Key West Building Permit Timelines & Delays
In Key West, the wait to build a new home starts before plan review: every new house, apartment or guest unit needs a building allocation from a state-capped pool, and the city awards them only once a year. The current round closed to applications on November 6, 2026 and the Planning Board decides awards in May 2027, so a builder who misses the deadline loses a full year.
Key West permitting, the figures
The key published figures for this jurisdiction — each cited to its official source.
What the data shows
Every new permanent or transient residential unit in Key West needs a BPAS allocation, and allocations are awarded once a year: Year 14 applications were due November 6, 2026, with Planning Board awards in May 2027 (City of Key West, BPAS Year 14 Schedule, 2026).
The state’s ten-year grant of up to 91 units a year ran from July 2013 to June 2023; across Years 1–13 the city has allocated 1,019.32 units, about 68% deed-restricted affordable, and the 2025–26 round awarded 4 units at the Planning Board (City of Key West, 2026 BPAS Annual Report).
Since Ordinances 23-03 and 23-04, 75% of units allocated after Year 10 must be deed-restricted affordable, leaving market-rate homes at most a quarter of new allocations (City of Key West, BPAS Year 14 Schedule, 2026).
An award is not a permit: the building permit must be issued within two years of the Planning Board’s final award, or the units return to the city for the next award year (City of Key West, BPAS Recovered Units, Penalties & Enforcement, 2026).
Florida’s SB 180 raised the Keys’ hurricane evacuation clearance time from 24 to 24.5 hours and allows up to 900 new allocations over 10 years; local news reports Key West’s share as 36 over the decade, released from January 1, 2026 (Florida Senate, 2025; Keys Weekly, 2025).
Most delay accumulates before technical review
The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.
Key West permitting: FAQ
Why does building a new home in Key West take so long?
Because a permit for any new permanent or transient residential unit first needs a Building Permit Allocation System (BPAS) award, and the city awards them once a year (City of Key West, Development Subjected to BPAS). For Year 14, applications opened July 1, 2026 and closed November 6, 2026; staff send an initial ranking January 15, 2027 and the Planning Board makes the final award in May 2027 (BPAS Year 14 Schedule). Replacing existing units without adding any, public uses, holders of an unexpired vested rights order, and units in existence at the April 1, 2010 Census are not subject to BPAS.
How many new units does Key West award each year?
From July 2013 to June 2023 the state allowed the city up to 91 new units a year (City of Key West, Annual Allocation Schedule). Recent rounds have been much smaller: Year 13 (2025–26) awarded 1 market-rate and 3 affordable units at the Planning Board, plus 1.78 affordable units approved by staff (City of Key West, 2026 BPAS Annual Report). Under Ordinances 23-03 and 23-04, 75% of units allocated after Year 10 must be deed-restricted affordable (BPAS Year 14 Schedule). The city does not state how many units are available in Year 14.
Is Key West’s BPAS the same as Monroe County’s ROGO?
No. The City of Key West awards its own allocations under its Code of Ordinances (Sections 108-995 and 108-997), while Monroe County runs ROGO for the unincorporated Keys, and Marathon and Islamorada run their own allocation systems. Their pools and counts are separate: of the 900 allocations created by SB 180, local news reports 36 for Key West, 657 for unincorporated Monroe County, 135 for Marathon and 72 for Islamorada over the next decade (Keys Weekly, Dec 19, 2025).
Did Florida add building capacity for Key West?
Yes, a little. SB 180 (ch. 2025-190, approved June 26, 2025) raised the Florida Keys’ hurricane evacuation clearance time from 24 to 24.5 hours and allows up to 900 new allocations, distributed over 10 years (Florida Senate, SB 180 bill summary). The Governor and Cabinet approved the distribution on December 17, 2025: 300 units available from January 1, 2026, then 150 every two years through 2035, with Key West’s share reported as 36 (Keys Weekly, Dec 19, 2025). As written, the law allows one new right per vacant buildable lot.
Sources
All figures on this page are drawn from Building Permit Allocation System (BPAS), City of Key West, FL, Planning Department. Key West’s annual award of state-capped allocations required for every new permanent or transient residential unit (up to 91 units a year, July 2013–June 2023). The 2026 BPAS Annual Report counts 1,019.32 units allocated in Years 1–13, about 68% deed-restricted affordable; Year 14 (2026–27) applications were due November 6, 2026. Separate from Monroe County’s ROGO. cityofkeywest-fl.gov/336/Building-Permit-Allocation-System-BPAS. Specific tables, reports, and pages are cited inline with each figure above.
These are allocation counts and deadlines, not measured plan-review times: the City of Key West publishes no review-time data. Once a project has an allocation, its building permit still falls under Florida’s §553.792 review deadlines (30 business days for a complete single-family application under 7,500 sq ft reviewed by the city). Unit totals are equivalent single-family units from the city’s 2026 BPAS Annual Report; Key West’s 36-unit share of the 2025 state units comes from local news, not an official notice. Monroe County’s ROGO is a separate system with its own numbers, so don’t combine them, and these counts aren’t comparable with other cities.