Portland, OR Building Permit Timelines & Delays

In Portland the first look at your plans usually comes on time; the whole trip does not. From January to September 2025 the City met its first-review goal for 93% of residential permits, up from 83% in 2021. But a new home took a median 105 to 144 business days from submittal to approval in July to September 2025, well past the City’s own goal of 65, and more than double it in July and September. Fewer homes are being permitted, about 1,400 housing units in 2025 against roughly 5,400 in 2021, and the City is now waiving system development charges on most new housing permits issued from August 15, 2025 through September 30, 2028.

Last reviewed November 2, 2026
headline figure
105–144 d Median business days from submittal to approval for a new home, July–September 2025; the City’s goal is 65
what to know
Portland meets its first-review goal for 93% of residential permits, but a new home took a median 105 to 144 business days to clear every review in July–September 2025, against a City goal of 65.
data source
Permit Improvement Quarterly Update: Third Quarter 2025
by the numbers

Portland permitting, the figures

The key published figures for this jurisdiction — each cited to its official source.

105–144 business days
Median time to approval, new home, July–September 2025
Median business days from submittal to “approved to issue”, for the report’s “Residential New Construction” category, including all mandatory and final reviews: 140 in July, 105 in August, 144 in September, against a City goal of 65; measured
Source: Permit Improvement Quarterly Update: Third Quarter 2025 — City of Portland, Permit Improvement Quarterly Update, Q3 2025 (Nov 2025)
7–15 business days
Residential first-review goals
7 for alterations, 15 for additions and new construction; commercial goals are 10 and 20; City goals, not measured times
Source: Permit Improvement Quarterly Update: Third Quarter 2025 — City of Portland, Permit Improvement Quarterly Update, Q3 2025 (Nov 2025)
93%
Residential first reviews on time, January–September 2025
Share meeting the first-review goal, up from 83% in 2021; new construction 88% (72% in 2021); commercial 95% (88% in 2021); measured
Source: Permit Improvement Quarterly Update: Third Quarter 2025 — City of Portland, Permit Improvement Quarterly Update, Q3 2025 (Nov 2025)
65%
Residential plans reviewed on schedule by every bureau, FY 2023-24
Share of residential plans that every reviewing bureau finished by its scheduled end date, up from 51% in FY 2022-23; the City’s strategic target is 85%; measured
Source: Permit Improvement Quarterly Update: Third Quarter 2025 — City of Portland, FY 2025-26 Requested Budget, PP&D performance measures
4,827
Residential building permits issued, FY 2023-24
Down from 5,126 in FY 2022-23; residential building permits, not housing units; measured
Source: Permit Improvement Quarterly Update: Third Quarter 2025 — City of Portland, FY 2025-26 Requested Budget, PP&D performance measures
About 1,400
Housing units permitted, 2025
Down from roughly 5,400 in 2021; permits issued by the City, as reported by OPB, a public news organization; OPB does not name the underlying dataset
Source: Permit Improvement Quarterly Update: Third Quarter 2025 — OPB (March 3, 2026)
976
Units exempted from system development charges, first year
Issued with the exemption through August 14, 2026; 2,871 units in all were issued or enrolled, against a City goal of 5,000 new units in three years
Source: Permit Improvement Quarterly Update: Third Quarter 2025 — City of Portland, PP&D (Oct 12, 2026)
635,109
Population, July 2025
Down 2.7% from the April 2020 estimates base of 652,466 (Census estimate)
Source: Permit Improvement Quarterly Update: Third Quarter 2025 — U.S. Census Bureau, QuickFacts (Vintage 2025)
analysis

What the data shows

  • Portland usually meets its first-review goals: from January to September 2025 the first review met its goal for 93% of residential permits and 95% of commercial permits, up from 83% and 88% in 2021 (City of Portland, Permit Improvement Quarterly Update, 2025).

  • Getting through every review takes far longer: a new home took a median 140, 105 and 144 business days from submittal to “approved to issue” in July, August and September 2025 against the City’s 65-day goal, and a new commercial building took 98 to 155 days against a goal of 71 (City of Portland, Permit Improvement Quarterly Update, 2025).

  • The gap is not new: in 2021 the City Auditor found the City had not met its timely plan review standard in the previous five years, and its follow-up at the end of 2022 said the City had been taking roughly twice as long as its stated goals (Portland City Auditor, 2021 and 2022).

  • Fewer homes are being permitted, about 1,400 housing units in 2025 against roughly 5,400 in 2021, and the City now waives system development charges on most new housing permits issued from August 15, 2025 through September 30, 2028, with 976 units exempted in the first year (OPB, 2026; City of Portland, 2026).

how Permavia helps in portland

Most delay accumulates before technical review

The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.

frequently asked

Portland permitting: FAQ

How long does it take to get a building permit in Portland, Oregon?

