Permittable is now Permavia. Read about our new name

jurisdiction guide · colorado

Aspen Building Permit Timelines & Delays

A new major home permit in Aspen is scheduled for 16 to 18 weeks just for its first review round, and each correction round adds another 8 to 10 weeks, according to the city’s posted timelines (as of July 2026). On that schedule a project with two correction rounds spends 32 to 38 weeks in review, about seven and a half to nine months, and the clock starts only once the application is complete and fees are paid.

Last reviewed November 7, 2026
headline figure
16–18 wk for the first review of a new major home permit
what to know
Aspen’s posted schedule (as of July 2026) puts a new major residential permit at 16–18 weeks for first review, plus 8–10 weeks per correction round.
data source
Building Permit Timelines (Community Development)
by the numbers

Aspen permitting, the figures

The key published figures for this jurisdiction — each cited to its official source.

16–18 weeks
New major residential, first review
Starts once the application is deemed complete and fees are paid
Source: Building Permit Timelines (Community Development) — City of Aspen, Building Permit Timelines (as of July 2026)
+8–10 weeks
Major permit, per correction round
Each added review round on a major permit or major change order
Source: Building Permit Timelines (Community Development) — City of Aspen, Building Permit Timelines (as of July 2026)
8–10 weeks
New minor permit, first review
Each added review round adds 6–8 weeks
Source: Building Permit Timelines (Community Development) — City of Aspen, Building Permit Timelines (as of July 2026)
18–20 weeks
Posted major permit estimate, Feb 2022
New minor permits were posted at 14–16 weeks then
Source: Building Permit Timelines (Community Development) — City of Aspen, Community Development Update (timelines as of Feb 15, 2022)
1 week + 1–2 days
Final review, then issuance
Final review within a week of all agency sign-offs; ready to issue in 1–2 business days
Source: Building Permit Timelines (Community Development) — City of Aspen, Building Permit Timelines (as of July 2026)
Up to 6
Departments in a first review
Building, zoning, engineering, utilities, parks and, if required, historic preservation; reported by the Aspen Times
Source: Building Permit Timelines (Community Development) — Aspen Times, July 20, 2023
6 per year
Demolition allotments (as of Feb 2024)
Single-family and duplex; awarded by lottery from 2024 (Ord. 23, Series 2023), per the city’s February 2024 memo
Source: Building Permit Timelines (Community Development) — City of Aspen, Council work session memo, GMQS Demolition Allotment Program (Feb 2024)
+33% YoY
Building permit applications, Jan–Jun 2023
240 to 318 applications, reported by the Aspen Times; the city also said its agencies met an internal goal to cut first-round review times by 25%, with no baseline published
Source: Building Permit Timelines (Community Development) — City of Aspen, Community Development Update (mid-2023); Aspen Times, July 20, 2023
analysis

What the data shows

  • Aspen’s posted review times have come down most for smaller jobs: a new minor permit is now scheduled at 8–10 weeks for first review, down from 14–16 weeks in February 2022, while a new major permit moved from 18–20 to 16–18 weeks (City of Aspen, Building Permit Timelines, 2026; Community Development Update, 2022).

  • Correction rounds are where a schedule stretches: each added round on a major permit adds 8–10 weeks, the clock starts only after the application is complete and fees are paid, and the city says every timeline shifts with queue volume, so a complete first submittal saves months (City of Aspen, Building Permit Timelines, 2026).

  • Tearing down a single-family home or duplex to rebuild needs a demolition allotment, capped at six a year as of the city’s February 2024 memo and awarded by lottery from 2024 under Ordinance 23 (Series 2023), and the project must divert at least 35% of its waste by weight and supply product carbon disclosures for half its steel and concrete (City of Aspen, Council memo, 2024; Residential Demolition and Redevelopment Standards, Ord. 13, 2022).

  • The latest measured figures the city has published are from mid-2023: building permit applications were up 33% on a year earlier, and the city said its agencies had met an internal goal to cut first-round review times by 25%, without publishing a baseline (City of Aspen, Community Development Update, 2023).

how Permavia helps in aspen

Most delay accumulates before technical review

The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.

frequently asked

Aspen permitting: FAQ

How long does a building permit take in Aspen?

On the city’s posted schedule (as of July 2026), a new major residential permit gets its first review in 16 to 18 weeks, and each correction round adds 8 to 10 weeks. A new minor permit takes 8 to 10 weeks for first review plus 6 to 8 weeks per added round, while mechanical, electrical and plumbing permits take 1 to 2 weeks in total. The clock starts once the application is complete and fees are paid (City of Aspen, Building Permit Timelines).

Why can an Aspen building permit take so long?

Mostly review rounds and routing. A first review may involve up to six departments: building, zoning, engineering, utilities, parks and, if required, historic preservation (reported by the Aspen Times, July 2023). Each correction round on a major permit then adds 8 to 10 weeks, and the city says all its timelines shift with queue volume (City of Aspen, Building Permit Timelines, July 2026).

What is Aspen’s demolition cap?

Six a year for single-family homes and duplexes, as of the city’s February 2024 council memo: Aspen created the cap under its Growth Management Quota System with Ordinance 13 (Series 2022), after the 2021–2022 residential moratorium. From 2024 the allotments have been drawn by lottery instead of first-come, first-served (City of Aspen, Council work session memo, Feb 2024), and demolition projects must meet the city’s waste-diversion and future-electrification standards.

Have Aspen’s permit times improved?

On the city’s own estimates, yes since 2022, though not back to 2020 levels. The posted first review for a new minor permit fell from 14–16 weeks (February 2022) to 8–10 weeks (July 2026), and for a new major permit from 18–20 to 16–18 weeks, still longer than the 11–13 weeks posted in October 2020 (City of Aspen, Community Development Updates; Building Permit Timelines). The latest measured result is from mid-2023, when the city said its agencies had met an internal goal to cut first-round review times by 25%, without publishing a baseline.

Sources

All figures on this page are drawn from Building Permit Timelines (Community Development), City of Aspen. The city’s posted building permit review timeframes (as of July 2026, updated quarterly and subject to queue volume): a New Major Residential first review at 16–18 weeks and 8–10 weeks per added review round for major permits, a New Minor first review at 8–10 weeks with 6–8 weeks per round, beginning once an application is deemed complete and submittal fees are paid. These are city estimates, not measured averages. aspen.gov/244/Building-Permit-Timelines. Specific tables, reports, and pages are cited inline with each figure above.

The week counts are the City of Aspen’s posted estimates (updated quarterly and subject to queue volume), not measured averages, and they start only once an application is complete and fees are paid. The 2023 application increase is a measured count for January to June 2023; the 25% review-time cut is the city’s report of meeting an internal goal, with no baseline published. No newer measured review times are published, and figures are not comparable across cities.