New York Building Permit Timelines & Delays

New York sets no statewide deadline for deciding a building permit, so how long you wait depends on the city, town, village or county that reviews your plans, and New York City runs its own codes and its own review. What changed this year is environmental review: many housing projects on previously developed land that connect to existing water and sewer no longer need the state’s environmental review at all. Outside New York City, permit applications filed since December 31, 2025 must meet the 2025 Uniform Fire Prevention and Building Code, and the state’s administration rules require each local building department to examine applications for code compliance without setting a time limit for deciding them.

Last reviewed November 12, 2026
headline figure
65.7% multifamily share of homes permitted in 2025 in buildings of five or more units, second only to Connecticut among states
what to know
New York sets no statewide deadline for deciding building permits, and New York City runs its own codes. In 2025, 65.7% of the homes the state permitted were in buildings of five or more units, second only to Connecticut among states.
data source
NYS Uniform Code (19 NYCRR) and 2025 code adoption
by the numbers

New York permitting, the figures

The key published figures for this jurisdiction — each cited to its official source.

None
Statewide permit decision deadline
Local programs must examine permit applications for compliance with the Uniform Code and Energy Code and set how long an issued permit stays valid; no time limit for deciding a permit
Source: NYS Uniform Code (19 NYCRR) and 2025 code adoption — 19 NYCRR §1203.3(a) (NY Department of State)
2025 Uniform Code
Current state building code
In effect for permit applications since Dec. 31, 2025, repealing the 2020 edition; enforced by every city, town, village and county except New York City, which adopts its own codes; the Energy Code applies statewide
Source: NYS Uniform Code (19 NYCRR) and 2025 code adoption — NY Department of State, 2025 Uniform Code adoption notice; Division of Building Standards and Codes FAQ
Suspended (July 2026 notice)
All-electric rules for new buildings
The Department of State’s latest notice, dated July 2, 2026, says the 2025 code’s limits on fossil-fuel equipment in new buildings (19 NYCRR §1240.6, Subpart 1229-2) are suspended by court order and not enforceable; it had posted no later update as of Nov. 12, 2026, so confirm the current status with the Department of State or the local building department
Source: NYS Uniform Code (19 NYCRR) and 2025 code adoption — NY Department of State, Notice of Adoption page (court update of July 2, 2026)
Up to 500 homes
Housing exempt from environmental review
On previously disturbed sites connected to existing water and sewer: 300 homes in urbanized areas outside NYC, 100 elsewhere (20 with no zoning), 250 to 500 in NYC by density; the agency has 120 days from a permit application to decide if it applies; in effect since May 26, 2026
Source: NYS Uniform Code (19 NYCRR) and 2025 code adoption — State Environmental Quality Review Act as amended by FY2027 budget, Part R; NYS DEC, SEQR Amendments; Governor’s office, May 2026
Not law
Proposed permit clock with private review
If a department estimates more than 30 business days for a residential or mixed-use permit, the applicant could hire a licensed professional and the department would have 20 business days after that report; in Senate Rules since Sept. 11, 2026 and Assembly Governmental Operations since Sept. 2, 2026
Source: NYS Uniform Code (19 NYCRR) and 2025 code adoption — S10695 / A11685 (2025–26 session), NY Senate bill pages
65.7%
Multifamily share (2025)
25,389 of 38,667 units were in buildings of 5+ units; second among states after Connecticut (66.5%)
Source: NYS Uniform Code (19 NYCRR) and 2025 code adoption — U.S. Census Bureau, Building Permits Survey, 2025 annual highlights
38,667
Housing units authorized (2025)
9th among states; down 16.9% from 46,549 in 2024; Brooklyn 6,844 and the Bronx 6,032
Source: NYS Uniform Code (19 NYCRR) and 2025 code adoption — U.S. Census Bureau, Building Permits Survey, 2025 annual highlights
25.4 days
NYC avg. filing-to-approval (FY2026)
Department of Buildings’ online filing system, all applications; up from 20.3 in FY2025; first plan review averaged 5.4 days
Source: NYS Uniform Code (19 NYCRR) and 2025 code adoption — NYC Mayor’s Management Report, FY2026
analysis

What the data shows

  • No state law or rule sets a deadline for deciding a building permit in New York: the state’s administration rules require every local building department outside New York City to examine permit applications for compliance with the Uniform Code and Energy Code, and since December 31, 2025 that means the 2025 Uniform Code, but they set no time limit for the decision (NY Department of State, 2026).

