. The State Fire Marshal’s Office sets Tennessee’s statewide building standards. Counties and cities may exempt one- and two-family dwellings from them by a two-thirds vote, a resolution that expires 180 days after the next election of the local legislative body; owners in opt-out areas can request a state inspection. Since October 1, 2024, local programs have 10 business days to act on plans a registered third party has checked, or must refund plan review fees (§68-120-101(k)). www.tn.gov/commerce/fire/residential-permits/opt-out-jurisdictions.html. Specific tables, reports, and pages are cited inline with each figure above.

Every timeline here is a legal deadline or condition, not a measured outcome: no statewide data was found on how fast Tennessee local governments review plans or how often the 10-business-day third-party deadline is missed. The State Fire Marshal’s Office pages reviewed give no list or count of opt-out jurisdictions, so how many Tennesseans live in them is not stated here. Public Chapter 1044’s deadlines are given as summarized by the University of Tennessee Institute for Public Service, because the statute text could not be opened for this guide. The housing figure is the Census Bureau’s count of units authorized by permits in 2025; it measures volume, not speed, and is not comparable with any city’s review-time figures.