jurisdiction guide · maryland

Baltimore Building Permit Timelines & Delays

Baltimore’s permit office is climbing out of a rough 2025: when the city switched to a new online permitting system that February, monthly issuance fell from more than 3,000 permits to 688, and by January 2026 city officials reported residential permits took about 3 days, down from 12 in October 2025. Treat that wait-time figure with some caution: it comes from testimony to the City Council, not a published report. New housing units authorized in the city also fell to 543 in 2025, from 1,273 the year before.

Last reviewed November 2, 2026
headline figure
688 permits issued Feb 2025 vs. 3,000+ the month before
what to know
Issuance collapsed when Baltimore moved to a new online permit system in February 2025; city officials told the Council residential waits fell to 3 days by January 2026.
data source
Permits and Inspections
by the numbers

Baltimore permitting, the figures

The key published figures for this jurisdiction — each cited to its official source.

688
Permits issued, Feb 2025
First month on the new online system, vs. 3,000+ in January 2025; news analysis of the city’s open permit data
Source: Permits and Inspections — Baltimore Banner, 2025
9,941
Permits issued, Jan 1–June 3, 2025
About half the same period of 2024; fewest since the city’s public records begin in 2015
Source: Permits and Inspections — Baltimore Banner, 2025
5,928
Permits in process, July 2025
About 200 not yet touched by an employee, per the deputy mayor at a July 22, 2025 Council hearing
Source: Permits and Inspections — Baltimore Banner, 2025
1,700+ → 68
Initial-review backlog
Applications awaiting initial review, May 2025 to February 5, 2026; the city’s own snapshots, not an audited figure
Source: Permits and Inspections — Baltimore DHCD, What We’ve Improved (2026)
12 → 3 days
Residential permit wait (city-reported)
October 2025 to January 2026, per city testimony to the Council; measure not defined and not independently published
Source: Permits and Inspections — WBFF (Fox45), 2026
543
New housing units authorized, 2025
Down from 1,273 in 2024 and 1,843 in 2023; units in permits issued, not review time
Source: Permits and Inspections — U.S. Census Bureau, Building Permits Survey (via FRED)
11,839
Vacant building notices
As of April 20, 2026, down 6% since the fiscal year began July 1, 2025
Source: Permits and Inspections — Maryland DHCD, Baltimore Vacants Reinvestment Council minutes (Apr 2026)
37,500
Vacant-property goal
Vacant houses and lots to transform under a $3 billion, 15-year plan; a target, not a result
Source: Permits and Inspections — City of Baltimore, Bmore FAST
analysis

What the data shows

  • After the city’s new online permit system launched in February 2025, monthly issuance fell from more than 3,000 permits in January to 688 in February, and the 9,941 permits issued through June 3 were about half the same period of 2024 (Baltimore Banner, 2025).

  • At a July 2025 Council hearing, the deputy mayor said 5,928 permits were in process, about 200 untouched, and news reports described reviewers consulting older legacy systems for data meant to be in the new system and trouble moving existing permit records (Baltimore Banner and WYPR, 2025).

  • Baltimore’s permit czar told the City Council that residential wait times fell from 12 days in October 2025 to 3 days in January 2026, though a council member questioned the city’s data and no published dataset for the figure was found (WBFF Fox45, 2026).

  • The Census Bureau counts 543 new private housing units authorized by building permits in Baltimore City in 2025, down from 1,273 in 2024 and 1,843 in 2023 (U.S. Census Bureau, 2025).

how Permavia helps in baltimore

Most delay accumulates before technical review

The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.

frequently asked

Baltimore permitting: FAQ

How long does it take to get a building permit in Baltimore?

City officials told the City Council that residential permit wait times fell from 12 days in October 2025 to 3 days in January 2026 (WBFF Fox45, 2026), but a council member questioned the city’s data, the city hasn’t defined that measure publicly, and no published service standard or regular performance report was found. Its Bmore FAST plan commits to publishing standard review times (City of Baltimore).

Why did Baltimore permits slow down in 2025?

In February 2025 the city switched to a new Accela-based online permitting system, and issuance dropped from over 3,000 permits in January to 688 in February (Baltimore Banner, 2025). The Banner reported that reviewers had to consult legacy systems for data that hadn’t been integrated, and WYPR reported trouble moving existing permit records and workflow errors that stalled reviews (WYPR, 2025).

Is Baltimore’s permit backlog improving?

Yes, by the city’s own count: applications awaiting initial review fell from more than 1,700 in May 2025 to 68 as of February 5, 2026, and the Department of Housing & Community Development added an Auto-Issue feature that issues simple permits needing no technical review once the application is complete (Baltimore DHCD, What We’ve Improved). In July 2025 the deputy mayor had said 5,928 permits were in process, about 200 not yet touched (Baltimore Banner, 2025), and by January 2026 the city reported residential waits of about 3 days, a figure a council member questioned (WBFF Fox45, 2026).

Does Baltimore’s vacant housing affect permitting?

The city links the two: it presents its Bmore FAST permitting reforms as needed to carry out a $3 billion, 15-year plan that aims to transform 37,500 vacant houses and lots (City of Baltimore, Bmore FAST). As of April 2026, 11,839 buildings carried vacant building notices, down 6% since July 2025 (Maryland DHCD, 2026).

Sources

All figures on this page are drawn from Permits and Inspections, Baltimore City Department of Housing & Community Development. DHCD’s permits hub: the Accela-based E-Permits portal, the E-Permits Help Center, plans review consultations and building permit guidance. www.baltimorecity.gov/dhcd/our-work/permits-and-inspections. Specific tables, reports, and pages are cited inline with each figure above.

Baltimore publishes no regular report of permit review times against a target, so this guide relies on measured counts; the initial-review backlog figures are the city’s own snapshots on its What We’ve Improved page. Monthly and year-to-date issuance figures are Baltimore Banner analyses of the city’s open permit database; the 12-to-3-day residential wait is the city’s own figure as presented to the City Council and reported by WBFF, with no published definition, and a council member questioned the data. Census counts are housing units in permits issued, not review times, and the 2025 drop can’t be attributed to the system change alone.