  • Housing on previously disturbed sites that connects to existing water and sewer is exempt from state environmental review since May 26, 2026, up to 300 homes in urbanized areas outside New York City, 100 elsewhere and 250 to 500 in New York City, and the reviewing agency must decide within 120 days of a permit application whether the exemption applies (NYS Department of Environmental Conservation, 2026).

  • New York permitted 38,667 homes in 2025, 9th among states and down 16.9% from 2024, and 65.7% of them were in buildings of five or more units, the second-highest share of any state after Connecticut (U.S. Census Building Permits Survey, 2025).

  • In New York City, the average time from filing to plan approval rose to 25.4 days in FY2026 from 20.3 days in FY2025, and the city says the time plans spend with the applicant for corrections is typically three times the time they spend with the Department of Buildings (NYC Mayor’s Management Report, FY2026).

how Permavia helps in new york

Most delay accumulates before technical review

The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.

frequently asked

New York permitting: FAQ

Does New York have a statewide building permit deadline?

No. The state’s administration rules (19 NYCRR Part 1203) require local building departments to examine permit applications for code compliance but set no deadline for deciding them, so timing depends on the local department (NY Department of State). A bill that would let an applicant hire a private licensed professional when a department expects to take more than 30 business days on a residential or mixed-use permit, with the department then deciding within 20 business days of that report, is in committee in both houses and is not law (S10695 / A11685, as of November 12, 2026).

Which building code applies in New York?

Outside New York City, permit applications since December 31, 2025 must meet the 2025 Uniform Code, which repealed the 2020 edition and is enforced by each city, town, village and county (NY Department of State, 2025 Uniform Code adoption notice). New York City adopts its own building codes, though the state Energy Code applies statewide. The Department of State’s latest notice on the 2025 code’s limits on fossil-fuel equipment in new buildings, dated July 2, 2026, says they are suspended by court order, and it had posted no later update as of November 12, 2026; confirm the current status with the Department of State or your local building department before designing around them.

Do New York housing projects still need environmental review?

Many no longer do. Since May 26, 2026, housing on previously disturbed sites that connects to existing water and sewer is exempt from the State Environmental Quality Review Act up to 300 homes in urbanized areas outside New York City, 100 in other areas (20 where there is no zoning) and 250 to 500 in New York City depending on density (Governor’s office; NYS DEC). The agency has 120 days from a permit application to decide whether the exemption applies, and projects still reviewed face a one-year deadline for the significance decision and two years for a final environmental impact statement, with extensions possible (NYS DEC, SEQR Amendments). Separately, since June 12, 2026, state rules exempt certain multifamily projects of no more than 10,000 square feet of floor area (NYS DEC, Part 617 notice of adoption).

How long does plan approval take in New York City?

The Department of Buildings’ average from filing to approval was 25.4 days in FY2026 (July 2025–June 2026), up from 20.3 days in FY2025, and first plan review averaged 5.4 days across all applications (NYC Mayor’s Management Report, FY2026). The city says the time plans spend with the applicant for corrections is typically three times as long as the time they spend with the Department.

Sources

All figures on this page are drawn from NYS Uniform Code (19 NYCRR) and 2025 code adoption, NY Department of State, Division of Building Standards and Codes. New York’s Uniform Fire Prevention and Building Code is enforced by every city, town, village and county except New York City, which adopts its own codes. The 2025 Uniform Code has applied to permit applications since December 31, 2025. The administration rules (19 NYCRR Part 1203) require plan examination but set no deadline for a permit decision. dos.ny.gov/notice-adoption. Specific tables, reports, and pages are cited inline with each figure above.

Most figures here are legal rules or bill status, not measured outcomes: New York publishes no statewide data on how long local building departments take. The only measured review times are New York City’s, from the Mayor’s Management Report: city fiscal-year averages across all application types, covering filing to plan approval rather than permit issuance, so they aren’t comparable with other places’ figures. Housing counts are units authorized by building permits in the U.S. Census Bureau’s 2025 annual data. Bill status is as published by the Legislature on November 12, 2026; the all-electric suspension is as stated in the Department of State’s July 2, 2026 notice, its latest as of November 12, 2026, so confirm the current status with the Department of State or the local building department.