jurisdiction guide · district of columbia

Washington, DC Building Permit Timelines & Delays

Washington’s building department finished the first review of a filed permit application within 30 business days 97.1% of the time in fiscal year 2025, so for most projects the city’s own plan review is not the bottleneck. Two things sit outside that clock: historic preservation review for buildings in historic districts, and a federal height limit that no District agency can waive. The Department of Buildings (DOB), which opened on October 1, 2022 when the District split the former Department of Consumer and Regulatory Affairs in two, met its 90% targets for triage, first review and re-review that year, and missed only its solar review goal among its plan-review targets.

Last reviewed November 2, 2026
headline figure
30 d DOB first-review standard for filed projects; 97.1% met in FY2025
what to know
DC’s Department of Buildings finished 97.1% of first reviews of filed plans within 30 business days in FY2025; historic review and the federal height cap sit outside that clock.
data source
Department of Buildings: Performance Accountability & Service Level Agreements
by the numbers

Washington permitting, the figures

The key published figures for this jurisdiction — each cited to its official source.

30 business days
Filed-project first-review standard
97.1% of ProjectDox applications met this in FY2025 (target 90%)
Source: Department of Buildings: Performance Accountability & Service Level Agreements — DC DOB, FY2025 Performance Accountability Report
91.4%
Applications triaged within 2 business days
FY2025; target 90%, met
Source: Department of Buildings: Performance Accountability & Service Level Agreements — DC DOB, FY2025 PAR
94.2%
Re-reviews within 15 business days
FY2025; target 90%, met
Source: Department of Buildings: Performance Accountability & Service Level Agreements — DC DOB, FY2025 PAR
84.7%
Solar plan reviews within 10 business days
FY2025; target 90%, missed (the published service level for solar is 15 business days)
Source: Department of Buildings: Performance Accountability & Service Level Agreements — DC DOB, FY2025 PAR; DOB Service Level Agreements
next business day
Homeowner’s Center and digital walk-thru review
Published service level (a target, not a measured time); DOB review only
Source: Department of Buildings: Performance Accountability & Service Level Agreements — DC DOB, Plan Review and Permit Timelines (Service Level Agreements)
97%
Historic applications cleared by staff
Of 5,908 permit and related applications in FY2022; 181 (3%) went to the Review Board
Source: Department of Buildings: Performance Accountability & Service Level Agreements — DC Office of Planning, HPO Annual Report FY2022
30–60 days
Review Board decision on major historic work
Typical time from filing; the board meets monthly and a neighborhood commission can ask for up to a 45-day deferral
Source: Department of Buildings: Performance Accountability & Service Level Agreements — DC Office of Planning, DC Historic Preservation Review Process
130 ft
Federal height cap, business streets
Street width plus 20 feet, up to 130 feet (160 on part of Pennsylvania Avenue NW); on residential streets, street width minus 10 feet, up to 90 feet
Source: Department of Buildings: Performance Accountability & Service Level Agreements — D.C. Code §6-601.05; NCPC
analysis

What the data shows

  • DOB reviewed 97.1% of filed ProjectDox applications within 30 business days in FY2025 against a 90% target and met its triage and re-review targets, but missed its solar goal, finishing 84.7% of solar plan reviews within 10 business days (DC DOB, FY2025 Performance Accountability Report, 2026).

  • DOB’s Instant Permits, which issue permits online for common home projects, were expanded in early 2026 to most residential solar installations up to 15 kilowatts and the in-kind replacement of up to 15 windows (DC DOB, June 2026).

  • Historic review mostly stays at staff level: the Historic Preservation Office handled 97% of its 5,908 permit and related applications through expedited review in FY2022, yet 59 of 161 new-construction applications were referred to the Historic Preservation Review Board (DC Office of Planning, 2022).

  • Federal law caps buildings at the width of the fronting street plus 20 feet, to a maximum of 130 feet on business streets and 90 feet on residential streets, and Congress last changed the Act in 2014, mainly to let people occupy one-story penthouses of up to 20 feet above the roof (D.C. Code §6-601.05; Pub. L. 113-103, 2014).

how Permavia helps in washington

Most delay accumulates before technical review

The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.

frequently asked

Washington permitting: FAQ

How long does plan review take with DC’s Department of Buildings?

DOB’s Service Level Agreement is 30 business days for filed projects reviewed in ProjectDox and next business day for Homeowner’s Center and digital walk-thru applications, counting DOB’s review only (DC DOB, Service Level Agreements). In FY2025, DOB reported finishing 97.1% of first reviews of ProjectDox applications within 30 business days and 94.2% of re-reviews within 15 business days, both against a 90% target (DC DOB, FY2025 Performance Accountability Report).

Does DOB actually meet its permit targets?

Mostly. In FY2025, DOB met its targets for triaging applications within two business days (91.4%), first review within 30 business days (97.1%) and re-review within 15 business days (94.2%), each against 90%, but finished only 84.7% of solar plan reviews within 10 business days, short of its 90% goal (DC DOB, FY2025 Performance Accountability Report). These are the agency’s own figures. Since early 2026, most residential solar installations up to 15 kilowatts can go through DOB’s online Instant Permits instead (DC DOB, June 2026).

Why is permitting in DC more complicated than DOB’s timelines suggest?

Work on a historic property also needs Historic Preservation Office review. In FY2022 the office handled 97% of its 5,908 permit and related applications through expedited staff review, but sent 181 to the Historic Preservation Review Board, including 59 of 161 new-construction applications (DC Office of Planning, HPO Annual Report FY2022). The office says minor work is typically approved within 1–3 days; the board meets once a month, typically reviews major work within 30–60 days of filing, and a neighborhood commission can ask to defer a case for up to 45 days (DC Office of Planning, DC Historic Preservation Review Process).

What is the Height Act and how does it affect DC development?

The federal Height of Buildings Act of 1910 limits a building to the width of the street in front plus 20 feet, with a maximum of 130 feet on business streets (160 feet on the north side of Pennsylvania Avenue NW between 1st and 15th Streets) and 90 feet on residential streets (D.C. Code §6-601.05; NCPC). The District cannot raise those limits on its own: a Justice Department legal opinion says the Council may amend the District’s schedule of heights near public buildings only within the Act’s overall limits (U.S. DOJ, Office of Legal Counsel). Congress’s 2014 amendment mainly let people occupy one-story penthouses of up to 20 feet above the roof (D.C. Code §6-601.05; NCPC).

Sources

All figures on this page are drawn from Department of Buildings: Performance Accountability & Service Level Agreements, DC Department of Buildings. DOB’s published plan-review Service Level Agreements (next business day for Homeowner’s Center and digital walk-thru applications, 30 business days for filed projects; DOB review only) and its annual Performance Accountability Reports on review timeliness. dob.dc.gov/publication/plan-review-and-permit-timelines-service-level-agreements. Specific tables, reports, and pages are cited inline with each figure above.

DOB’s percent-on-time figures are the agency’s own FY2025 Performance Accountability Report (dated January 15, 2026) and measure DOB’s review clock only: they exclude historic-preservation, zoning, federal or other-agency review and the applicant’s resubmission time. The service levels are published targets, not measured times. The historic review counts are from the Historic Preservation Office’s FY2022 annual report, the newest found, and its 1–3 day and 30–60 day timings are typical, not guaranteed. DOB reported 63,675 permits issued in FY2025 in its performance report but 53,514 in its February 2026 Council testimony, so no permit volume is shown here.