Michigan Building Permit Timelines & Delays
In Michigan, the building department has 10 business days to grant or deny a permit application, or 15 for an unusually complicated building, but a missed deadline counts as a denial, not an approval: your remedy is an appeal to the board of appeals. New houses are still reviewed under the 2015 Michigan Residential Code, because a court order in a home builders’ lawsuit has kept the state from moving ahead with its updated residential and energy rules since July 2025, while commercial buildings moved to the 2021 Michigan Building Code on April 9, 2025.
Michigan permitting, the figures
The key published figures for this jurisdiction — each cited to its official source.
What the data shows
A Michigan building department must grant, in whole or in part, or deny a permit application within 10 business days, or 15 for an unusually complicated building or structure; if it doesn’t, the application is treated as denied so the applicant can appeal to the board of appeals, not approved (Single State Construction Code Act, MCL 125.1511, 1972).
New houses are still reviewed under the 2015 Michigan Residential Code, in effect since February 8, 2016: a stipulated Court of Claims order of July 7, 2025, in lawsuits brought by home builders, keeps the state from moving ahead with its updated residential and residential energy rules while the cases continue, though commercial buildings moved to the 2021 Michigan Building Code on April 9, 2025 (Michigan LARA, Bureau of Construction Codes, 2026).
Since July 21, 2026, an apartment building with no more than four levels above grade, four units and 4,000 square feet per level may use a single interior exit stair if it has a manual fire alarm with automatic smoke detection, a travel distance of no more than 125 feet and a stair at least 48 inches wide, among other conditions; the rule ends once the state adopts the International Code Council’s own single-stair provision (Michigan PA 28 and PA 29 of 2026).
One code applies throughout the state, enforced either by a building department that a city, village, township or county set up by ordinance or, where none has, by the state’s Bureau of Construction Codes, and permit fees must be intended to bear a reasonable relation to the cost of the service, including overhead (MCL 125.1508a, 125.1508b and 125.1522; Michigan Compiled Laws, 2025).
Most delay accumulates before technical review
The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.
Michigan permitting: FAQ
Does Michigan have a deadline to decide a building permit?
Yes. Under the Stille-DeRossett-Hale Single State Construction Code Act, the building department must grant, in whole or in part, or deny a permit application within 10 business days, or within 15 business days for an unusually complicated building or structure (MCL 125.1511). If it misses the deadline, the application is treated as denied so you can appeal to the board of appeals; it is not approved automatically.
Which building code applies to a new house in Michigan?
The 2015 Michigan Residential Code, in effect since February 8, 2016, which also carries the residential energy requirements. The state proposed updated residential and residential energy rules, but a stipulated Court of Claims order of July 7, 2025, in lawsuits brought by home builders, keeps it from moving ahead with them while the cases continue, and the 2015 provisions stay in effect (Michigan LARA, Bureau of Construction Codes). Commercial buildings follow the 2021 Michigan Building Code (since April 9, 2025) and the 2021 Michigan Commercial Energy Code (since April 22, 2025); plumbing and mechanical work follows the 2021 Michigan codes, and electrical work the 2023 National Electrical Code with Michigan rules, all since March 12, 2024. Moving plumbing and mechanical to the 2024 International codes is only proposed (public hearings were scheduled for August 5, 2026).
Can an apartment building in Michigan have just one stairway?
Yes, since July 21, 2026, if it is small enough. A multifamily building with no more than four levels above grade plane, no more than four units and 4,000 square feet per level may have a single interior exit stair if it meets every condition in the law, including a manual fire alarm and automatic smoke detection, a travel distance of no more than 125 feet, sprinklers in the stair placed to the national fire sprinkler standard, no elevator opening into it and a stair at least 48 inches wide (Michigan PA 28 of 2026, MCL 125.1504j). The rule stops applying once the state adopts the International Code Council’s single-stair provision into the code (PA 29 of 2026, MCL 125.1504k).
Who issues building permits in Michigan, and what can they charge?
Usually your city, village, township or county, if it has chosen by ordinance to enforce the state code; where it hasn’t, the state Bureau of Construction Codes does (MCL 125.1508b), and the bureau tells applicants to check its Statewide Jurisdiction List before applying. Fees are set by the local legislative body and must be intended to bear a reasonable relation to the cost of the service, including overhead, and may pay only for the building department or board of appeals (MCL 125.1522). The state publishes no measured review times; Detroit said in March 2026 that inspectors could approve most renovation permits in the field the same day (City of Detroit, 2026).
Sources
All figures on this page are drawn from Michigan Single State Construction Code Act (1972 PA 230) & the 10-business-day permit clock, Michigan Legislature / Michigan LARA, Bureau of Construction Codes. Under the Stille-DeRossett-Hale Single State Construction Code Act (1972 PA 230; MCL 125.1501 et seq.), one code applies throughout the state (MCL 125.1508a); a city, village, township or county may enforce it by ordinance, and LARA’s Bureau of Construction Codes enforces it where none does (MCL 125.1508b). The building department must grant, in whole or in part, or deny a permit application within 10 business days, or 15 for an unusually complicated building or structure; a missed deadline is deemed a denial for purposes of an appeal (MCL 125.1511). www.legislature.mi.gov/Laws/MCL?objectName=mcl-125-1511. Specific tables, reports, and pages are cited inline with each figure above.
The 10- and 15-business-day figures are legal deadlines with a deemed-denial appeal remedy, not measured turnaround times; no statewide data was found on how quickly Michigan building departments decide permits, and the state Bureau of Construction Codes publishes no review times. Detroit’s same-day and up-to-30-day figures come from the city’s March 2026 announcement, not a measured series, so they can’t be compared with the state deadline or with other guides.
- Michigan Legislature: MCL 125.1511 (10- and 15-business-day permit decision)
- Michigan LARA, Bureau of Construction Codes: codes currently in effect
- Michigan LARA, Bureau of Construction Codes: rules currently open (residential code on hold)
- Michigan Legislature: Public Act 28 of 2026 (single interior exit stairway)