Sacramento Building Permit Timelines & Delays
The City of Sacramento reports that 98.5% of its plan reviews finish on time or early, but its published targets apply to each review cycle, not to the whole permit, so a permit’s real timeline depends on how many rounds of corrections the plans need. For a new home, the Community Development Department targets 20 working days for the first cycle, then 15 for the second and 5 for the third.
Sacramento permitting, the figures
The key published figures for this jurisdiction — each cited to its official source.
What the data shows
Sacramento reports that 98.5% of its roughly 23,000 annual plan reviews are completed on time or early, above the department’s 90% goal, though the report does not state the period measured (Sacramento City Council report 2025-01833, 2026).
A new single-family home faces a 20-working-day first plan-review target, followed by 15- and 5-day targets for any second and third correction cycles, so each extra round adds time rather than counting against one overall clock (Sacramento CDD, Form CDD-0294, 2026).
Residential solar PV, battery storage and EV-charger reviews target 24 hours per cycle, and eligible small projects in Small Project Rapid Review are reviewed within 1–3 business days for an expedited fee (Sacramento CDD, 2026).
Under state law enacted in 2022 and in effect as of October 2026, cities have 30 business days after a complete application to review post-entitlement permits for housing of 25 units or fewer and 60 business days for larger projects (Cal. Gov. Code §65913.3, per Assembly Housing Committee analysis, 2026).
Most delay accumulates before technical review
The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.
Sacramento permitting: FAQ
How long does plan review take for a new house in Sacramento?
The City targets 20 working days to complete the first review cycle on a new residential building, then 15 for a second cycle and 5 for a third if corrections are needed (Sacramento CDD, Form CDD-0294, 2026). These targets require a complete submittal, and the Chief Building Official or Supervising Engineer may adjust them up or down.
Does the timeline restart every time I resubmit corrected plans?
Effectively yes: the city sets a separate target for each cycle (20, then 15, then 5 working days for a new home), so projects that don’t pass on the first try accumulate review time (Sacramento CDD, Form CDD-0294, 2026).
Is there a legal maximum on how long Sacramento can take?
For qualifying housing, yes. As of October 2026, Government Code §65913.3, enacted by AB 2234 (Chapter 651, Statutes of 2022), requires a city to complete its review within 30 business days of a complete application for projects of 25 units or fewer and 60 business days for 26 or more units (Senate Housing Committee analysis of AB 2234, 2022; Assembly Housing Committee analysis, 2026). Whether the City meets this clock is not publicly reported.
Which permits are fastest in Sacramento?
Residential solar PV, battery storage and EV-charging permits carry a 24-hour target per review cycle, and patio covers, carports, decks and revisions target 5 working days per cycle (Sacramento CDD, Form CDD-0294, 2026). Eligible minor projects, such as residential remodels with minor structural changes, or outdoor pools and spas, can use Small Project Rapid Review, which reviews plans within 1–3 business days for an expedited fee (Sacramento CDD, 2026).
Sources
All figures on this page are drawn from Cycle Times for Building Plan Review (Form CDD-0294, revised March 4, 2026), City of Sacramento, Community Development Department. The City's official plan-review cycle-time schedule by project type, in working days per review cycle; figures are targets that require a complete submittal and may be adjusted by the Chief Building Official or Supervising Engineer. www.cityofsacramento.gov/content/dam/portal/cdd/Building/Forms/CDD-0294_Projected-Cycle-Times-for-Building-Plan-Review.pdf. Specific tables, reports, and pages are cited inline with each figure above.
Cycle times are the City’s published targets (Form CDD-0294, revised March 4, 2026): they cover building plan review cycles only, require a complete submittal, and may be adjusted by the Chief Building Official or Supervising Engineer; projects over $75 million get project-specific cycle times. The 98.5% on-time rate is the City’s own measured figure, reported to the City Council in February 2026 without a stated period; the report does not say which targets it measured (plan review there spans several City departments), it does not measure total time to permit, and it does not report compliance with the state’s §65913.3 clock. The City’s issued-permit open dataset carries a status date but no application or review dates, so measured review days could not be derived from it. Targets and methods differ by city, so these figures are not comparable across jurisdictions.