Virginia Beach Building Permit Timelines & Delays
Virginia Beach says its new-home building permits were typically approved in about 26 days in fiscal 2025, and most home additions and alterations in just over 11. How long the first review of a plan set takes depends on which city page you read: the Permits page says 15–45 business days for an online submission, while the Planning homepage and a March 2026 city report say three. Small jobs can skip the online queue: the city now reviews small residential and commercial alterations at a walk-in counter on weekdays. For a new home, plan on several weeks, and confirm the current review time with the city when you file (City of Virginia Beach, 2026).
Virginia Beach permitting, the figures
The key published figures for this jurisdiction — each cited to its official source.
What the data shows
Virginia Beach reports that its 277 permits for new homes in fiscal 2025 were typically approved in about 26 days and most of its 1,986 residential alteration and addition permits in just over 11 days, without saying whether those are calendar or business days, or averages or medians (City of Virginia Beach, 2026).
The city’s stated review time depends on the page: the Permits page says the first review of an online submission takes 15–45 business days and revisions half that, while the Planning homepage and the city’s March 2026 report say three business days (City of Virginia Beach, 2026).
Small zoning, trade and building permits can now be handled at a walk-in counter open 8 a.m. to 4:30 p.m. on weekdays, the department reported in March 2026, after a fiscal 2025 in which it issued more than 34,000 permits and completed nearly 79,000 inspections (City of Virginia Beach, 2026).
In a city of 453,737, building permits authorized 436 new housing units in 2025, 266 of them single-family homes, down from 666 in 2024, while the population fell 1.2% from April 2020 to July 2025 (U.S. Census Bureau, 2026).
Most delay accumulates before technical review
The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permavia's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.
Virginia Beach permitting: FAQ
How long does a building permit take in Virginia Beach?
The city reports that in fiscal 2025, permits for new homes were typically approved in about 26 days and most residential alterations and additions in just over 11 days (City of Virginia Beach, March 2026). For the first review of a plan set submitted online, the city’s Permits page says 15–45 business days, with revisions taking half that, while its Planning homepage says three business days, so ask the city which applies to your project. Small projects that qualify for walk-in counter review skip the online queue.
How do I apply for a building permit in Virginia Beach?
Most applications go in through Accela Citizen Access, the city’s online permitting service, which is also where you request inspections (City of Virginia Beach Planning). Small projects can be reviewed in person at the counter: residential additions, alterations and accessory structures with 500 square feet of work area or less, and commercial alterations of 2,500 square feet or less with no change of use, each with five plan pages or fewer. The Planning Department is in Building 3 at 2403 Courthouse Drive, and commercial building permits require a $200 plan review deposit (City of Virginia Beach, 2025 and 2026).
What flood and shoreline rules apply to building in Virginia Beach?
Homes in the floodplain must be elevated at least one foot above the base flood elevation; the city says the required freeboard varies by flood zone and location, and its current flood maps took effect January 16, 2015 (City of Virginia Beach, floodplain management). In the northern third of the city, which drains to the Chesapeake Bay, the Chesapeake Bay Preservation Area ordinance applies, including the state’s 100-foot buffer along tidal shores, tidal and connected wetlands and perennial streams, and a nine-member board hears requests under it (City of Virginia Beach; 9VAC25-830-80). Using or altering a coastal primary sand dune needs a permit from the city’s Wetlands Board first (Zoning Ordinance Article 16, §1603).
Does Virginia set a deadline for building permits?
No. Virginia’s Uniform Statewide Building Code says the building official examines an application “within a reasonable time after filing” and issues a compliant permit “as soon as practicable,” with no day count (13VAC5-63-100). Site plans and plats do have a clock: since July 1, 2025, a locality has 40 days to act on a site plan and 30 days on a corrected resubmission, which is deemed approved if it is not acted on in time (Code of Virginia §15.2-2259). Since July 1, 2026, localities of more than 3,500 people must report their average approval times for new residential applications each March 1, and the Department of Housing and Community Development publishes the locality reports (Code of Virginia §15.2-2209.3).
Sources
All figures on this page are drawn from Permits: building permits in the City of Virginia Beach, City of Virginia Beach Planning and Community Development Department. The department’s Permits page (counter review requirements and online review times), its Planning homepage, its residential and commercial building permit pages, its building permit statistics page, its March 11, 2026 report on FY2025 permit results, its floodplain management, Chesapeake Bay Preservation Area Board, Wetlands Board and AICUZ pages, the city’s “What is Freeboard?” handout and its October 22, 2025 hazard mitigation progress report; supplemented by the Code of Virginia (§§15.2-2259 and 15.2-2209.3), the Virginia Uniform Statewide Building Code (13VAC5-63-100), the Virginia Administrative Code (9VAC25-830-80) and U.S. Census Bureau building permit and population estimates. Read the Permits page (City of Virginia Beach Planning). Specific tables, reports, and pages are cited inline with each figure above.
The 26- and 11-day figures are the city’s own fiscal 2025 results from a March 2026 department report, which does not say whether they count calendar or business days, whether they are averages or medians, or which step ends the clock. The 15–45 and three business-day figures are city statements of expected review time, not measured results; both appeared on city pages on November 25, 2026. The city’s building permit statistics page lists average review times by permit type, which we could not read for this guide. The 40-day site plan clock and the one-foot freeboard are rules, not outcomes, and the AICUZ overlay around Naval Air Station Oceana (Zoning Ordinance Article 18) also limits what can be built in its zones. Census figures count new housing units in permits issued, not review time. Methods differ, so these numbers are not comparable across jurisdictions.
- City of Virginia Beach, Planning and Community Development: faster service report (March 11, 2026)
- City of Virginia Beach, Building Permit Statistics (average review times by permit type)
- City of Virginia Beach, Air Installation Compatible Use Zone (AICUZ)
- Virginia DHCD, Local Housing Policies (locality fee and review-time reports)