Washington Building Permit Timelines & Delays (2025 Data)

Washington's largest cities and counties got faster in 2025, the first year new legal review deadlines applied: across permit types, reviews ran a median 13 days faster than the deadlines, after running a median 17 days slower in 2024. The number of jurisdictions meeting or beating the deadlines rose from 33 to 42 (2025 report, pp. 4, 21).

Last reviewed October 27, 2026
headline figure
50 jurisdictions · 1,731 decisions the statewide dataset behind every WA city guide
what to know
Official 2025 data: reviews ran a median 13 days faster than the legal deadlines, after running 17 days slower in 2024.
data source
Annual Permitting Performance Report - 2025
by the numbers

Washington permitting, the figures

The key published figures for this jurisdiction — each cited to its official source.

50 of 51
Jurisdictions reporting
7 counties and 44 cities must report
Source: Annual Permitting Performance Report - 2025 — Executive summary, p. 4; Introduction, p. 8
1,731
Permit decisions in 2025
on 1,462 unique permits; building permits are no longer counted
Source: Annual Permitting Performance Report - 2025 — Key findings, p. 4
13 days faster
Median review vs. deadline
after a median 17 days slower in 2024
Source: Annual Permitting Performance Report - 2025 — Yearly comparison, p. 21
42
Jurisdictions meeting deadlines
up from 33 in 2024
Source: Annual Permitting Performance Report - 2025 — Yearly comparison, p. 21
about 19% faster
Median review time
than 2024, across all permit categories
Source: Annual Permitting Performance Report - 2025 — Yearly comparison, p. 21
63 median days
Construction permits (no notice, no hearing)
65-day deadline
Source: Annual Permitting Performance Report - 2025 — Table 6, p. 21
110.5 median days
Multifamily (notice, no hearing)
100-day deadline
Source: Annual Permitting Performance Report - 2025 — Table 6, p. 21
137.67 median days
Multifamily (notice and hearing)
170-day deadline; 20.34 days slower than 2024
Source: Annual Permitting Performance Report - 2025 — Table 6, p. 21
analysis

What the data shows

  • Multifamily housing is still the slow lane: permits that need public notice but no hearing took a median 110.5 days against a 100-day deadline, and no-notice multifamily permits a median 77 days against 65 (Table 6, p. 21).

  • Construction permits needing no notice or hearing, which in this report now cover site work such as civil and site-disturbance permits rather than building permits, came in at a median 63 days against a 65-day deadline (Table 6, p. 21; p. 13).

  • The steep drop in subdivision times (preliminary subdivisions fell from a median 188 days to 71.5) likely reflects a reporting change: in 2025, jurisdictions typically reported each shorter review cycle separately (Table 6, p. 21).

  • Fewer permits are counted than before: a 2025 law (HB 1935) took building permits out of the reporting, so 2025 counts 1,731 decisions against 2,774 in the initial 2024 report, a smaller scope rather than less building (pp. 4, 21).

how Permavia helps in washington

Most delay accumulates before technical review

The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.

frequently asked

Washington permitting: FAQ

How long do building permits take in Washington?

The statewide report no longer tracks building permits: a 2025 law (HB 1935, Chapter 102, Laws of 2025, in effect since July 27, 2025) says a building permit is not a project permit under these review rules. For the land-use and site permits still reported, 2025 reviews ran a median 13 days faster than the legal deadlines, while multifamily permits needing public notice took a median 110.5 days against a 100-day deadline (Department of Commerce, 2025 report, pp. 4, 12, 21; SHB 1935 Final Bill Report).

What are Washington's permit review deadlines?

Since January 2025, RCW 36.70B sets 65 days for project permits that need no public notice, 100 days for those that need notice, and 170 days for those that need notice and a hearing, counted in calendar days from the day the application is complete. The subdivision statute sets 90 days for preliminary and 30 days for final subdivisions. Before SB 5290, a single 120-day period applied (2025 report, pp. 8–11).

What happens if a Washington city misses the deadline?

Since January 2025, it must refund part of the application fee, on a sliding scale of up to 20%, unless it has adopted at least three of the optional streamlining measures in the statute. Time the application spends waiting on the applicant, for example after the city asks for more information, does not count against the clock (2025 report, pp. 11–12).

Is the 2025 data reliable?

It is the first year measured against the new deadlines, and the Department of Commerce says data quality improved over 2024. But fewer permits are reported, so one or two unusual permits can swing a jurisdiction's results, and jurisdictions still sort permits and define “multifamily” differently, so compare cities with care (2025 report, pp. 4, 6, 16).

Sources

All figures on this page are drawn from Annual Permitting Performance Report - 2025, Washington State Department of Commerce, Growth Management Services. Local Project Review performance reporting under RCW 36.70B, pursuant to SB 5290 (Ch. 338, Laws of 2023): permit decisions made in 2025, the first year under the new review deadlines. Building permits are no longer reported (Ch. 102, Laws of 2025, HB 1935). Read the 2025 report (PDF, Department of Commerce). Specific tables, reports, and pages are cited inline with each figure above.

Figures are from the Department of Commerce's Annual Permitting Performance Report 2025, covering permit decisions made in 2025; statewide figures are medians in calendar days. Building permits are no longer reported (HB 1935), so totals are not comparable with the 2024 report, and the Department of Commerce says the large subdivision improvement likely reflects a change in how review cycles were reported. The headline uses medians; the report notes that on averages most permit types still exceeded their deadlines (p. 18). The 2025 report gives the initial 2024 count as 2,774 decisions; the 2024 report itself printed 2,723. Permit data vested under older timelines is still included (2025 report, pp. 4, 8, 18, 21).