California Building Permit Timelines & Delays
A contested California housing project can spend three to five years in court: that is how long the state says lawsuits under the California Environmental Quality Act (CEQA) take outside its fast track, which aims for about 270 days. Two newer rules help housing builders: since July 1, 2025, qualifying infill housing on sites of up to 20 acres is exempt from CEQA, and from January 1, 2027, agencies may not require more than two plan check reviews for a housing project’s building permit.
California permitting, the figures
The key published figures for this jurisdiction — each cited to its official source.
What the data shows
Outside the state’s judicial streamlining program, a lawsuit under the California Environmental Quality Act takes three to five years, the state says, against a target of about 270 days for projects the Governor certifies (Governor’s Office of Land Use and Climate Innovation, 2025).
Where SB 35 streamlining applied, median approval time in Los Angeles fell to 2.7 months, down from roughly seven months for comparable earlier projects (NYU Furman Center / Pew, 2024).
CEQA lawsuits filed in 2020 sought to block an estimated 48,000 approved housing units, just under half of California’s housing production, according to a study by Jennifer Hernandez, a Holland & Knight land-use partner who works for private sector, public agency and nonprofit clients on housing and other projects, the kind of projects such suits can delay; it counts units named in lawsuits, not units the suits actually stopped (Chapman Law Review, 2022).
Accessory dwelling units took an average of 260 days to permit inside Los Angeles County’s Coastal Zone versus 147 days outside it, for permits from 2018 to 2022 (Terner Center, 2024).
Most delay accumulates before technical review
The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.
California permitting: FAQ
How long do housing approvals take in California?
The state publishes no statewide approval-duration figure, and times vary by project, city, and approval pathway. A contested project can spend three to five years in CEQA litigation (Governor’s Office of Land Use and Climate Innovation, 2025), while under SB 35, Los Angeles approvals cleared in a median of 2.7 months, versus roughly seven months for comparable earlier projects (NYU Furman Center / Pew, 2024).
Why does CEQA add so much delay?
The California Environmental Quality Act lets opponents sue to block an approved project, and the state says those suits take three to five years unless a project qualifies for its fast track (Governor’s Office of Land Use and Climate Innovation, 2025). A study by Jennifer Hernandez, a Holland & Knight land-use partner who works for private sector, public agency and nonprofit clients on housing and other projects, estimated that 2020 lawsuits sought to block about 48,000 approved housing units, just under half the state’s housing production; it counts units named in suits, not units stopped (Chapman Law Review, 2022).
Did the 2025 CEQA reforms change anything?
Yes. AB 130 and SB 131 were signed June 30, 2025 and took effect July 1, 2025; SB 158, signed Oct 11, 2025, amended several of their provisions (Association of Bay Area Governments, 2025; County of San Mateo, 2025). AB 130 exempts qualifying infill housing on sites of up to 20 acres from CEQA and applies Permit Streamlining Act deadlines to housing entitlements, with a 60-day deadline for ministerial permits (Senate Budget Committee, 2025; County of San Mateo, 2025). Separately, for projects the Governor certifies for judicial streamlining, a program that predates the 2025 reforms and now lists AB 130 among its governing laws, courts are meant to resolve CEQA lawsuits in about 270 days rather than three to five years (Governor’s Office of Land Use and Climate Innovation, 2025).
Has streamlining actually sped things up?
Yes, where it applies. Under SB 35, median approval time fell to 2.7 months in Los Angeles and about four months in San Francisco, versus baselines of roughly seven months and “more than a year” (NYU Furman Center / Pew, 2024). Separately, Gov. Code § 65913.3, added by AB 2234, requires agencies to act on post-entitlement permits within 30 business days of a complete application for projects of 25 units or fewer and 60 business days for 26 or more (AB 2234, 2022). AB 1621 (Ch. 780, Stats. 2026), signed Sept 29, 2026 and in effect from Jan 1, 2027, keeps those limits, bars agencies from requiring more than two plan check reviews for a housing project’s building permit, shortens appeal decisions to 30 business days for 25 units or fewer and 45 for 26 or more (from 60 and 90), and lets an applicant seek a writ of mandate if an appeal is denied or not decided in time (AB 1621, 2026).
Sources
All figures on this page are drawn from CEQA Judicial Streamlining (factsheet), California Governor’s Office of Land Use and Climate Innovation. The state’s summary of its CEQA judicial streamlining program: certified projects aim for lawsuits resolved in about 270 days, against three to five years otherwise. Statutory deadlines and research figures on the guide are cited inline. www.lci.ca.gov/ceqa/judicial-streamlining/docs/20251021-Judicial_Streamlining_Factsheet.pdf. Specific tables, reports, and pages are cited inline with each figure above.
Figures come from independent studies and state sources with different scopes, years, and methods, so they are not directly comparable: the SB 35 figures reflect small samples of mostly affordable projects approved under the law (18 in Los Angeles; 10 in San Francisco, nine with timing data), compared with a few similar earlier projects (11 in Los Angeles; one in San Francisco, from 2014–2017), and the CEQA-litigation figures count lawsuits rather than all projects. The 270-day court target, the 30–60 business-day permit deadlines and AB 1621’s limit of two plan check reviews (from Jan 1, 2027) are targets set by the state and by statute, not measured outcomes. The 48,000-unit figure is an estimate from a study by Jennifer Hernandez, a Holland & Knight land-use partner who works for private sector, public agency and nonprofit clients on housing and other projects, of lawsuits filed in 2019–2021; it counts housing units named in lawsuits filed in 2020, not units the suits stopped, and is not a state figure. The ADU figures are a Terner Center analysis of data that cities and counties report to the California Department of Housing and Community Development (HCD), which publishes application, entitlement, permit, and completion data but no statewide approval-duration figure.
- Association of Bay Area Governments: Assembly Bill (AB) 130 and Senate Bill (SB) 131 (technical assistance, updated Dec 2025)
- County of San Mateo Planning and Building: AB 130 and SB 131, housing and public resources budget trailer bills (2025, with SB 158 amendments)
- Pew / NYU Furman Center: Reforms Spur Faster Housing Approvals in California (2024)
- Hernandez, “In the Name of the Environment Part III: CEQA, Housing, and the Rule of Law,” Chapman Law Review 26:1 (2022), study by a Holland & Knight partner (PDF hosted by the firm)