Boise Building Permit Review Times
Boise now completes first review of standard new commercial and multi-family buildings in 19 working days, well inside its goal of under 30: in May–July 2026 both were 5–8 days faster than a year earlier. The largest projects went the other way, slowing by 7–8 days to 35–36 working days, though still inside their goal of under 45. The city’s Planning & Development Services department publishes these actual averages every month, each against its goal, a rare level of transparency.
Boise permitting, the figures
The key published figures for this jurisdiction — each cited to its official source.
What the data shows
Boise publishes actual average first-review times by permit type every month, each against a goal, a rare level of transparency. In the May–July 2026 report, averages for the commercial, multi-family and tenant-improvement types ran from 8 working days (simple tenant improvements) to 36 (new multi-family, Level 2) (City of Boise, Permit Processing Timeframes).
New-building reviews are far faster than in 2022: new commercial (Level 1) first review took 19 working days (from 40 in 2022) and new multi-family (Level 1) 19 (from 52). The city reports only one building permit type above its goal, Commercial Occupancy Evaluation Level 2 (7 days against under 5), but the largest commercial and multi-family projects ran 7–8 days slower than a year earlier, and tenant improvements Level 2 sat at the limit of its goal.
These are first-review averages in working business days; ready-to-issue time (which includes resubmittals and applicant time) and customer pick-up time are tracked separately. More new homes are waiting: 112 new single-family homes were under review on August 4, 2026, up from 102 a year earlier.
Most delay accumulates before technical review
The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.
Boise permitting: FAQ
How long does plan review take in Boise?
In the City of Boise’s May–July 2026 Permit Processing Timeframes report, average first review ran about 19 working days for a new commercial building (Level 1), 19 for new multi-family (Level 1), and 35–36 for the most complex commercial and multi-family projects (Level 2). Simple tenant improvements averaged 8 days. The city reports only one type above its goal, Commercial Occupancy Evaluation Level 2 (7 days against under 5); tenant improvements Level 2 sat exactly at its limit.
Are these the total permit times?
No: they’re average first-review times in working business days. Resubmittal cycles and the time a finished permit waits for customer pick-up are tracked separately, and figures change from one edition to the next.
Does Boise publish its review times?
Yes. Boise’s Planning & Development Services department publishes a Permit Processing Timeframes report each month, covering the latest three months, showing the actual average first-review time for each permit type.
Sources
All figures on this page are drawn from Permit Processing Timeframes (May 1 – July 31, 2026 edition), City of Boise, Planning & Development Services. Official report of average first-review timeframes by permit type, in working business days (excludes holidays and weekends), each against its goal. Issued monthly, each edition covering the latest three months; figures cited from the May 1 – July 31, 2026 edition. Year-over-year comparisons to 2022 use the April 1 – June 30, 2022 edition. www.cityofboise.org/media/21757/permit-processing-timeframes-5-1-26-to-7-31-26.pdf. Specific tables, reports, and pages are cited inline with each figure above.
These are the City of Boise Planning & Development Services department’s average first-review times in working business days (excludes holidays and weekends), from its Permit Processing Timeframes report for May 1 – July 31, 2026 (the city’s Building page also lists a newer June–August 2026 edition, not yet reflected here). They are first-review averages, not total end-to-end permit time, and they change from one edition to the next. Boise restructured its categories after 2022 into Level 1/Level 2 tiers, so the year-over-year comparisons map the old single rows to the current Level 1 tier. Methodology differs from other jurisdictions on this site, so compare with care.