jurisdiction guide · utah

Utah Building Permit Timelines & Delays

In Utah, a city or county has 14 business days to finish plan review on a one- or two-family home or townhome, and 21 business days for other residential buildings, counted from the end of a three-business-day completeness check. If it misses the deadline on plans stamped by a licensed architect or structural engineer, it can’t enforce the plan review requirement and must give back the plan review fee. Inspections have a clock too: if the city or county can’t inspect within three business days of your request, you can hire a third-party inspection firm from the state’s list. These rules are in effect now (current text effective November 6, 2025).

Last reviewed November 14, 2026
headline figure
14 biz-d to review home and townhome plans; miss it on stamped plans and the fee is refunded
what to know
Utah cities and counties must finish plan review on a one- or two-family home or townhome within 14 business days, 21 for other residential buildings. If they miss it on plans stamped by a licensed architect or engineer, they can’t enforce plan review and must refund the fee.
data source
Utah Code §10-20-909 and §17-79-810: plan review deadlines; State Construction Code (Title 15A)
by the numbers

Utah permitting, the figures

The key published figures for this jurisdiction — each cited to its official source.

14 business days
Plan review deadline, homes and townhomes
One- or two-family dwellings and townhomes, after the three-business-day screening period; applies to cities and counties; current text effective November 6, 2025; a legal deadline, not a measured time
Source: Utah Code §10-20-909 and §17-79-810: plan review deadlines; State Construction Code (Title 15A) — Utah Code §10-20-909(4)(a); §17-79-810
21 business days
Plan review deadline, other residential
Other residential structures under the State Construction Code, excluding lodging establishments, after the screening period; cities and counties
Source: Utah Code §10-20-909 and §17-79-810: plan review deadlines; State Construction Code (Title 15A) — Utah Code §10-20-909(4)(b); §17-79-810
3 business days
Completeness screening period
The local government must decide within this period whether an application is complete; if it raises a deficiency after 5 p.m. on the last day, it must start plan review anyway
Source: Utah Code §10-20-909 and §17-79-810: plan review deadlines; State Construction Code (Title 15A) — Utah Code §10-20-909(1)(f), (3)
Fee refunded on stamped plans
If the deadline is missed
On plans stamped by a licensed architect or structural engineer, the city or county may not enforce the plan review requirement and must return the plan review fee
Source: Utah Code §10-20-909 and §17-79-810: plan review deadlines; State Construction Code (Title 15A) — Utah Code §10-20-909(8); §17-79-810
3 business days
Inspection wait before third-party option
If a city or county that charges an inspection fee can’t inspect within three business days of a request, the applicant may use a third-party inspection firm from the state’s list
Source: Utah Code §10-20-909 and §17-79-810: plan review deadlines; State Construction Code (Title 15A) — Utah Code §10-20-909(2); §17-79-810
65% of permit fee
City plan review fee cap
A city’s plan review fee may not exceed the lesser of the actual cost of the review or 65% of its building permit fee for that building
Source: Utah Code §10-20-909 and §17-79-810: plan review deadlines; State Construction Code (Title 15A) — Utah Code §10-20-904(1)
15 and 20 business days
Subdivision review, cities over 5,000
15 business days to review a complete application and 20 for improvement plans (30 and 40 in cities of 5,000 or fewer); single-family, two-family and townhome subdivisions; no more than four review cycles
Source: Utah Code §10-20-909 and §17-79-810: plan review deadlines; State Construction Code (Title 15A) — Utah Code §10-20-806
3,217
Salt Lake City housing units authorized, 2025
Up from 1,283 in 2024, the largest increase of any place in the West; units authorized by permit, a volume measure, not review time
Source: Utah Code §10-20-909 and §17-79-810: plan review deadlines; State Construction Code (Title 15A) — U.S. Census Bureau, Building Permits Survey, 2025 Annual Highlights
analysis

What the data shows

  • A Utah city or county must finish plan review within 14 business days for a one- or two-family home or townhome and 21 for other residential buildings, counted from the end of a three-business-day completeness check, and if it misses that on plans stamped by a licensed architect or structural engineer it may not enforce plan review and must refund the fee (Utah Code §10-20-909; §17-79-810, current text effective 2025).

  • Late objections don’t delay review: if a city or county flags a deficiency after 5 p.m. on the last screening day, it must begin plan review anyway, and for homes and townhomes they may require only a single resubmittal, and only for deficiencies that affect the site plan or the building’s footprint (Utah Code §10-20-909, 2025).

