Malibu Building Permit Timelines & Delays
If you are rebuilding a Malibu home lost in the January 2025 fire, expect the permit to take about nine months, and expect the file to spend most of that time outside agency review. The City’s rebuild dashboard shows applications averaging 265 calendar days from application to permit, only 73 of them in agency review, according to undated figures the City reports to the State of California’s rebuild page (by our dating, from between August 10 and September 14, 2026; see the methodology note). By September 14, 2026 the City had issued 100 rebuild construction permits and one certificate of occupancy, after the fire destroyed 532 single-family homes and 17 multifamily buildings in the city.
Malibu permitting, the figures
The key published figures for this jurisdiction — each cited to its official source.
What the data shows
Most of a Malibu rebuild permit’s 265-day average is spent outside agency review: applications averaged 73 days in agency review, and at an October 15, 2025 council meeting City staff named plans missing required notes and numbers as a main reason applications stall; the City published architect templates to avoid corrections and cut intake from 12 steps to six (State of California, Rebuilding LA, 2026; Los Angeles Times via Governing, 2025).
Permits picked up speed but still trail planning approvals: the City went from 4 rebuild permits in October 2025, as the Los Angeles Times reported, to 25 home permits on February 4, 2026, 77 on June 26 and 100 on September 14, 2026, when it also counted 370 planning approvals and 66 projects under building plan review (City of Malibu, 2026).
A rebuild for the same use, no more than 10% larger and in substantially the same location, is exempt from a coastal development permit, and the City’s policy caps a like-for-like replacement at 110% of the prior structure’s height, bulk or square footage, with Palisades Fire rebuilds barred from extending farther seaward than the pre-fire home; moving more than 50% outside the old footprint needs a waiver or a full coastal permit (City of Malibu, Rebuild Policies, 2025).
Malibu’s sites add work before plan check: a November 2025 state executive order counts at least 700 destroyed or substantially damaged Malibu homes that relied on septic or cesspool systems, and the City’s rebuild guide calls a geotechnical engineer “a must,” with a coastal engineer also needed for homes on coastal terrain (Executive Order N-37-25, 2025; City of Malibu, 2026).
Most delay accumulates before technical review
The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.
Malibu permitting: FAQ
How long does a Palisades Fire rebuild permit take in Malibu?
Rebuild applications averaged 265 calendar days from application to permit, with 73 of those days in agency review, according to the City’s Permitting Progress Dashboard as published by the State of California (Rebuilding LA, retrieved October 28, 2026; the page gives no as-of date). The City’s stated target is 10 business days per Planning Verification review, and a rebuild development permit decision is due within 15 calendar days of a complete application; the guide states no target for building plan check (City of Malibu, Start-to-Finish Rebuilding Guide, April 2026). The first finished rebuild received its certificate of occupancy on September 14, 2026, about 11 months after its permit (City of Malibu, 2026).
Do I need a coastal development permit to rebuild my Malibu home after the fire?
Not for a like-for-like rebuild. The City treats a replacement for the same use, no more than 10% over the prior floor area, height or bulk and in substantially the same location, as exempt; a larger or relocated rebuild needs a coastal development permit, and moving more than 50% outside the prior footprint needs a de minimis waiver or a permit (City of Malibu, Start-to-Finish Rebuilding Guide, 2026; Rebuild Policies, 2025). Executive Order N-20-25, signed February 13, 2025, also suspended Coastal Act permitting for Palisades Fire rebuilds in substantially the same location and within 110% of the prior footprint and height, and makes the local agency’s approval determinative of eligibility (Office of the Governor, 2025). The Coastal Commission’s staff report on Malibu’s 2025 disaster-rebuild amendment says the orders’ exemptions apply where they conflict with the coastal plan provisions in that amendment (California Coastal Commission, 2025).
Are Malibu rebuild permit fees waived?
City fees are waived for eligible owners rebuilding a single-family home or an owner-occupied duplex lost in the Broad, Franklin or Palisades fires that was their primary residence on the fire date, for like-for-like or like-for-like plus 10% rebuilds; commercial rebuilds, other agencies’ fees and post-approval revisions are not covered. The City Council adopted the waiver as Resolution No. 25-29 on July 14, 2025; waiver applications are due by 4 p.m. on June 30, 2028, planning applications must be deemed complete by then, and building permits must be obtained by December 30, 2030. If the property sells before the certificate of occupancy, the waived fees must be repaid within 90 days (City of Malibu, Fee Waiver Program; Start-to-Finish Rebuilding Guide, 2026).
Who issues building permits in Malibu, the City or Los Angeles County?
The City of Malibu, through its Rebuild Center and Development Portal. The City adopts by reference the Los Angeles County building code as in effect on January 1, 2026, which is based on the 2025 California Building Code (Malibu Municipal Code §15.04.010, Ord. 531, January 12, 2026). Los Angeles County Fire reviews fire code and fuel modification, Waterworks District 29 sets water requirements, and Caltrans permits work on Pacific Coast Highway (City of Malibu, Start-to-Finish Rebuilding Guide, 2026). Residential rebuilds of homes destroyed or substantially damaged in the January 2025 fires, including the Palisades Fire, may follow the 2022 California building standards instead of the 2025 edition, except the State Fire Marshal’s fire and public safety rules and minimum flood-elevation standards, under Executive Order N-37-25 (in effect since November 24, 2025); the order does not name the Franklin or Broad fires (Office of the Governor, 2025).
Sources
All figures on this page are drawn from Milestone in Palisades Fire Rebuild: 100th Rebuild Permit and First Certificate of Occupancy (Sep 14, 2026), City of Malibu. City announcement reporting 100 rebuild construction permits, 370 planning approvals, 66 projects in building plan review and the first certificate of occupancy, as of September 14, 2026; supplemented by the City’s rebuild progress updates of February 5 and June 29, 2026, its Start-to-Finish Rebuilding Guide (April 2026), its Rebuild Policies (October 15, 2025) and its fee waiver program. Read the announcement (City of Malibu). Specific tables, reports, and pages are cited inline with each figure above.
Two kinds of numbers appear here. Measured: the 265-day and 73-day averages come from the City’s Permitting Progress Dashboard as republished on the State of California’s Rebuilding LA page, which says local data is updated at least monthly but gives no as-of date; it showed 94 permits issued, a count the City passed between August 10 and September 14, 2026, so the averages may lag the City’s latest counts, and the City’s own dashboard could not be read directly. The 192 days outside agency review are our subtraction, and the dashboard does not say how that time divides; it labels the 73 days “agency review” and does not say whether that includes Los Angeles County Fire or Waterworks District 29 reviews. Permit, approval and plan-review counts come from City announcements (February 5, June 29 and September 14, 2026); the October 2025 count of 4 permits and the correction and intake changes come from the Los Angeles Times. Targets: the 10-business-day Planning Verification review and 15-day rebuild permit decision are City-stated targets, not published averages. Corrections to the lead: the City counts 532 single-family homes and 17 multifamily buildings destroyed, not about 720 homes (the Times figure); Spectrum News reported 88 permits on August 4, 2026, and the 100th permit and first certificate of occupancy came on September 14, 2026. Executive Order N-37-25 replaced the building-code and solar paragraphs of Executive Order N-29-25. No order rescinding N-20-25 or N-37-25 was found as of October 28, 2026, and the Coastal Commission’s final action on Malibu’s 2025 rebuild amendment could not be confirmed, so this guide relies on the City’s current rebuild guide for the coastal exemption rules. Malibu figures are not compared with Los Angeles or Los Angeles County, whose dashboards count differently.