Permittable is now Permavia. Read about our new name

jurisdiction guide · colorado

Greeley Building Permit Review Times

Plan on about four weeks of plan review for a new building in Greeley, Colorado: the City lists typical plan review at 20 working days for new commercial and residential construction, and 10 working days for additions, remodels, tenant finishes and residential footing-and-foundation permits (as of October 2026).

Last reviewed October 28, 2026
headline figure
10–20 working-day plan review typical building plan review, 10–20 working days
what to know
Greeley lists typical building plan review at 20 working days for new construction and 10 working days for additions, remodels and tenant finishes (as of October 2026).
data source
Building Permits and Inspections: Typical Plan Review Timelines
by the numbers

Greeley permitting, the figures

The key published figures for this jurisdiction — each cited to its official source.

20 working days
New construction plan review
typical; new commercial and residential construction
Source: Building Permits and Inspections: Typical Plan Review Timelines — City of Greeley, Building Permits and Inspections: Typical Plan Review Timelines (as of Oct 2026)
10 working days
Additions, remodels, tenant finishes
typical; also residential footing and foundation
Source: Building Permits and Inspections: Typical Plan Review Timelines — City of Greeley, Building Permits and Inspections: Typical Plan Review Timelines (as of Oct 2026)
analysis

What the data shows

  • Greeley lists typical building plan review at 20 working days for new commercial and residential construction and 10 working days for additions, remodels, tenant finishes and residential footing and foundation work; reviews by other City departments can extend that (City of Greeley, 2026).

  • A review is scheduled only after a complete submittal: an incomplete application delays the start of the review window.

  • Land-use (planning) submittals run on a separate clock: they are typically scheduled for a two-week review, except the first round, which takes three weeks (City of Greeley, 2026).

how Permavia helps in greeley

Most delay accumulates before technical review

The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.

frequently asked

Greeley permitting: FAQ

How long does building permit review take in Greeley?

The City of Greeley lists typical plan review at 20 working days for new commercial and residential construction and 10 working days for additions, remodels, tenant finishes and residential footing and foundation permits (as of October 2026). Reviews by other City departments can add time.

What can delay a Greeley review?

An incomplete submittal: the City starts a review only once all required items are submitted, so missing materials push back the start of the review clock. Reviews by other City departments can also extend the timeframe.

Sources

All figures on this page are drawn from Building Permits and Inspections: Typical Plan Review Timelines, City of Greeley, Community Development. City page listing typical plan review timelines (20 working days for new commercial and residential construction; 10 working days for residential footing and foundation, residential additions or remodels, and commercial tenant finish, addition or remodel) and stating that review begins only after a complete submittal; retrieved October 28, 2026. greeleyco.gov/business/construction-and-growth/building-permits-and-inspections. Specific tables, reports, and pages are cited inline with each figure above.

The 10- and 20-working-day figures are the City of Greeley’s published typical plan review timelines for complete building permit submittals (as of October 2026), not measured averages or a statutory deadline; the City’s permit pages do not say how often it meets them. Source: City of Greeley, Building Permits and Inspections.