jurisdiction guide · texas

Texas Building Permit Timelines & Delays

Texas doesn't publish a statewide permit-timing dataset, but it has done something unusual: written an escape hatch into law. When a city or county sits on a development application, the Legislature’s 2023 answer was to let the applicant route around it entirely.

Last reviewed October 28, 2026
headline figure
hire your own reviewer when the city blows the deadline by 15 days
what to know
Texas lets applicants route around a slow city: miss a review deadline by 15 days and a developer can bring in a licensed engineer or ICC-certified inspector, at no added fee.
data source
Tex. Local Gov't Code ch. 247: Third-Party Review of Development Documents
by the numbers

Texas permitting, the figures

The key published figures for this jurisdiction — each cited to its official source.

15 days late
Third-party review trigger
Past a deadline already set elsewhere in the Local Government Code
Source: Tex. Local Gov't Code ch. 247: Third-Party Review of Development Documents — Tex. Local Gov't Code §247.002
$0
Added fee for third-party review
The regulatory authority may not charge for the review or inspection
Source: Tex. Local Gov't Code ch. 247: Third-Party Review of Development Documents — Tex. Local Gov't Code §247.003
P.E., ICC or approved staff
Qualified reviewer / inspector
A licensed engineer, or a plan reviewer or building inspector employed by the city or county or by another government it approves; inspectors may also be ICC-certified. Never the applicant or anyone whose work is under review
Source: Tex. Local Gov't Code ch. 247: Third-Party Review of Development Documents — Tex. Local Gov’t Code §247.002
60 days
Appeal / deemed-approved backstop
If the governing body doesn't affirm an appealed decision within 60 days, the document is approved or the inspection waived
Source: Tex. Local Gov't Code ch. 247: Third-Party Review of Development Documents — Tex. Local Gov't Code §247.006
30 days
Plat decision deadline
Approve, conditionally approve, or disapprove, or it's deemed approved
Source: Tex. Local Gov't Code ch. 247: Third-Party Review of Development Documents — Tex. Local Gov't Code §§212.009, 212.0091
Prohibited
Waiver of the deadlines
A city may not require an applicant to waive these timelines
Source: Tex. Local Gov't Code ch. 247: Third-Party Review of Development Documents — Tex. Local Gov't Code §247.005
analysis

What the data shows

  • Since September 1, 2023, when a Texas regulatory authority fails to act on a development document within 15 days after an applicable Local Government Code deadline, the applicant may have the review or inspection performed by a qualified third party (Tex. Local Gov't Code §247.002; HB 14, 88th Leg., R.S.).

  • The city is barred from charging an additional fee for that third-party review or inspection (Tex. Local Gov't Code §247.003), and it may not require the applicant to waive the deadlines (§247.005).

  • A third party's decision can be appealed to the governing body; if the body does not affirm it by majority vote within 60 days, the document is deemed approved or the inspection waived (Tex. Local Gov't Code §247.006).

  • Separately, Texas’s long-standing plat rule requires a municipal authority to approve, conditionally approve, or disapprove a plat within 30 days of filing, or it is deemed approved (Tex. Local Gov’t Code §§212.009, 212.0091).

  • Since September 1, 2025, home backup power systems (generators, batteries and standby systems serving a one- or two-family home) don’t have to wait for a missed deadline: a qualified third party, including a master electrician, can review and inspect them without first going to the city or county, which must then issue the permit or approval within three business days of getting the results (Tex. Local Gov’t Code §247.0025; SB 1202, 89th Leg., R.S.).

how Permavia helps in texas

Most delay accumulates before technical review

The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.

frequently asked

Texas permitting: FAQ

Can a builder really bypass the city in Texas?

In a narrow, defined way, yes. Under Local Government Code ch. 247 (HB 14, 2023), if a regulatory authority misses an applicable review deadline by 15 days, a qualified third party may perform the review or inspection instead (a licensed engineer, or a plan reviewer or building inspector employed by the city or county or by another government it approves; inspections can also go to an ICC-certified inspector) and the city may not charge an extra fee for it (Tex. Local Gov’t Code §§247.002–247.004). It is a statutory remedy with an appeal process, not a free-for-all.

Does the city have to accept the third party's results?

Not automatically. The third party must give the regulatory authority notice of the results, and a decision may be appealed to the governing body. If the governing body does not affirm the appealed decision by a majority vote within 60 days, the development document is deemed approved or the inspection is waived (Tex. Local Gov't Code §247.006).

What is Texas's 30-day plat rule?

Under Local Government Code §212.009, a municipal authority must approve, conditionally approve, or disapprove a plat within 30 days after it is filed; §212.0091 requires any disapproval to be in writing with specific reasons. Miss the window and the plat is deemed approved. This is a separate, older shot clock from the ch. 247 third-party remedy.

Is chapter 245 a permit deadline?

No. That's a common misconception. Chapter 245 is Texas's vested-rights (“permit freeze”) statute: filing an application freezes the regulations that apply to a project. It does not impose a review deadline or a deemed-approved clock. The timing tools are ch. 247 (third-party remedy) and ch. 212 (plats).

Sources

All figures on this page are drawn from Tex. Local Gov't Code ch. 247: Third-Party Review of Development Documents, Texas Legislature (Texas Legislative Council). Created by HB 14, 88th Legislature, R.S. (2023), effective September 1, 2023: when a regulatory authority misses an applicable review deadline by 15 days, the applicant may use a qualified third-party reviewer or inspector at no added fee, subject to a governing-body appeal with a 60-day deemed-approved backstop. SB 1202 (2025), effective September 1, 2025, added §247.0025, which lets qualified third parties review and inspect home backup power installations without waiting for a missed deadline. Texas’s separate 30-day plat shot clock lives in ch. 212. tcss.legis.texas.gov/resources/LG/pdf/LG.247.pdf. Specific tables, reports, and pages are cited inline with each figure above.

These are statutory rights and deadlines, not measured outcomes: Texas does not publish a standardized statewide permit-turnaround dataset, so the figures describe what the law allows, not observed average review times. The third-party remedy and its 60-day appeal backstop come from HB 14 (2023) / Local Government Code ch. 247; the 30-day plat rule is the separate, pre-existing ch. 212. (Local permit-fee calculation was addressed separately by HB 3492, 2023.)