San Diego Building Permit Timelines & Delays
San Diego reports that staff review of 100%-affordable housing and shelter projects averages nine days, well inside the City’s commitment to a first review within 30 business days. As of March 2024, more than half of all its permits were issued the same day.
San Diego permitting, the figures
The key published figures for this jurisdiction — each cited to its official source.
What the data shows
San Diego’s Affordable Housing Permit Now program commits to a first review of 100%-affordable and shelter projects within 30 business days, reports an average staff review of nine days, and counts 7,481 homes it has helped permit since its 2023 launch (City of San Diego, 2026).
Outside the fast lanes, standard first reviews completed in the 30 days before Oct 31, 2026 averaged 8–32 calendar days by discipline, with planning at 19 days and electrical at 32 (City of San Diego DSD, 2026).
Unlike Los Angeles County (260 vs. 147 days) and Orange County (233 vs. 101 days), San Diego County showed no statistically significant difference in average ADU permitting time inside versus outside the Coastal Zone for 2018–2022 (Terner Center, 2024).
San Diego has pivoted sharply from single-family homes to ADUs: single-family units permitted fell from 864 in 2016 to 132 in 2024, while ADU permits rose from zero to 2,107 (Terner Center, 2025).
Most delay accumulates before technical review
The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.
San Diego permitting: FAQ
How long does a building permit take in San Diego?
It depends on the lane. As of March 2024 more than half of all DSD permits were issued the same day, and 100%-affordable projects average about nine days of staff review against a 30-business-day first-review commitment (City of San Diego, 2024–2026). Standard projects go through review by discipline: in the 30 days before Oct 31, 2026, first reviews averaged 8–32 calendar days and rechecks 6–25 days, so total time depends on how many correction rounds a project needs (City of San Diego DSD, 2026).
Does San Diego have a fast-track for affordable housing?
Yes. Mayor Todd Gloria’s Executive Order 2023-1, in effect since 11:59 p.m. on Jan 11, 2023, orders the City to conclude all reviews of 100 percent affordable housing projects, and issue approvals or requests for corrections, within 30 business days of the deemed-complete date, and to process their building permit and certificate of occupancy applications within 5 business days (2 for emergency shelters) (City of San Diego, Executive Order 2023-1). The Development Services Department runs the fast track as Affordable Housing Permit Now, which promises a first review of 100% affordable and shelter projects within 30 business days, and the City reports an average staff-review time of nine days (City of San Diego, 2026). The City says the program has helped permit 7,481 homes since its launch; its June 2026 tally of 7,246 included 2,809 homes still in review and 2,848 completed (City of San Diego, 2026). The City’s budget separately reports an average of 12.43 days per review cycle for 100%-affordable projects in FY2026 (City of San Diego, FY2027 Adopted Budget).
Is the coastal zone a permitting bottleneck in San Diego?
Less than in peer regions. The Terner Center found no statistically significant difference in average ADU permitting time inside versus outside the Coastal Zone across San Diego County for 2018–2022, whereas Orange County averaged 233 days inside the Coastal Zone versus 101 days outside (Terner Center, 2024).
Where can I see current San Diego permit times?
The City of San Diego Development Services Department publishes a weekly Permit Processing Timeline, with intake, review by discipline and issuance shown separately, and a Permitting Center Dashboard with processing times by permit category, both on sandiego.gov (City of San Diego DSD, 2026).
Sources
All figures on this page are drawn from Development Services permit performance & Affordable Housing Permit Now, City of San Diego, Development Services Department. Official DSD permit-processing timeline plus the City’s reporting on same-day issuance and its affordable-housing fast track (Affordable Housing Permit Now, with a first review within 30 business days). www.sandiego.gov/development-services/permits/timeline. Specific tables, reports, and pages are cited inline with each figure above.
Figures come from different programs, periods and clocks and are not directly comparable. The nine-day figure is the City’s program average for staff review in the affordable fast-track lane, measured against a 30-business-day first-review commitment; the budget’s 12.43 days is a different measure, the FY2026 average time per review cycle. The executive order’s 30 business days run from the deemed-complete date and are a mandated limit, not a measured outcome. The same-day share is a March 2024 figure for all DSD permits and does not describe correction-heavy projects. The DSD weekly timeline reports intake and review in calendar days and issuance in approximate business days, as separate estimates rather than a single end-to-end figure. The Terner Center coastal-zone comparison covers ADUs across San Diego County, not only the city.