  • For single-family, two-family and townhome subdivisions, cities of more than 5,000 people must review a complete application within 15 business days and improvement plans within 20 (30 and 40 in smaller cities), with no more than four review cycles; separately, if a city doesn’t answer a written completeness request within 30 days with a deficiency notice, the application is considered complete (Utah Code §10-20-806; §10-20-905, 2025).

  • Since July 1, 2026, commercial and multifamily buildings in Utah follow the 2024 International Building Code and related 2024 codes with the 2023 National Electrical Code, while homes and townhomes remain on the 2021 International Residential Code, and cities and counties may not adopt stricter rules on subjects the state code covers (Utah Code §15A-2-103; §15A-1-204, 2026).

how Permavia helps in utah

Most delay accumulates before technical review

The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.

frequently asked

Utah permitting: FAQ

How fast must a Utah city or county review building plans?

Within 14 business days for a one- or two-family home or townhome and 21 business days for other residential buildings, excluding lodging establishments, counted after a three-business-day screening period in which the local government decides whether the application is complete (Utah Code §10-20-909(4) for cities; §17-79-810 for counties). If it flags a deficiency after 5 p.m. on the last screening day, it must start the review anyway; it may pause the clock only within the review’s last five days, until the missing information arrives. An applicant can waive these deadlines or agree in writing to a different timeline.

What happens if a Utah city or county misses the plan review deadline?

If the plans carry a licensed architect’s or structural engineer’s stamp, the city or county may not enforce the plan review requirement and must return the plan review fee (Utah Code §10-20-909(8); §17-79-810). Separately, if it can’t perform a requested inspection within three business days, the applicant may hire a third-party inspection firm from the state’s list (Utah Code §10-20-909(2)).

Which building codes apply in Utah?

Since July 1, 2026, the State Construction Code adopts the 2024 International Building, Plumbing, Mechanical, Fuel Gas, Energy Conservation and Existing Building Codes and the 2023 National Electrical Code, while one- and two-family homes and townhomes stay on the 2021 International Residential Code, all with Utah amendments (Utah Code §15A-2-103, as amended by H.B. 65, 2026). The Legislature adopts the code by statute on recommendations from the Uniform Building Code Commission, and cities and counties may not adopt or enforce rules stricter than the state code on subjects it specifically addresses (Utah Code §15A-1-204).

Are there deadlines for subdivision review in Utah?

Yes, for single-family, two-family and townhome subdivisions. A city of more than 5,000 people must review a complete application within 15 business days and improvement plans within 20 business days (30 and 40 in cities of 5,000 or fewer), may require no more than four review cycles, and if it misses the 20-business-day deadline on the final review, the owner can ask it to convene an appeal panel or put the deficiencies and appeal rights in writing within 10 business days (Utah Code §10-20-806). For any land use application, if a city doesn’t answer a written completeness request within 30 days with a deficiency notice, the application is considered complete, though the law allows no money damages (Utah Code §10-20-905).

Sources

All figures on this page are drawn from Utah Code §10-20-909 and §17-79-810: plan review deadlines; State Construction Code (Title 15A), Utah State Legislature (Utah Code). Cities (§10-20-909) and counties (§17-79-810) must finish plan review within 14 business days for one- or two-family homes and townhomes and 21 for other residential buildings, after a three-business-day screening period; if they miss it on stamped plans, they may not enforce plan review and must refund the fee (current text effective November 6, 2025, renumbered from §10-6-160 and §17-36-55). Subdivision review deadlines are in §10-20-806, application completeness in §10-20-905, and the State Construction Code editions in §15A-2-103 (2024 International Building Code and 2021 International Residential Code since July 1, 2026). le.utah.gov/xcode/Title10/Chapter20/C10-20-S909_2025110620251206.html. Specific tables, reports, and pages are cited inline with each figure above.

Every day count here is a legal deadline, not a measured result: no statewide data on how fast Utah cities and counties actually review plans, or how often they miss the deadlines, was found. State law now requires the Uniform Building Code Commission to publish an annual report on local building regulators’ performance before October 1, but no such report was located for this guide. Utah renumbered its city and county land use laws effective November 6, 2025 (for example, the plan review section moved from §10-6-160 to §10-20-909 for cities and from §17-36-55 to §17-79-810 for counties), so older documents cite the former numbers. The Salt Lake City figure counts housing units authorized by permit in 2025, a volume measure, and is not comparable with any review time.