Port Orchard Building Permit Timelines & Delays

A new house in Port Orchard can take most of a year to get from submittal to permit. The 58 new single-family permits the City issued in June and July 2026 took a median of about 10 months from the day they were submitted, and 32 of them took more than 300 days. The City’s own notice says a first plan review alone runs 4–8 weeks after staff departures, in a city that added 1,240 residents in a year and grew faster than all but three Washington cities.

Last reviewed October 28, 2026
headline figure
~10 mo median, submittal to issuance, new-home permits issued Jun–Jul 2026
what to know
The 58 new single-family permits Port Orchard issued in June and July 2026 took a median of about 10 months from submittal, while the City quotes 4–8 weeks for a first review.
data source
Port Orchard Permit Center: plan-review turnaround notice and Building Permits Issued list (June–July 2026)
by the numbers

Port Orchard permitting, the figures

The key published figures for this jurisdiction — each cited to its official source.

~10 months
Median time to a new-home permit
305 days from submittal to issuance, median of the 58 new single-family permits issued June 1 to July 31, 2026 (range 21–426 days); our count from the City’s list, which includes time with the applicant
Source: Port Orchard Permit Center: plan-review turnaround notice and Building Permits Issued list (June–July 2026) — City of Port Orchard, Building Permits Issued, Jun–Jul 2026
77-day median
New-home permits issued in July 2026
28 permits; 10 were issued within 60 days of submittal, while the 30 issued in June had a 327-day median; our count from the City’s list
Source: Port Orchard Permit Center: plan-review turnaround notice and Building Permits Issued list (June–July 2026) — City of Port Orchard, Building Permits Issued, Jun–Jul 2026
4–8 weeks
Stated first-round single-family review
The City’s stated current average as of June 9, 2026, attributed to building department staff departures; one review round, not a measured submittal-to-permit time
Source: Port Orchard Permit Center: plan-review turnaround notice and Building Permits Issued list (June–July 2026) — City of Port Orchard, Permit Center, Jun 9, 2026
219
Permits issued, June and July 2026
114 in June and 105 in July, all permit types; 58 were new single-family homes
Source: Port Orchard Permit Center: plan-review turnaround notice and Building Permits Issued list (June–July 2026) — City of Port Orchard, Building Permits Issued, Jun–Jul 2026
~$21,300
Median fees on a new-home permit
Total fees listed on the 58 new single-family permits issued June–July 2026 (range $16,388–$26,879), our count from the City’s list; the list does not break fees down by type
Source: Port Orchard Permit Center: plan-review turnaround notice and Building Permits Issued list (June–July 2026) — City of Port Orchard, Building Permits Issued, Jun–Jul 2026
20,500
Population, April 1, 2026
Up 6.44% from 19,260 in 2025, fourth fastest of Washington cities by percentage and eighth by number (+1,240), none of it from annexation
Source: Port Orchard Permit Center: plan-review turnaround notice and Building Permits Issued list (June–July 2026) — WA Office of Financial Management, April 1 estimates, Jun 29, 2026
+31.5%
Growth since the 2020 Census
From 15,587 (April 2020) to 20,500 (April 2026); our arithmetic from the state’s table
Source: Port Orchard Permit Center: plan-review turnaround notice and Building Permits Issued list (June–July 2026) — WA Office of Financial Management, April 1, 2026 population table
405 days
Kitsap County project permits, 2025
Average calendar days of review without pauses (570 with pauses) for 46 land-use project permit decisions in unincorporated Kitsap County; 40 exceeded the deadline; building permits are not counted
Source: Port Orchard Permit Center: plan-review turnaround notice and Building Permits Issued list (June–July 2026) — WA Dept. of Commerce, Permitting Performance Report 2025, Table 50
analysis

What the data shows

  • Port Orchard’s new-home permits issued in June and July 2026 took a median of about 10 months from submittal to issuance, though the two months differ sharply: the 30 issued in June had a 327-day median and the 28 issued in July a 77-day median, so a single median hides very different waits (City of Port Orchard, Building Permits Issued, 2026).

  • The City’s quoted 4–8 weeks covers only the first round of single-family plan review, the City says it has no definite time frame for when permits will be ready, and it attributes the wait to building department staff departures and a higher volume of applications (City of Port Orchard, Permit Center, 2026).

