jurisdiction guide · missouri

St. Louis Building Permit Timelines & Delays

In St. Louis, a building permit took an average of 29 days to issue in 2025, but new-construction permits have averaged about 69 days since 2021, nearly three times as long as alterations. The city’s goal is 80% of permits within 30 days, and it fell short of that goal for three straight quarters in its latest published data.

Last reviewed November 9, 2026
headline figure
short of its 80%-in-30-days goal below the city’s 30-day permit goal for three straight quarters
what to know
The City of St. Louis aims to issue 80% of building permits within 30 days and has fallen short for three quarters; permits averaged 29 days to issue in 2025.
data source
Building Permits By Year dashboard and CityStat: Building Division
by the numbers

St. Louis permitting, the figures

The key published figures for this jurisdiction — each cited to its official source.

80% within 30 days
City permit goal (target)
The Building Division’s published goal for building permits; a target, not a measured result
Source: Building Permits By Year dashboard and CityStat: Building Division — City of St. Louis, CityStat: Building Division (page updated Oct 30, 2026)
Short for 3 quarters
Performance against the goal
The city reports the division underperformed the goal over the past three quarters; its Q3 data is still being validated
Source: Building Permits By Year dashboard and CityStat: Building Division — City of St. Louis, CityStat: Building Division (page updated Oct 30, 2026)
29 days
Avg days to issue, all building permits (2025)
31 in 2021, 27 in 2022, 18 in 2023, 24 in 2024; mean days, method not published
Source: Building Permits By Year dashboard and CityStat: Building Division — City of St. Louis, Building Permits By Year dashboard (permit type All, as of Nov 9, 2026)
22 days
Avg days to issue, 2026 to date
Partial year; counts change as the data refreshes
Source: Building Permits By Year dashboard and CityStat: Building Division — City of St. Louis, Building Permits By Year dashboard (as of Nov 9, 2026)
About 4,500
Building permits issued (2025)
About $1.36 billion in reported construction value
Source: Building Permits By Year dashboard and CityStat: Building Division — City of St. Louis, Building Permits By Year dashboard (as of Nov 9, 2026)
69 days
Avg days to issue, new construction (2021–2026)
1,635 permits; alterations averaged 24 days, additions 19, repairs 10
Source: Building Permits By Year dashboard and CityStat: Building Division — City of St. Louis, Building Permits By Project Type dashboard (2021–2026, as of Nov 9, 2026)
Most within 5 working days
Historic district review (city target)
Small jobs such as fences, rear decks and repointing can be approved at the CRO Hotspot desk
Source: Building Permits By Year dashboard and CityStat: Building Division — City of St. Louis, Cultural Resources Office, CRO Review FAQs (2026)
1 day, up to 4 units
Tornado rebuild review (city target)
Hot Spot desk Mon, Wed, Thu 12–3 p.m.; larger projects aim for approval or feedback within 15 days; permit fees waived in the impact zone
Source: Building Permits By Year dashboard and CityStat: Building Division — City of St. Louis, Permits and Approvals for Properties Impacted by the May 16 Tornado (updated May 2026)
analysis

What the data shows

  • The City of St. Louis Building Division’s goal is to issue 80% of building permits within 30 days, and the city reports it underperformed that goal for three straight quarters in its latest published data (City of St. Louis CityStat, 2026).

  • Across all building permits, the city’s average days to issue was 29 in 2025, up from 18 in 2023 and 24 in 2024, and 22 for 2026 to date (City of St. Louis Building Permits dashboard, 2026).

  • New-construction permits averaged 69 days to issue from 2021 to 2026, against 24 days for alterations and 10 for repairs, so project type matters more than the citywide average (City of St. Louis Building Permits dashboard, 2026).

  • In city historic districts, all exterior work except painting wood trim needs Cultural Resources Office approval; most permits clear within 5 working days, while large projects and work that can’t meet the district standards go to the Preservation Board, which meets the fourth Monday of each month (City of St. Louis Cultural Resources Office, 2026).

  • For properties hit by the May 16, 2025 tornado, the city waives permit fees in the impact zone and reviews homes of up to four units in one day at its Hot Spot desk, and a federal major disaster declaration (FEMA-4877-DR, June 9, 2025) opened Individual Assistance to city residents (City of St. Louis, 2026; FEMA, 2025).

how Permavia helps in st. louis

Most delay accumulates before technical review

The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.

frequently asked

St. Louis permitting: FAQ

How long does it take to get a building permit in St. Louis?

About a month on average, longer for new construction. The city’s dashboard shows building permits averaged 29 days to issue in 2025 and 22 days in 2026 to date, while new-construction permits averaged 69 days over 2021–2026 (City of St. Louis, Building Permits dashboards, as of Nov 9, 2026). The city’s goal is 80% of permits within 30 days, and it reports missing that goal for three straight quarters in its latest published data (City of St. Louis CityStat).

How do I apply for a residential building permit in the City of St. Louis?

Online through the city’s permit portal, or in person at the Permit Section, City Hall, 1200 Market Street, Room 425. You need the project address, plans and a $25 application fee; the permit fee is due after final approvals and is $10 per $1,000 of estimated cost for projects over $3,000 (City of St. Louis, Residential Construction Permit page, 2026). Complex projects may need several review meetings.

Does historic district review add time in St. Louis?

Usually a few days. In city historic districts all exterior work except painting wood trim needs Cultural Resources Office approval; the office says most permits are approved within 5 working days and small jobs such as fences, rear decks and repointing can be approved at its Hotspot desk (City of St. Louis, CRO Review FAQs). Large projects and work that can’t meet the standards go to the Preservation Board, which meets the fourth Monday of each month, so plan around that cycle.

What permit help is there for May 16, 2025 tornado repairs in St. Louis?

Permit fees are waived for rebuilding in the tornado impact zone, homes of up to four units can be approved in one day at the Hot Spot desk (Monday, Wednesday and Thursday, 12–3 p.m.), and larger projects aim for approval or feedback within 15 days (City of St. Louis, tornado permits and approvals page, updated May 2026). Minor work that restores pre-storm condition, such as gutters, fencing or most roofing, needs no permit outside a local historic district. Executive Order 90 lets owners rebuild nonconforming structures over an extended timeframe and extends conditional use permits from one to three years.

Sources

All figures on this page are drawn from Building Permits By Year dashboard and CityStat: Building Division, City of St. Louis. The city’s permit dashboard reports building permits issued, value and average days to issue by year (29 days for all permits in 2025, as of November 9, 2026); CityStat states the Building Division’s goal of 80% of permits within 30 days and reports it missed that goal for three straight quarters in its latest published data (data last updated October 30, 2026). www.stlouis-mo.gov/data/dashboards/building-permits/years.cfm. Specific tables, reports, and pages are cited inline with each figure above.

The 80%-within-30-days figure is the city’s goal, not a result; the city reports only that it missed the goal for three quarters and does not publish the quarterly percentages as text. The average days to issue come from the city’s live permit dashboard (permit type All, read November 9, 2026); the city doesn’t define the clock, counts shift slightly as the data refreshes, and the city notes the refresh is unstable. The 5-working-day historic review and the 1-day and 15-day tornado timelines are city targets, not measured outcomes. These figures cover only the City of St. Louis, which has been separate from St. Louis County since 1876; county suburbs run their own permit offices, and numbers aren’t comparable with other cities.