The City aims to finish the first review of a residential permit within 7 business days for alterations and 15 for additions and new construction (10 and 20 for commercial work), and it met that goal for 93% of residential permits from January to September 2025. Its goal for the whole trip, from submittal to “approved to issue”, is a median of 65 business days for a new home, 42 for an addition and 27 for an alteration. In July to September 2025 new homes took a median 105 to 144 business days and additions 42 to 63 (City of Portland, Permit Improvement Quarterly Update, Q3 2025). After approval the permit is issued once you pay the final fees; the City’s Permit Review Dashboard, updated every Monday, has the latest times (City of Portland, Check Permit Timelines).

Who issues building permits in Portland, OR?

Portland Permitting & Development, the City bureau that since July 1, 2024 combines the former Bureau of Development Services with the permitting teams from Environmental Services, Transportation, Water and Urban Forestry (City of Portland, July 1, 2024). Apply through Development Hub PDX (DevHub); some permit types must be sent by email, and incomplete applications are rejected; general questions go to 503-823-7300 (City of Portland, Apply for Permits). The City also issues building permits for some areas outside its limits, such as properties west and north of Portland and on Jenne Lane, while the City of Gresham covers Pleasant Valley and areas east of Gresham (Multnomah County, Service Providers).

Does Portland waive system development charges for new housing?

Yes, for now. Permits for newly created housing units and congregate living issued from August 15, 2025 through September 30, 2028 are exempt from system development charges; accessory dwelling units, caretaker quarters and transient lodging do not qualify. Within 12 months of issuance the project must pass a foundation or concrete pour inspection (or an insulation and vapor barrier inspection for a conversion), unless a construction completion guarantee is filed before the permit is issued (City of Portland, Housing SDC Exemption). Through August 14, 2026, 976 units had been issued with the exemption (City of Portland, Oct 12, 2026).

Does Oregon’s 120-day rule apply to building permits in Portland?

The 120-day rule is about land-use approvals: it applies to applications for a permit, meaning a discretionary approval of a proposed development of land, a limited land use decision or a zone change, and requires the city to take final action within 120 days of the date the application is deemed complete, or 100 days for qualifying affordable housing (ORS 227.160 and 227.178). The building permit review times on this page are the City’s published goals (City of Portland, Permit Improvement Quarterly Update, Q3 2025).

Sources

All figures on this page are drawn from Permit Improvement Quarterly Update: Third Quarter 2025, City of Portland, Portland Permitting & Development. The City’s own quarterly report (November 2025) on its building permit goals: first-review goals in business days with the share met in 2021 and in 2025 to date, and median business days from submittal to “approved to issue” against a goal for each permit type, month by month; supplemented by the City’s FY 2025-26 Requested Budget performance measures, its Clear Impact performance page, the City Auditor’s 2021 building permit review audit and 2022 follow-up, the City’s housing system development charge exemption page and first-year report (October 2026), Multnomah County’s permit service map, U.S. Census QuickFacts, and OPB reporting (2026) on housing units permitted. Read the City’s Q3 2025 permit improvement update (City of Portland). Specific tables, reports, and pages are cited inline with each figure above.

Two kinds of numbers appear here. Goals: the first-review times (7, 15, 10 and 20 business days) and the median submittal-to-approval goals (65 business days for a new home, 71 for a new commercial building) are the City’s published goals. Measured: the share of first reviews meeting the goal (2021 and January to September 2025) and the monthly medians for July to September 2025 come from the City’s quarterly report of November 2025 (its “2025 (YTD)” column, read here as January to September); the median runs from submittal to “approved to issue”, includes all mandatory and final reviews, covers only applications submitted through DevHub (not paper submittals or the Facility Permit, Process Managed and Field Issuance Remodel programs), and the report does not say whether time spent waiting on the applicant is excluded; it notes that small monthly permit counts, especially for new construction, make the medians swing. The FY 2022-23 and FY 2023-24 figures are actuals from the City’s FY 2025-26 Requested Budget; later columns in that table are targets and are not used. The 2021 and 2025 housing unit counts are as reported by OPB, which does not name its dataset; no published City table was found. No newer quarterly report was found, so the measured times stop at September 2025; the City’s performance page reports that 90% of commercial and residential permits were reviewed on time across all review rounds in FY 2025-26, down from 92% in FY 2024-25, a different measure from the first-review share above; check the City’s dashboard for current figures.