jurisdiction guide · washington

Bellevue Building Permit Timelines & Delays (2025 Data)

Bellevue's own review of routine site permits is fast and its multifamily review is slow. In 2025, construction permits averaged 38 days of active review against a 65-day deadline, while multifamily reviews averaged 457 days, and 7 of the 16 multifamily decisions missed the deadline (2025 report, Table 15, p. 35).

Last reviewed October 27, 2026
headline figure
fast site permits, slow multifamily construction 38d · multifamily 457d (2025)
what to know
Construction permits beat the 65-day deadline in 2025, but multifamily reviews ran far over.
data source
Annual Permitting Performance Report - 2025
by the numbers

Bellevue permitting, the figures

The key published figures for this jurisdiction — each cited to its official source.

79
Permit decisions in 2025
on 78 unique permits; building permits are no longer reported
Source: Annual Permitting Performance Report - 2025 — Table 15, p. 35
38 avg days
Construction permits
active review; 65-day deadline; 6 of 63 over; 343 days including paused time
Source: Annual Permitting Performance Report - 2025 — Table 15, p. 35
457 days
Multifamily, average active review
763 days including paused time; 7 of 16 over
Source: Annual Permitting Performance Report - 2025 — Table 15, p. 35
139 avg days
Multifamily (notice, no hearing)
active review; 100-day deadline
Source: Annual Permitting Performance Report - 2025 — Figure 7, p. 37
158 avg days
Multifamily (notice and hearing)
active review; 170-day deadline
Source: Annual Permitting Performance Report - 2025 — Figure 7, p. 37
560.33 avg days
Multifamily (other)
active review; Bellevue's 170-day deadline (state default 100)
Source: Annual Permitting Performance Report - 2025 — Figure 7, p. 37; Table 16, p. 36
analysis

What the data shows

  • Construction permits, which in this report cover site work such as civil and site-preparation permits, averaged 38 days against a 65-day deadline, and 57 of 63 met it (Table 15, p. 35; p. 13).

  • Multifamily was the bottleneck: 7 of 16 multifamily decisions missed the deadline, and those reviewed on their own averaged 457 days of active review, or 763 counting paused time (Table 15, p. 35).

  • Multifamily permits with a hearing came in under their 170-day deadline at 158 days, but those with public notice and no hearing averaged 139 days against 100, and “other” multifamily permits 560.33 days (Figure 7, p. 37).

  • Bellevue's 2025 figures are not comparable with its 2024 entry: building permits dropped out of the statewide report under a 2025 state law, and the 2024 data came before the new deadlines took effect (2025 report, pp. 4, 8).

how Permavia helps in bellevue

Most delay accumulates before technical review

The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.

frequently asked

Bellevue permitting: FAQ

How long does a building permit take in Bellevue?

Washington's statewide report no longer tracks building permits. For the permits it does track, Bellevue's 2025 construction (site) permits averaged 38 days of active review against a 65-day deadline, and multifamily reviews averaged 457 days, with 7 of 16 over the deadline (Department of Commerce, 2025 report, Table 15, p. 35).

Why are Bellevue's multifamily permits so much slower?

The report shows the gap, not the cause. Multifamily approvals in this report are processes such as design review, conditional use permits and variances, and Bellevue allows 170 days for “other” multifamily permits, the category that averaged 560.33 days (2025 report, p. 13; Table 16, p. 36; Figure 7, p. 37).

What are Bellevue's permit review deadlines?

Bellevue uses the state's deadlines: 65 days with no public notice, 100 days with notice, 170 days with notice and a hearing, 90 days for a preliminary subdivision and 30 days for a final one. The exception is “other” multifamily permits, where it set 170 days instead of 100 (Table 16, p. 36).

Is Bellevue's 2025 data reliable?

It is the first year measured against the new deadlines, but the multifamily sample is small: half of the 16 decisions went through consolidated review, which does not have to report review days. The Department of Commerce also warns that jurisdictions sort permits and define “multifamily” differently (2025 report, Table 15, p. 35; pp. 6, 15).

Sources

All figures on this page are drawn from Annual Permitting Performance Report - 2025, Washington State Department of Commerce, Growth Management Services. Local Project Review performance reporting under RCW 36.70B, pursuant to SB 5290 (Ch. 338, Laws of 2023): permit decisions made in 2025, the first year under the new review deadlines. Building permits are no longer reported (Ch. 102, Laws of 2025, HB 1935). Read the 2025 report (PDF, Department of Commerce). Specific tables, reports, and pages are cited inline with each figure above.

Figures are Bellevue's entry in the Department of Commerce's Annual Permitting Performance Report 2025 (permit decisions made in 2025): average calendar days of review with and without paused time, and decisions over the deadline. Building permits are no longer part of the report, and the 2024 data predates the new deadlines, so the two years are not comparable. Each jurisdiction classifies permits and defines “multifamily” its own way, so compare across cities with care. The City of Bellevue's own summary page labels the with-pause and without-pause columns the other way round; the Department of Commerce report's Figure 7 shows 38 and 457 are the figures not including pauses (2025 report, pp. 4, 6, 8, 35–37).