Illinois Building Permit Timelines & Delays

In Illinois, a city or county does not have to adopt a building code at all, so the rules for a project depend on exactly where it sits. Where a local code exists, state law has required since January 1, 2025 that its structural rules be at least as strict as the least restrictive International Building, Existing Building or Residential Code edition first published this year or in the previous nine, and that floor applies to home-rule cities too. Where no local code exists, a new house is built to the residential code the builder and buyer choose in the contract from options set by state law, or the current International Residential Code if they name none, and a new commercial building cannot be occupied until a state-qualified inspector certifies that it meets the state’s codes.

Last reviewed November 14, 2026
headline figure
building code optional locally but any local code has had to meet a structural baseline since Jan 1, 2025; the energy code applies statewide
what to know
An Illinois city or county does not have to adopt a building code, but any code it does adopt has had to meet a statewide structural baseline since January 1, 2025, and the 2024 energy code applies everywhere.
data source
Illinois building code rules: local adoption, the 2025 structural baseline and the statewide energy code
by the numbers

Illinois permitting, the figures

The key published figures for this jurisdiction — each cited to its official source.

Optional
Local building code
A municipality or county is not required to adopt one; without one it is a “non-building code jurisdiction” and state fallback rules apply
Source: Illinois building code rules: local adoption, the 2025 structural baseline and the statewide energy code — Illinois Capital Development Board, Illinois Codes FAQ
Since Jan 1, 2025
Structural floor for local codes
Any municipal or county building code must regulate structural design at least as strictly as the least restrictive International Building Code (with Appendix G), Existing Building Code or Residential Code edition first published in the current year or the 9 before it; applies to home-rule units; in effect
Source: Illinois building code rules: local adoption, the 2025 structural baseline and the statewide energy code — 20 ILCS 3105/10.18(e); Public Act 103-0510
30 days
Notice before a new local code
A municipality or county adopting a new code edition must identify the model code, edition and local amendments to the Capital Development Board at least 30 days before it takes effect; in effect
Source: Illinois building code rules: local adoption, the 2025 structural baseline and the statewide energy code — 20 ILCS 3105/10.18(a)
Contract code
New homes with no local code
Builder and buyer agree on the International Residential Code or a local code in force within 100 miles; if they don’t, the state energy code, the state plumbing code and the current International Residential Code apply by law; applies to new residential construction only
Source: Illinois building code rules: local adoption, the 2025 structural baseline and the statewide energy code — 815 ILCS 670/15; Illinois Capital Development Board, Illinois Codes FAQ
Inspection before occupancy
New commercial buildings with no local code
The owner must hire a state-qualified inspector, who files a certification of compliance with the state’s codes for these jurisdictions with the municipality or county before anyone occupies the building
Source: Illinois building code rules: local adoption, the 2025 structural baseline and the statewide energy code — 20 ILCS 3105/10.09-1; Public Acts 103-0510 and 104-0417
2024 IECC
Statewide energy code
International Energy Conservation Code with Illinois amendments (commercial also ASHRAE 90.1-2022), in effect since November 30, 2025, for residential and commercial buildings statewide
Source: Illinois building code rules: local adoption, the 2025 structural baseline and the statewide energy code — Illinois Capital Development Board, Illinois Energy Conservation Code; U.S. DOE Building Energy Codes Program
56 days (median)
Chicago new-construction permit (measured)
Application to issuance, all review paths; mean 91; 34% within 30 days (1,550 permits, 12 months to Oct 26, 2026)
Source: Illinois building code rules: local adoption, the 2025 structural baseline and the statewide energy code — Permavia analysis of City of Chicago Building Permits data (ydr8-5enu), 2026
96 days
Chicago Time to Permit tracker
36 days with the Department of Buildings, 60 with the applicant, as of Oct 30, 2026; a daily figure, and the page does not say which permits or which statistic it counts
Source: Illinois building code rules: local adoption, the 2025 structural baseline and the statewide energy code — City of Chicago Dept. of Buildings, Time to Permit tracker (as of Oct 30, 2026)
analysis

What the data shows

  • A city or county in Illinois is not required to adopt a building code; where none is adopted, a contract for a new home must name the residential code the builder and buyer agree on (the International Residential Code or a local code in force within 100 miles), and a new commercial building cannot be occupied until a state-qualified inspector files a certification of compliance (Illinois Capital Development Board, 2026; 815 ILCS 670/15; 20 ILCS 3105/10.09-1).

  • Since January 1, 2025, every municipal or county building code, including a home-rule city’s, must regulate structural design at least as strictly as the least restrictive International Building, Existing Building or Residential Code edition first published this year or in the previous nine, and a new code edition must be reported to the Capital Development Board at least 30 days before it takes effect (20 ILCS 3105/10.18; Public Act 103-0510, 2023).