  • Port Orchard reached 20,500 residents on April 1, 2026, up 6.44% in a year and 31.5% since 2020, past 20,000, the size at which cities in Kitsap and six other counties report permit times to the state; it was below that size in the 2024 and 2025 reports and is absent from both, so no state report card covers its permits (WA Office of Financial Management, 2026; WA Department of Commerce, 2025 report).

  • Only parcels inside city limits go to the City; unincorporated lots are permitted by Kitsap County, whose 2025 land-use project permits averaged 405 days of review without pauses, with 40 of 46 decisions past deadline, a different permit type from the City’s building permits (Kitsap County DCD, 2026; WA Department of Commerce, 2025 report).

how Permavia helps in port orchard

Most delay accumulates before technical review

The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.

frequently asked

Port Orchard permitting: FAQ

How long does it take to get a building permit in Port Orchard, WA?

The City says first-round single-family plan review averaged 4–8 weeks as of June 9, 2026, that plans are reviewed in the order received, and that it has no definite time frame for issuance (City of Port Orchard, Permit Center). Measured end to end, the 58 new single-family permits issued in June and July 2026 took a median of 305 days from submittal to issuance, with July’s 28 permits at a 77-day median; that count includes time with the applicant and any resubmittals (City of Port Orchard, Building Permits Issued, June–July 2026).

Does Kitsap County or the City of Port Orchard issue my building permit?

It depends on whether the parcel is inside city limits. The City of Port Orchard’s Department of Community Development handles building and fire permits inside the City (City of Port Orchard, Community Development). Kitsap County’s Department of Community Development handles unincorporated Kitsap County, and its parcel pages flag a parcel that “is in an Incorporated City” and send you to that city (Kitsap County DCD, Incorporated Cities). The County’s office at 619 Division St. is in Port Orchard, but it does not permit City parcels.

How much are building permit fees for a new house in Port Orchard?

On the 58 new single-family permits the City issued in June and July 2026, total fees ranged from $16,388 to $26,879, with a median of about $21,300, on listed valuations of about $235,000 to $716,000 (City of Port Orchard, Building Permits Issued, June–July 2026). The list does not say which fees are included, so check the City’s fee schedules and its residential impact fee documents for your project (City of Port Orchard, Fees).

How do I schedule a building inspection in Port Orchard?

Since August 1, 2025, all inspections must be requested in the City’s SmartGov Online Public Portal; the City no longer takes inspection requests by email or phone. Requests made by 3:30 pm can be scheduled as soon as the next day (City of Port Orchard, Permit Center). The Permit Center’s phone line is 360-874-5533.

Sources

All figures on this page are drawn from Port Orchard Permit Center: plan-review turnaround notice and Building Permits Issued list (June–July 2026), City of Port Orchard, Department of Community Development. The Permit Center’s June 9, 2026 notice that staff departures put first-round single-family plan review at 4–8 weeks, plus the City’s Building Permits Issued list for June 1 to July 31, 2026, which gives each permit’s type, submitted date, issue date, valuation and total fees. Read the Permit Center notice (City of Port Orchard). Specific tables, reports, and pages are cited inline with each figure above.

Two kinds of numbers appear here. Measured: the submittal-to-issuance times and fee figures are our count of the 58 permits typed “R-SFR” (new single-family homes; model homes, ADUs and carriage houses have their own type codes and are not counted) on the City’s Building Permits Issued list for June 1 to July 31, 2026, in calendar days from the listed submitted date to the listed issue date. That span includes time waiting on applicants, resubmittals and any wait for a lot to be ready, which the list does not separate, and two months is a small sample. Permits also came in batches (16 were issued on June 18, 2026, all submitted June 27 to August 4, 2025), so a few subdivisions weigh heavily on the median; read it as about 10 months rather than a precise figure. The City posts the file as a list of permits issued in the last two months, so it can change. Target: the 4–8-week figure is the City’s stated average for a first plan review as of June 9, 2026, not a measured outcome. The Washington Department of Commerce’s 2024 and 2025 permit performance reports contain no Port Orchard data. Building permits have not been part of that state reporting since 2025, so the Kitsap County figure covers land-use project permits only and is not comparable to the City’s building permits. Corrections to the lead: the 6.4% growth is for one year (April 2025 to April 2026, 6.44% in the state’s table); the 4–8 weeks is a first-round review time, not time to permit. No City budget performance measure for permit review times could be found.