Wyoming Building Permit Timelines & Delays

Since July 1, 2026, a Wyoming city or county that takes more than 30 calendar days to decide a completed small-home permit has, by law, approved it as submitted, unless the clock was paused for missing information or extended by agreement. The Fast Track Permits Act makes silence count as a yes for one- and two-unit homes of up to 3,000 square feet per unit.

Last reviewed October 28, 2026
headline figure
30-day shot clock small homes auto-approve if the city runs late
what to know
Wyoming's Fast Track Permits Act gives cities 30 days to decide a small-home permit. Miss it and the application is deemed approved the next day (inspections still apply).
data source
Wyo. Stat. §§16-13-101 to 16-13-102: Building Permit Timelines (Fast Track Permits Act)
by the numbers

Wyoming permitting, the figures

The key published figures for this jurisdiction — each cited to its official source.

10 business days
Completeness-notice window
To notify the applicant the application is complete or what's missing
Source: Wyo. Stat. §§16-13-101 to 16-13-102: Building Permit Timelines (Fast Track Permits Act) — Wyo. Stat. §16-13-102(b)
30 calendar days
Decision deadline
To approve or deny a completed application
Source: Wyo. Stat. §§16-13-101 to 16-13-102: Building Permit Timelines (Fast Track Permits Act) — Wyo. Stat. §16-13-102(c)
Day after the deadline
Deemed-approved trigger
Approved as submitted, still subject to all safety and code inspections
Source: Wyo. Stat. §§16-13-101 to 16-13-102: Building Permit Timelines (Fast Track Permits Act) — Wyo. Stat. §16-13-102(g)
1–2 units · ≤3 stories
Covered project
IRC dwellings of 3,000 sq ft or less per unit; larger and multifamily are excluded
Source: Wyo. Stat. §§16-13-101 to 16-13-102: Building Permit Timelines (Fast Track Permits Act) — Wyo. Stat. §16-13-102(a)
7 calendar days
Written reasons if denied
Source: Wyo. Stat. §§16-13-101 to 16-13-102: Building Permit Timelines (Fast Track Permits Act) — Wyo. Stat. §16-13-102(e)
Pending info or agency
Clock pauses for
The 30-day clock is suspended while clarification or a required state/federal approval is pending
Source: Wyo. Stat. §§16-13-101 to 16-13-102: Building Permit Timelines (Fast Track Permits Act) — Wyo. Stat. §16-13-102(c)–(d)
analysis

What the data shows

  • Effective July 1, 2026, Wyoming's Fast Track Permits Act gives a local government 30 calendar days to approve or deny a completed small-residential permit application, after a 10-business-day completeness-notice step (Wyo. Stat. §16-13-102(b)–(c); HB 2, 2026 Budget Session).

  • If the local government misses the 30-day deadline, the application is deemed approved as submitted on the day after the deadline lapses, but the building still must pass all safety and code inspections before a certificate of occupancy issues (Wyo. Stat. §16-13-102(g)).

  • The law is narrow: it covers only dwellings of one or two units, three stories or fewer, and 3,000 square feet or less of finished floor area per unit, regulated under the International Residential Code (Wyo. Stat. §16-13-102(a)). Larger and multifamily projects are not covered.

  • The 30-day clock is not absolute: it is suspended while requested clarification or a required state or federal agency approval is pending, and may be extended by written agreement (Wyo. Stat. §16-13-102(c)–(d)).

how Permavia helps in wyoming

Most delay accumulates before technical review

The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.

frequently asked

Wyoming permitting: FAQ

Does Wyoming really auto-approve permits?

Yes, for covered small-home permits. Under the Fast Track Permits Act (effective July 1, 2026), if a local government fails to approve or deny a completed application within 30 calendar days, the application is deemed approved as submitted on the day after the deadline lapses (Wyo. Stat. §16-13-102(g)). Approval of the application does not waive inspections: the home still must pass all safety and code inspections before occupancy.

Which projects does the Fast Track Permits Act cover?

Only small residential dwellings: one or two dwelling units, no more than three stories above grade, and 3,000 square feet or less of finished floor area per unit, regulated under the International Residential Code (Wyo. Stat. §16-13-102(a)). Larger single-family homes, multifamily buildings, and commercial projects fall outside the law.

Can the 30-day clock be paused?

Yes. The decision clock is suspended while the local government is waiting on requested clarification or additional information, or on a required state or federal agency approval, and it can be extended by written agreement between the applicant and the local government (Wyo. Stat. §16-13-102(c)–(d)). So 30 days is the baseline, not an unconditional cap.

When did the law take effect?

HB 2 of the 2026 Budget Session, the Fast Track Permits Act, was signed by Governor Gordon on March 5, 2026 and takes effect July 1, 2026, applying to applications filed on or after that date. It is codified at Wyoming Statutes §§16-13-101 to 16-13-102 (House Enrolled Act 16; ch. 42, 2026 Session Laws of Wyoming).

Sources

All figures on this page are drawn from Wyo. Stat. §§16-13-101 to 16-13-102: Building Permit Timelines (Fast Track Permits Act), Wyoming Legislature (Legislative Service Office). Enacted as HB 2, 2026 Budget Session (House Enrolled Act 16; ch. 42, 2026 Session Laws of Wyoming); signed March 5, 2026, effective July 1, 2026. Sets a 10-business-day completeness notice and a 30-calendar-day decision deadline for small residential dwellings, with the application deemed approved the day after the deadline lapses (inspections still apply). www.wyoleg.gov/Legislation/2026/HB0002. Specific tables, reports, and pages are cited inline with each figure above.

These are statutory deadlines and triggers taking effect July 1, 2026, not measured outcomes: Wyoming does not publish observed average permit-review times, and the deemed-approved provision applies only to applications filed on or after the effective date. The law is also narrow in scope (small IRC dwellings) and its 30-day clock can be suspended or extended, so real-world timelines will vary.