  • The Illinois Energy Conservation Code moved to the 2024 International Energy Conservation Code with Illinois amendments on November 30, 2025; it applies to all buildings in the state, so a project must comply even where no local office enforces it, and a locally adopted stretch energy code replaces it (Illinois Capital Development Board, 2025).

  • In Chicago, new-construction permits issued in the 12 months to October 26, 2026 took a median 56 days from application to issuance, the Department of Buildings’ Time to Permit tracker read 96 days on October 30, 2026 (60 with the applicant, 36 with the department), and self-certified permits are typically issued within 10 business days after zoning approval (City of Chicago Department of Buildings and Data Portal, 2026).

how Permavia helps in illinois

Most delay accumulates before technical review

The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.

frequently asked

Illinois permitting: FAQ

Does Illinois have a statewide building code?

Not one that every town must adopt. A municipality or county is not required to adopt a building code, but since January 1, 2025 any code it does adopt must regulate structural design at least as strictly as a recent International Building, Existing Building or Residential Code edition, and that floor applies to home-rule cities too (20 ILCS 3105/10.18(e); Illinois Capital Development Board, Illinois Codes FAQ). The Illinois Energy Conservation Code (the 2024 International Energy Conservation Code with Illinois amendments, since November 30, 2025) applies to all buildings statewide, and the plumbing code is set by the Illinois Department of Public Health. Ask the local building department which editions and amendments it enforces.

Is there a deadline to issue a permit in Illinois?

No state law reviewed for this guide sets one: the state statutes on building codes set standards and reporting duties, not review deadlines, so timing is up to each city or county (20 ILCS 3105/10.18). Governor Pritzker’s housing plan, which proposed third-party inspections to speed timelines, did not advance before the spring session ended on June 1, 2026, Capitol News Illinois reported. Chicago publishes its own figures: its Time to Permit tracker read 96 days on October 30, 2026, and self-certified permits are typically issued within 10 business days after zoning approval (City of Chicago Department of Buildings, 2026).

Which code applies to a new house where there is no local building code?

The one written into the construction contract. The builder and buyer may agree on the International Residential Code or any municipal or county residential code in effect on the first day of construction within 100 miles of the home; if they don’t agree or the contract names none, the state energy code, the Illinois Department of Public Health plumbing code and the current International Residential Code apply by law (815 ILCS 670/15). The rule covers new residential construction only, not repairs to existing homes (Illinois Capital Development Board, Illinois Codes FAQ).

How long does a building permit take in Chicago?

A median 56 days from application to issuance for new construction, and about 60 days for renovations and alterations, over the 12 months to October 26, 2026 (Permavia analysis of City of Chicago Building Permits data). The Department of Buildings’ Time to Permit tracker read 96 days on October 30, 2026, 36 with the department and 60 with the applicant. Chicago routes permits through the Express Permit Program for minor work, Self-Certification, Standard Plan Review for most projects with architectural plans, and Developer Services for larger, complex projects; self-certified permits are typically issued within 10 business days after zoning approval (City of Chicago Department of Buildings, 2026).

Sources

All figures on this page are drawn from Illinois building code rules: local adoption, the 2025 structural baseline and the statewide energy code, Illinois Capital Development Board / Illinois General Assembly. A municipality or county is not required to adopt a building code. Since January 1, 2025, any municipal or county building code, including a home-rule unit’s, must regulate structural design at least as strictly as a baseline International Building, Existing Building or Residential Code edition, and a new code edition must be reported to the Capital Development Board at least 30 days before it takes effect (20 ILCS 3105/10.18, as amended by Public Act 103-0510). Where no local code exists, new homes follow the code agreed in the construction contract (815 ILCS 670/15) and new commercial buildings need a qualified inspector’s certification before occupancy (20 ILCS 3105/10.09-1). The Illinois Energy Conservation Code, the 2024 IECC with Illinois amendments, has applied statewide since November 30, 2025. cdb.illinois.gov/business/codes/illinois-codes-faq.html. Specific tables, reports, and pages are cited inline with each figure above.

The code rules and the 30-day notice are legal requirements, not measured outcomes, and no statewide data was found on how fast Illinois cities and counties review permits. The Chicago medians are Permavia’s analysis of the city’s Building Permits dataset (permits issued in the 12 months to October 26, 2026, all review paths), and the 96-day figure is one day’s reading of the city’s Time to Permit tracker, which does not define the permits or statistic counted; the two use different clocks and do not match each other. Methods differ between jurisdictions, so these figures are not directly comparable with other guides.